Bidder Selection Plan
Contractor selection plan (project preparation phase) for the project: Trung Hung Kindergarten
Contractor Selection Plan ID
PL2400010244-00
Publishing time
15:47 22/01/2024
Contractor selection plan name
Contractor selection plan (project preparation phase) for the project: Trung Hung Kindergarten
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
PR2400048981-00
Spending Category
Investment and Development Spending
Authority that issues the decision
Ban Quản lý dự án đầu tư xây dựng thị xã Sơn Tây
Approval ID
Quyết định số 27/QĐ-BQLDA ngày 15/01/2024
Approval Documents
Downloading files directly on the new Public Procurement System requires a computer using Windows operating system and installing Client Agent software (Linux and MacOS operating systems cannot install Client software yet). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use DauThau.info software to download files. To download, please Login or Register
Files with this icon are not supported by the public procurement system for direct download in normal mode. Visit DauThau.info and select Quick Download mode to download the file if you do not use Windows with Agent . DauThau.info supports downloading on most modern browsers and devices! In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
List of Bid:
Number of packages: 11
1. Tender package No 01: Measuring and drawing the current status map at scale 1/500
Tender/ Prequalification Notice ID
Contract execution period
150 days
Domestic/ International
Domestic
Regulatory compliance
Bidding Law
Summary of main tasks of the bid package
Measure and draw current status map at scale 1/500
Capital source details
Son Tay town budget and other legal capital sources
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
January 2024
Type of contract
All in One
Implementation location (After merge)
Implementation location (Before merge)
Ha Noi city
2. Package 02: Geological Survey
Tender/ Prequalification Notice ID
Contract execution period
45 days
Domestic/ International
Domestic
Regulatory compliance
Bidding Law
Summary of main tasks of the bid package
Geological Survey
Capital source details
Son Tay town budget and other legal capital sources
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
January 2024
Type of contract
All in One
Implementation location (After merge)
Implementation location (Before merge)
Ha Noi city
3. Package 03: Setting up the red line and providing technical assistance data
Tender/ Prequalification Notice ID
Contract execution period
120 days
Domestic/ International
Domestic
Regulatory compliance
Bidding Law
Summary of main tasks of the bid package
Establish red line demarcation and provide technical assistance data
Capital source details
Son Tay town budget and other legal capital sources
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
January 2024
Type of contract
All in One
Implementation location (After merge)
Implementation location (Before merge)
Ha Noi city
4. Bidding package No. 04: Preparation of F/S report for construction part
Tender/ Prequalification Notice ID
Contract execution period
120 days
Domestic/ International
Domestic
Regulatory compliance
Bidding Law
Summary of main tasks of the bid package
Prepare construction F/S report
Capital source details
Son Tay town budget and other legal capital sources
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
January 2024
Type of contract
All in One
Implementation location (After merge)
Implementation location (Before merge)
Ha Noi city
5. Tender package No 05: Preparation of F/S report for fire protection section
Tender/ Prequalification Notice ID
Contract execution period
120 days
Domestic/ International
Domestic
Regulatory compliance
Bidding Law
Summary of main tasks of the bid package
Prepare technical research report for fire protection section
Capital source details
Son Tay town budget and other legal capital sources
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
January 2024
Type of contract
All in One
Implementation location (After merge)
Implementation location (Before merge)
Ha Noi city
6. Package 06: Verification of the F/S report
Tender/ Prequalification Notice ID
Contract execution period
45 days
Domestic/ International
Domestic
Regulatory compliance
Bidding Law
Summary of main tasks of the bid package
Verification of the NCKT . report
Capital source details
Son Tay town budget and other legal capital sources
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
February 2024
Type of contract
All in One
Implementation location (After merge)
Implementation location (Before merge)
Ha Noi city
7. Tender package No 07: Measuring and placing landmarks for site clearance
Tender/ Prequalification Notice ID
Contract execution period
180 days
Domestic/ International
Domestic
Regulatory compliance
Bidding Law
Summary of main tasks of the bid package
Measure and set ground clearance landmarks
Capital source details
Son Tay town budget and other legal capital sources
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
January 2024
Type of contract
All in One
Implementation location (After merge)
Implementation location (Before merge)
Ha Noi city
8. Tender package No 08: Completing the map for site clearance
Tender/ Prequalification Notice ID
Contract execution period
180 days
Domestic/ International
Domestic
Regulatory compliance
Bidding Law
Summary of main tasks of the bid package
Complete the map for site clearance
Capital source details
Son Tay town budget and other legal capital sources
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
January 2024
Type of contract
All in One
Implementation location (After merge)
Implementation location (Before merge)
Ha Noi city
9. Tender package No 09: Supervision and survey
Tender/ Prequalification Notice ID
Contract execution period
45 days
Domestic/ International
Domestic
Regulatory compliance
Bidding Law
Summary of main tasks of the bid package
Survey monitoring
Capital source details
Son Tay town budget and other legal capital sources
Contractor Selection Type
Do it yourself
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
January 2024
Type of contract
All in One
Implementation location (After merge)
Implementation location (Before merge)
Ha Noi city
10. Tender package No 10: TMB planning (1/500 scale and preliminary architectural plan)
Tender/ Prequalification Notice ID
Contract execution period
120 days
Domestic/ International
Domestic
Regulatory compliance
Bidding Law
Summary of main tasks of the bid package
TMB planning (1/500 scale and preliminary architectural plan)
Capital source details
Son Tay town budget and other legal capital sources
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
January 2024
Type of contract
All in One
Implementation location (After merge)
Implementation location (Before merge)
Ha Noi city
11. Bidding package No. 11: Preparation of bidding documents, evaluation of bidding documents for consulting package to prepare technical research report
Tender/ Prequalification Notice ID
Contract execution period
75 days
Domestic/ International
Domestic
Regulatory compliance
Bidding Law
Summary of main tasks of the bid package
Prepare bidding documents, evaluate bidding documents for consulting packages to prepare technical research reports
Capital source details
Son Tay town budget and other legal capital sources
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
January 2024
Type of contract
All in One
Implementation location (After merge)
Implementation location (Before merge)
Ha Noi city
Utilities for you:
Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Contractor selection plan (project preparation phase) for the project: Trung Hung Kindergarten". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Following
Receive similar invitation to bid by email
To be one of the
first to receive email notifications of contractor selection plans similar to the "Contractor selection plan (project preparation phase) for the project: Trung Hung Kindergarten" plan as soon as they are posted,
sign up for DauThau.info's VIP 2 plan.