Contractor selection plan Project: Upgrading and developing medium and low voltage lines and substations in Bien Hoa city area in 2023

  Watching      
Find: 08:50 10/05/2024
Contractor Selection Plan ID
PL2400075478-00
Publishing time
08:49 10/05/2024
Posting Status
Published
Contractor selection plan name
Contractor selection plan Project: Upgrading and developing medium and low voltage lines and substations in Bien Hoa city area in 2023
Investment objective
- Prevent overloading of substations and low voltage lines under the management of Bien Hoa 2 Railway. - Reduce power loss on the grid. - Renovate and upgrade some old low-voltage power grids, pull new routes to prevent overloading of existing cable routes, exploit the full capacity of transformers, create low-voltage grid links of substations, increase Reliable electricity supply in Long Binh, An Binh, Long Binh Tan, Tan Hoa, Ho Nai, Tan Bien areas - Bien Hoa City - Dong Nai province.
Project management forms
The investor directly manages the project
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
PR2400021267-00
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group C
Project implementation time
2 Years
Location
Authority that issues the decision
Điện lực Biên Hòa 2
Approval date
09/05/2024
Approval ID
199/QĐ-ĐLBH2
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using the Windows operating system and needs to install Client Agent software (Linux and MacOS cannot download Client software yet). ). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use our DauThau.info.
Our system will help you download files faster, on any device without installing Client Agent.
To download, please Login or Register

File can only be downloaded on Windows computers using Agent, please see instructions here!!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
List of Bid:
Number of packages: 4
1.Bidding package: Procurement of construction materials and equipment Upgrading and developing medium and low voltage lines and substations in Bien Hoa city area in 2023
Tender/ Prequalification Notice ID
Contract execution period
300 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Goods
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Commercial loan and equity capital from Dong Nai Electricity Company Limited
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2024
Type of contract
All in One
Prequalification
No
Location
Biên Hòa City, Đồng Nai
2.Tender package No 02: Construction and installation of works to upgrade and develop medium and low voltage lines and substations in Bien Hoa city area in 2023
Tender/ Prequalification Notice ID
Contract execution period
300 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Commercial loan and equity capital from Dong Nai Electricity Company Limited
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2024
Type of contract
All in One
Prequalification
No
Location
Biên Hòa City, Đồng Nai
3.Tender package No 03: Construction supervision consultancy for upgrading and developing medium and low voltage lines and substations in Bien Hoa city area in 2023
Tender/ Prequalification Notice ID
Contract execution period
300 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Commercial loan and equity capital from Dong Nai Electricity Company Limited
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q4 2024
Type of contract
All in One
Prequalification
No
Location
Biên Hòa City, Đồng Nai
4.Tender package No 04: Consulting on auditing and finalizing the project to complete the project of upgrading and developing medium and low voltage lines and substations in Bien Hoa city area in 2023
Tender/ Prequalification Notice ID
Contract execution period
180 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Commercial loan and equity capital from Dong Nai Electricity Company Limited
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q3 2024
Type of contract
All in One
Prequalification
No
Location
Biên Hòa City, Đồng Nai

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Contractor selection plan Project: Upgrading and developing medium and low voltage lines and substations in Bien Hoa city area in 2023". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Contractor selection plan Project: Upgrading and developing medium and low voltage lines and substations in Bien Hoa city area in 2023" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 8

You did not use the site, Click here to remain logged. Timeout: 60 second