Contractor selection plan. Project: Upgrading medium and low voltage power grids and 1-phase to 3-phase substations in Bao Quang, Bau Tram, Hang Gon, Binh Loc communes, Bao Vinh, Bau Sen, Xuan Lap wards - Long Khanh city in 2024
Contractor selection plan. Project: Upgrading medium and low voltage power grids and 1-phase to 3-phase substations in Bao Quang, Bau Tram, Hang Gon, Binh Loc communes, Bao Vinh, Bau Sen, Xuan Lap wards - Long Khanh city in 2024
- Prevent wire overload, reduce power loss on low voltage grid.
- Increase the ability to develop 3-phase load.
- Ensure safe operation and continuous power supply, reducing incidents on the grid.
- Improve power quality, facilitate phase balancing for medium voltage branches.
- Meet the needs of load development to serve production and daily life for people in Bao Quang, Bau Tram, Hang Gon, Binh Loc communes, Bao Vinh, Bau Sen, Xuan Lap wards - Long Khanh city, Dong Nai province .
Downloading files directly on the new Public Procurement System requires a computer using the Windows operating system and needs to install Client Agent software (Linux and MacOS cannot download Client software yet). ). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use our DauThau.info. Our system will help you download files faster, on any device without installing Client Agent. To download, please Login or Register
QDPD KHLCNT.pdf
File can only be downloaded on Windows computers using Agent, please see instructions here!! In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
List of Bid:
Number of packages: 3
1.Tender package No 02: Construction and installation
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Contractor selection plan. Project: Upgrading medium and low voltage power grids and 1-phase to 3-phase substations in Bao Quang, Bau Tram, Hang Gon, Binh Loc communes, Bao Vinh, Bau Sen, Xuan Lap wards - Long Khanh city in 2024". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Contractor selection plan. Project: Upgrading medium and low voltage power grids and 1-phase to 3-phase substations in Bao Quang, Bau Tram, Hang Gon, Binh Loc communes, Bao Vinh, Bau Sen, Xuan Lap wards - Long Khanh city in 2024" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.