Contractor Selection Plan ID
PL2500244366-00
Publishing time
15:24 03/10/2025
Posting Status
Published
Contractor selection plan name
Contractor selection plan under the construction investment project: Repair a number of items at Agribank headquarters Vinh Linh Quang Tri Branch
Investment objective
Repair some items at Agribank headquarters of Vinh Linh Quang Tri branch to meet the working needs of the branch
Project management forms
The investor hires a project management consultant
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
PR2500050973-00
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group C
Project implementation time
3 Month
Authority that issues the decision
NGÂN HÀNG NÔNG NGHIỆP VÀ PHÁT TRIỂN NÔNG THÔN VIỆT NAM CHI NHÁNH QUẢNG TRỊ
Approval date
29/09/2025
Approval ID
Số 2412/QĐ-NHNo.QT-TH ngày 29/9/2025
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using Windows operating system and installing Client Agent software (Linux and MacOS operating systems cannot install Client software yet). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use DauThau.info software to download files.
To download, please Login or Register

Files with this icon are not supported by the public procurement system for direct download in normal mode. Visit DauThau.info and select Quick Download mode to download the file if you do not use Windows with Agent. DauThau.info supports downloading on most modern browsers and devices!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
List of Bid:
Number of packages: 4
1.Construction and repair and supply and installation of equipment
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Civil Works
Capital source details
Agribank's repair capital
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Fourth quarter, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
2.Construction supervision consultancy and installation of equipment
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
project supervision
Capital source details
Agribank's repair capital
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Fourth quarter, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
3.Project management consultancy
Tender/ Prequalification Notice ID
Contract execution period
150 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Construction project management
Capital source details
Agribank's repair capital
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Fourth quarter, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
4.Auditing and settlement consulting
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Auditing of settlements
Capital source details
Agribank's repair capital
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Fourth quarter, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Contractor selection plan under the construction investment project: Repair a number of items at Agribank headquarters Vinh Linh Quang Tri Branch". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Contractor selection plan under the construction investment project: Repair a number of items at Agribank headquarters Vinh Linh Quang Tri Branch" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 14

You did not use the site, Click here to remain logged. Timeout: 60 second