Bidder Selection Plan

Conveyor system for coal supply for Khe Cham refinery. Capacity 4.5 million tons/year

  Watching      
Find: 08:34 21/12/2019
Contractor selection plan ID
20191257882-00
Publication date
08:33 21/12/2019
Publication status
Actual notification
Contractor selection plan name
Conveyor system for coal supply for Khe Cham refinery. Capacity 4.5 million tons/year
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
20191257881-00
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Project
QD status
There has been a decision to approve the investment project
Approval date
18/12/2019
Approval ID
2133/QĐ-TKV
List of Bid:
Number of packages: 11
1.Package 6: Making a billboard to announce the planning project
Tender/ Prequalification Notice ID
Contract Period
20 days
Domestic/ International
International
Bidding method
Directly
Fields
Advise
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
Commercial loan capital of at least 80%, the rest is the owner's equity and other lawful capital sources
Contractor Selection Type
Appointment of contractors, domestic, no prequalification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2019
Contract Type
All in one
Prequalification
No
2.Tender package No 7: Planning Boundary Landmarks
Tender/ Prequalification Notice ID
Contract Period
20 days
Domestic/ International
International
Bidding method
Directly
Fields
Advise
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
Commercial loan capital of at least 80%, the rest is the owner's equity and other lawful capital sources
Contractor Selection Type
Appointment of contractors, domestic, no prequalification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2019
Contract Type
All in one
Prequalification
No
3.Tender package No 9: Measuring and drawing extracts of the current map of site clearance, scale 1/500
Tender/ Prequalification Notice ID
Contract Period
20 days
Domestic/ International
International
Bidding method
Directly
Fields
Advise
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
Commercial loan capital of at least 80%, the rest is the owner's equity and other lawful capital sources
Contractor Selection Type
Appointment of contractors, domestic, no prequalification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2019
Contract Type
All in one
Prequalification
No
4.Tender package No 10: Clearing mines
Tender/ Prequalification Notice ID
Contract Period
30 days
Domestic/ International
International
Bidding method
Directly
Fields
Advise
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
Commercial loan capital of at least 80%, the rest is the owner's equity and other lawful capital sources
Contractor Selection Type
Appointment of contractors, domestic, no prequalification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2019
Contract Type
All in one
Prequalification
No
5.Tender package No 11: Preparation of TCB-VTC - Estimation
Tender/ Prequalification Notice ID
Contract Period
20 days
Domestic/ International
International
Bidding method
Online
Fields
Advise
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
Commercial loan capital of at least 80%, the rest is the owner's equity and other lawful capital sources
Contractor Selection Type
Bidding widely, domestically, without prequalification, online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2019
Contract Type
All in one
Prequalification
No
6.Package 14: Supply and installation of conveyor equipment
Tender/ Prequalification Notice ID
Contract Period
90 days
Domestic/ International
International
Bidding method
Online
Fields
Goods
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
Commercial loan capital of at least 80%, the rest is the owner's equity and other lawful capital sources
Contractor Selection Type
Bidding widely, domestically, without prequalification, online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2020
Contract Type
All in one
Prequalification
No
7.Package 15: Supply and installation of equipment for shift house, production operation, mechanical repair, misting system, communication system and surveillance camera
Tender/ Prequalification Notice ID
Contract Period
60 days
Domestic/ International
International
Bidding method
Directly
Fields
Goods
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
Commercial loan capital of at least 80%, the rest is the owner's equity and other lawful capital sources
Contractor Selection Type
Competitive offers, domestic, no prequalification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2020
Contract Type
All in one
Prequalification
No
8.Package 16: Construction, supply and installation of substations, Construction of 35Kv lines and relocation of 6Kv lines, power lines
Tender/ Prequalification Notice ID
Contract Period
60 days
Domestic/ International
International
Bidding method
Directly
Fields
Civil Works
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
Commercial loan capital of at least 80%, the rest is the owner's equity and other lawful capital sources
Contractor Selection Type
Bidding widely, domestically, without prequalification, without online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2020
Contract Type
All in one
Prequalification
No
9.Package 17: Supervision of construction and equipment installation
Tender/ Prequalification Notice ID
Contract Period
270 days
Domestic/ International
International
Bidding method
Directly
Fields
Advise
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
Commercial loan capital of at least 80%, the rest is the owner's equity and other lawful capital sources
Contractor Selection Type
Bidding widely, domestically, without prequalification, without online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2020
Contract Type
All in one
Prequalification
No
10.Package 18: Audit of completed project QT reports
Tender/ Prequalification Notice ID
Contract Period
45 days
Domestic/ International
International
Bidding method
Online
Fields
Advise
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
Commercial loan capital of at least 80%, the rest is the owner's equity and other lawful capital sources
Contractor Selection Type
Bidding widely, domestically, without prequalification, online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2020
Contract Type
All in one
Prequalification
No
11.Tender package No 19: Construction insurance
Tender/ Prequalification Notice ID
Contract Period
270 days
Domestic/ International
International
Bidding method
Directly
Fields
Advise
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
Commercial loan capital of at least 80%, the rest is the owner's equity and other lawful capital sources
Contractor Selection Type
Appointment of contractors, domestic, no prequalification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2020
Contract Type
All in one
Prequalification
No

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Conveyor system for coal supply for Khe Cham refinery. Capacity 4.5 million tons/year". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Conveyor system for coal supply for Khe Cham refinery. Capacity 4.5 million tons/year" plan as soon as they are posted, sign up for DauThau.info's International VIP 2 plan.
Views: 395

You did not use the site, Click here to remain logged. Timeout: 60 second