Bidder Selection Plan

Dai Bi Pagoda (phase 3)

  Watching      
Find: 14:53 21/05/2019
Contractor selection plan ID
20190500060-02
Publication date
14:53 21/05/2019
Publication status
Actual notification
Contractor selection plan name
Dai Bi Pagoda (phase 3)
Bid Solicitor
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
20190500057-00
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Project
QD status
There has been a decision to approve the investment project
Approval date
17/05/2019
Approval ID
830/QĐ-UBND
Related announcements

- Change: Approval date, Approval ID, Publication date (View changes)

- Change: Notification form, Publication date (View changes)

Posted for the first time (View changes)

List of Bid:
Number of packages: 6
1.Bidding package No. 02: Consultancy on preparation of bidding documents and evaluation of bidding documents for package No. 01
Tender/ Prequalification Notice ID
Contract Period
45 days
Domestic/ International
International
Bidding method
Directly
Fields
Advise
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
District budget
Contractor Selection Type
Appointment of short-term, domestic contractors, no prequalification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q2 2019
Contract Type
All in one
Prequalification
No
2.Package 03: Consultancy on appraisal of bidding documents and contractor selection results for package No. 01
Tender/ Prequalification Notice ID
Contract Period
45 days
Domestic/ International
International
Bidding method
Directly
Fields
Advise
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
District budget
Contractor Selection Type
Appointment of short-term, domestic contractors, no prequalification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q2 2019
Contract Type
All in one
Prequalification
No
3.Tender package No 04: Construction Supervision Consultant
Tender/ Prequalification Notice ID
Contract Period
240 days
Domestic/ International
International
Bidding method
Directly
Fields
Advise
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
District budget
Contractor Selection Type
Appointment of short-term, domestic contractors, no prequalification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q2 2019
Contract Type
All in one
Prequalification
No
4.Tender package No 05: Construction insurance
Tender/ Prequalification Notice ID
Contract Period
240 days
Domestic/ International
International
Bidding method
Directly
Fields
Non-consulting
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
District budget
Contractor Selection Type
Appointment of short-term, domestic contractors, no prequalification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q2 2019
Contract Type
All in one
Prequalification
No
5.Package 06: Audit consulting
Tender/ Prequalification Notice ID
Contract Period
30 days
Domestic/ International
International
Bidding method
Directly
Fields
Advise
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
District budget
Contractor Selection Type
Appointment of short-term, domestic contractors, no prequalification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q2 2019
Contract Type
All in one
Prequalification
No
6.Package 01: Construction and installation and general items
Tender/ Prequalification Notice ID
Contract Period
240 days
Domestic/ International
International
Bidding method
Online
Fields
Civil Works
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
District budget
Contractor Selection Type
Bidding widely, domestically, without prequalification, online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q2 2019
Contract Type
All in one
Prequalification
No

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Dai Bi Pagoda (phase 3)". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Dai Bi Pagoda (phase 3)" plan as soon as they are posted, sign up for DauThau.info's International VIP 2 plan.
Views: 76

You did not use the site, Click here to remain logged. Timeout: 60 second