Contractor selection plan ID
20200415365-01
Publication date
15:22 15/04/2020
Publication status
Actual notification
Contractor selection plan name
Decision approving the cost estimate and project contractor selection plan: Installing CAMERA in Van Quan district
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Total investment
To view full information, please Login or Register
Spending Category
Mandatory spending activities
QD status
There has been a decision to approve the investment project
Approval date
07/04/2020
Approval ID
1009/QĐ-UBND
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using Windows operating system and installing Client Agent software (Linux and MacOS operating systems cannot install Client software yet). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use DauThau.info software to download files.
To download, please Login or Register

Related announcements

- Change: Notification form, Publication date (View changes)

Posted for the first time (View changes)

List of Bid:
Number of packages: 1
1.Install a camera in Van Quan district
Tender/ Prequalification Notice ID
Contract Period
60 days
Domestic/ International
International
Bidding method
Online
Fields
Goods
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
State budget 2020 is assigned in Decision No. 137/QD-UBND dated January 21, 2020
Contractor Selection Type
Brief competitive offer, domestic, no prequalification, online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q2 2020
Contract Type
All in one
Prequalification
No
Implementation location

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Decision approving the cost estimate and project contractor selection plan: Installing CAMERA in Van Quan district". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Decision approving the cost estimate and project contractor selection plan: Installing CAMERA in Van Quan district" plan as soon as they are posted, sign up for DauThau.info's International VIP 2 plan.
Views: 150

You did not use the site, Click here to remain logged. Timeout: 60 second