Bidder Selection Plan

Decision on approving the contractor selection plan for Thanh Binh Primary School Construction project

  Watching            
Project Contractor selection plan Prequalification Notice Result of opening prequalification/interest Prequalification Result Tender notice Bid Opening Result Bid award
Find: 09:47 20/09/2024
Contractor Selection Plan ID
PL2400205133-01
Publishing time
09:46 20/09/2024
Posting Status
Published
Contractor selection plan name
Decision on approving the contractor selection plan for Thanh Binh Primary School Construction project
Investment objective
In order to improve the quality of comprehensive education, improve training efficiency, and contribute to completing the educational development goals set by the town; Ensure physical facilities are solidified and modernized. Building a learning environment that meets the best conditions for students, creating the best working conditions for officials and teachers
Project management forms
The investor directly manages the project
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
PR2400053190-00
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group C
Project implementation time
3 Years
Authority that issues the decision
Ủy ban nhân dân thị xã Giá Rai
Approval date
19/09/2024
Approval ID
3723/QĐ-UBND
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using Windows operating system and installing Client Agent software (Linux and MacOS operating systems cannot install Client software yet). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use DauThau.info software to download files.
To download, please Login or Register

Files with this icon are not supported by the public procurement system for direct download in normal mode. Visit DauThau.info and select Quick Download mode to download the file if you do not use Windows with Agent. DauThau.info supports downloading on most modern browsers and devices!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
Related announcements

- Change: Publication date (View changes)

- Change: Publication date, Bidding package information (View changes)

Posted for the first time (View changes)

List of Bid:
Number of packages: 7
1.Package 06: Clearing mines
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Clearing mines
Capital source details
Land use fee revenue in 2022, balanced town budget source and additional provincial budget source
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
All in One
Implementation location
Giá Rai Town, Province Bạc Liêu
Implementation location (After merge)
Prequalification
No
2.Tender package No 07: Geological survey consulting (Project implementation phase)
Tender/ Prequalification Notice ID
Contract execution period
25 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Geological surveys serve design consulting and construction drawings
Capital source details
Land use fee revenue in 2022, balanced town budget source and additional provincial budget source
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2024
Type of contract
All in One
Implementation location
Giá Rai Town, Province Bạc Liêu
Implementation location (After merge)
Prequalification
No
3.Tender package No 08: Consulting and supervision of geological survey work (Project implementation phase)
Tender/ Prequalification Notice ID
Contract execution period
25 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Supervision of geological survey work (Project implementation phase)
Capital source details
Land use fee revenue in 2022, balanced town budget source and additional provincial budget source
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2024
Type of contract
All in One
Implementation location
Giá Rai Town, Province Bạc Liêu
Implementation location (After merge)
Prequalification
No
4.Bidding package No. 09: Consulting on preparing bidding documents, evaluating bid documents - Construction design consulting bidding package
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Prepare bidding documents, evaluate bids - Construction design consulting bidding package
Capital source details
Land use fee revenue in 2022, balanced town budget source and additional provincial budget source
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
All in One
Implementation location
Giá Rai Town, Province Bạc Liêu
Implementation location (After merge)
Prequalification
No
5.Bidding package No. 10: Consulting on construction drawing design and estimates
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Design construction drawings, cost estimates
Capital source details
Land use fee revenue in 2022, balanced town budget source and additional provincial budget source
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q4 2024
Type of contract
All in One
Implementation location
Giá Rai Town, Province Bạc Liêu
Implementation location (After merge)
Prequalification
Yes
6.Tender package No 11: Equipment price appraisal consulting
Tender/ Prequalification Notice ID
Contract execution period
15 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Equipment cost appraisal
Capital source details
Land use fee revenue in 2022, balanced town budget source and additional provincial budget source
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2024
Type of contract
All in One
Implementation location
Giá Rai Town, Province Bạc Liêu
Implementation location (After merge)
Prequalification
No
7.Tender package No 12: Consulting on verification of construction drawings and estimates
Tender/ Prequalification Notice ID
Contract execution period
20 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Verification of construction drawings and estimates
Capital source details
Land use fee revenue in 2022, balanced town budget source and additional provincial budget source
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2024
Type of contract
All in One
Implementation location
Giá Rai Town, Province Bạc Liêu
Implementation location (After merge)
Prequalification
No

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Decision on approving the contractor selection plan for Thanh Binh Primary School Construction project". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Decision on approving the contractor selection plan for Thanh Binh Primary School Construction project" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 15

You did not use the site, Click here to remain logged. Timeout: 60 second