Bidder Selection Plan

Decision on approving the plan to select contractors to carry out a number of construction, consulting, and non-consulting packages under the Investment Project to build Kenh Vang Bridge and the road leading to both ends of the bridge, connecting the two provinces of Bac Ninh and Hai Duong

  Watching      
Find: 22:40 22/07/2024
Contractor Selection Plan ID
PL2400141885-01
Publishing time
22:32 22/07/2024
Posting Status
Published
Contractor selection plan name
Decision on approving the plan to select contractors to carry out a number of construction, consulting, and non-consulting packages under the Investment Project to build Kenh Vang Bridge and the road leading to both ends of the bridge, connecting the two provinces of Bac Ninh and Hai Duong
Investment objective
The investment in construction of the Kenh Vang bridge project and the path at both ends of the bridge connecting the two provinces of Bac Ninh and Hai Duong contributes to completing the traffic infrastructure and technical infrastructure, connecting the two provinces of Bac Ninh and Hai Duong. , creating a premise to promote trade in goods and socio-economic development for localities
Project management forms
The investor directly manages the project
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
PR2400037743-00
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group B
Project implementation time
6 Years
Authority that issues the decision
Uỷ ban nhân dân tỉnh Bắc Ninh
Approval date
18/07/2024
Approval ID
868/QĐ-UBND
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using the Windows operating system and needs to install Client Agent software (Linux and MacOS cannot download Client software yet). ). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use our DauThau.info.
Our system will help you download files faster, on any device without installing Client Agent.
To download, please Login or Register

File can only be downloaded on Windows computers using Agent, please see instructions here!!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
Related announcements

- Change: Publication date, Bidding package information (View changes)

Posted for the first time (View changes)

List of Bid:
Number of packages: 31
1.Tender package No 08: Survey, prepare technical construction plans, estimate for bomb, mine and explosive material clearance
Tender/ Prequalification Notice ID
Contract execution period
20 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
According to Decision No. 771/QD-UBND dated June 24, 2024 of the Chairman of Bac Ninh Provincial People's Committee
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
All in One
Prequalification
No
Location
Gia Bình District, Bắc Ninh
2.Package 09: Clearing bombs, mines and explosives
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
According to Decision No. 771/QD-UBND dated June 24, 2024 of the Chairman of Bac Ninh Provincial People's Committee
Contractor Selection Type
Specify reference
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
All in One
Prequalification
No
Location
Gia Bình District, Bắc Ninh
3.Tender package No 10: Construction supervision consultancy for Tender package No 9
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
According to Decision No. 771/QD-UBND dated June 24, 2024 of the Chairman of Bac Ninh Provincial People's Committee
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
All in One
Prequalification
No
Location
Gia Bình District, Bắc Ninh
4.Bidding package No. 11: Consulting on preparing request documents and evaluating proposal documents for bidding package No. 9
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
According to Decision No. 771/QD-UBND dated June 24, 2024 of the Chairman of Bac Ninh Provincial People's Committee
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
All in One
Prequalification
No
Location
Gia Bình District, Bắc Ninh
5.Bidding package No. 12: Consulting on appraisal of request documents, appraisal of contractor selection results for bidding package No. 9
Tender/ Prequalification Notice ID
Contract execution period
20 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
According to Decision No. 771/QD-UBND dated June 24, 2024 of the Chairman of Bac Ninh Provincial People's Committee
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
All in One
Prequalification
No
Location
Gia Bình District, Bắc Ninh
6.Bidding package No. 13: Consulting on price appraisal of equipment, supplies and construction materials
Tender/ Prequalification Notice ID
Contract execution period
120 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
According to Decision No. 771/QD-UBND dated June 24, 2024 of the Chairman of Bac Ninh Provincial People's Committee
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
All in One
Prequalification
No
Location
Gia Bình District, Bắc Ninh
7.Tender package No 14: Construction of Kenh Vang bridge and route section from the project's starting point Km0+00 to Km6+625.44 (in Gia Binh district, Luong Tai district, Bac Ninh province and Nam Sach district, Hai Duong province )
Tender/ Prequalification Notice ID
Contract execution period
30 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
According to Decision No. 771/QD-UBND dated June 24, 2024 of the Chairman of Bac Ninh Provincial People's Committee
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
According to adjusted unit price
Prequalification
No
Location
Gia Bình District, Bắc Ninh
8.Tender package No 15: Construction of route section from Km6+625.44 to Km13+396.23 (in Nam Sach district, Hai Duong province)
Tender/ Prequalification Notice ID
Contract execution period
30 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
According to Decision No. 771/QD-UBND dated June 24, 2024 of the Chairman of Bac Ninh Provincial People's Committee
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
According to adjusted unit price
Prequalification
No
Location
Nam Sách District, Hải Dương
9.Bidding package No. 16: Consulting on preparing bidding documents and evaluating bid documents for bidding packages No. 14 and 15
Tender/ Prequalification Notice ID
Contract execution period
130 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
According to Decision No. 771/QD-UBND dated June 24, 2024 of the Chairman of Bac Ninh Provincial People's Committee
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
All in One
Prequalification
No
Location
Gia Bình District, Bắc Ninh
10.Bidding package No. 17: Consulting on appraisal of bidding documents, appraisal of contractor selection results for bidding packages No. 14 and 15
Tender/ Prequalification Notice ID
Contract execution period
40 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
According to Decision No. 771/QD-UBND dated June 24, 2024 of the Chairman of Bac Ninh Provincial People's Committee
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
All in One
Prequalification
No
Location
Gia Bình District, Bắc Ninh
11.Tender package No 18: Construction supervision consulting for package No. 14
Tender/ Prequalification Notice ID
Contract execution period
30 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
According to Decision No. 771/QD-UBND dated June 24, 2024 of the Chairman of Bac Ninh Provincial People's Committee
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q3 2024
Type of contract
All in One
Prequalification
No
Location
Gia Bình District, Bắc Ninh
12.Tender package No 19: Construction supervision consulting for package No. 15
Tender/ Prequalification Notice ID
Contract execution period
30 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
According to Decision No. 771/QD-UBND dated June 24, 2024 of the Chairman of Bac Ninh Provincial People's Committee
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q3 2024
Type of contract
All in One
Prequalification
No
Location
Nam Sách District, Hải Dương
13.Bidding package No. 20: Consulting on preparing bidding documents and evaluating bid documents for bidding packages No. 18 and 19
Tender/ Prequalification Notice ID
Contract execution period
120 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
According to Decision No. 771/QD-UBND dated June 24, 2024 of the Chairman of Bac Ninh Provincial People's Committee
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
All in One
Prequalification
No
Location
Lương Tài District, Bắc Ninh
14.Bidding package No. 21: Consulting on appraisal of bidding documents, appraisal of contractor selection results for bidding packages No. 18 and 19
Tender/ Prequalification Notice ID
Contract execution period
40 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
According to Decision No. 771/QD-UBND dated June 24, 2024 of the Chairman of Bac Ninh Provincial People's Committee
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
All in One
Prequalification
No
Location
Gia Bình District, Bắc Ninh
15.Tender package No 22: Consulting on quality inspection of bored piles and driven piles for packages No. 14, 15
Tender/ Prequalification Notice ID
Contract execution period
30 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
According to Decision No. 771/QD-UBND dated June 24, 2024 of the Chairman of Bac Ninh Provincial People's Committee
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q3 2024
Type of contract
All in One
Prequalification
No
Location
Gia Bình District, Bắc Ninh
16.Bidding package No. 23: Consulting on preparing bidding documents and evaluating bid documents for bidding package No. 22
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
According to Decision No. 771/QD-UBND dated June 24, 2024 of the Chairman of Bac Ninh Provincial People's Committee
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
All in One
Prequalification
No
Location
Gia Bình District, Bắc Ninh
17.Bidding package No. 24: Consulting on appraisal of bidding documents, appraisal of contractor selection results for bidding package No. 22
Tender/ Prequalification Notice ID
Contract execution period
20 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
According to Decision No. 771/QD-UBND dated June 24, 2024 of the Chairman of Bac Ninh Provincial People's Committee
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
All in One
Prequalification
No
Location
Gia Bình District, Bắc Ninh
18.Tender package No 25: Consulting on setting up environmental monitoring and supervision tasks during the construction process
Tender/ Prequalification Notice ID
Contract execution period
20 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
According to Decision No. 771/QD-UBND dated June 24, 2024 of the Chairman of Bac Ninh Provincial People's Committee
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
All in One
Prequalification
No
Location
Gia Bình District, Bắc Ninh
19.Tender package No 26: Consulting on environmental monitoring and supervision during construction
Tender/ Prequalification Notice ID
Contract execution period
30 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
According to Decision No. 771/QD-UBND dated June 24, 2024 of the Chairman of Bac Ninh Provincial People's Committee
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q3 2024
Type of contract
All in One
Prequalification
No
Location
Gia Bình District, Bắc Ninh
20.Bidding package No. 27: Consulting on preparing bidding documents and evaluating bid documents for bidding package No. 26
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
According to Decision No. 771/QD-UBND dated June 24, 2024 of the Chairman of Bac Ninh Provincial People's Committee
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
All in One
Prequalification
No
Location
Gia Bình District, Bắc Ninh
21.Bidding package No. 28: Consulting on appraisal of bidding documents, appraisal of contractor selection results for bidding package No. 26
Tender/ Prequalification Notice ID
Contract execution period
20 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
According to Decision No. 771/QD-UBND dated June 24, 2024 of the Chairman of Bac Ninh Provincial People's Committee
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
All in One
Prequalification
No
Location
Gia Bình District, Bắc Ninh
22.Package number 29: Construction insurance for package number 14
Tender/ Prequalification Notice ID
Contract execution period
42 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
According to Decision No. 771/QD-UBND dated June 24, 2024 of the Chairman of Bac Ninh Provincial People's Committee
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
By percentage
Prequalification
No
Location
Gia Bình District, Bắc Ninh
23.Package number 30: Construction insurance for package number 15
Tender/ Prequalification Notice ID
Contract execution period
42 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
According to Decision No. 771/QD-UBND dated June 24, 2024 of the Chairman of Bac Ninh Provincial People's Committee
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
By percentage
Prequalification
No
Location
Gia Bình District, Bắc Ninh
24.Bidding package No. 31: Consulting on preparing bidding documents and evaluating bid documents for bidding packages No. 29 and No. 30
Tender/ Prequalification Notice ID
Contract execution period
120 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
According to Decision No. 771/QD-UBND dated June 24, 2024 of the Chairman of Bac Ninh Provincial People's Committee
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
All in One
Prequalification
No
Location
Lương Tài District, Bắc Ninh
25.Bidding package No. 32: Consulting on appraisal of bidding documents, appraisal of contractor selection results for bidding packages No. 29 and No. 30
Tender/ Prequalification Notice ID
Contract execution period
40 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
According to Decision No. 771/QD-UBND dated June 24, 2024 of the Chairman of Bac Ninh Provincial People's Committee
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
All in One
Prequalification
No
Location
Gia Bình District, Bắc Ninh
26.Tender package No 33: Ensuring waterway traffic safety during construction
Tender/ Prequalification Notice ID
Contract execution period
30 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
According to Decision No. 771/QD-UBND dated June 24, 2024 of the Chairman of Bac Ninh Provincial People's Committee
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
All in One
Prequalification
No
Location
Gia Bình District, Bắc Ninh
27.Bidding package No. 34: Consulting on preparing bidding documents and evaluating bid documents for bidding package No. 33
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
According to Decision No. 771/QD-UBND dated June 24, 2024 of the Chairman of Bac Ninh Provincial People's Committee
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
All in One
Prequalification
No
Location
Gia Bình District, Bắc Ninh
28.Bidding package No. 35: Consulting on appraisal of bidding documents, appraisal of contractor selection results for bidding package No. 33
Tender/ Prequalification Notice ID
Contract execution period
20 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
According to Decision No. 771/QD-UBND dated June 24, 2024 of the Chairman of Bac Ninh Provincial People's Committee
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
All in One
Prequalification
No
Location
Gia Bình District, Bắc Ninh
29.Bidding package No. 36: Audit of final settlement report
Tender/ Prequalification Notice ID
Contract execution period
30 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
According to Decision No. 771/QD-UBND dated June 24, 2024 of the Chairman of Bac Ninh Provincial People's Committee
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q3 2024
Type of contract
All in One
Prequalification
No
Location
Gia Bình District, Bắc Ninh
30.Bidding package No. 37: Consulting on preparing bidding documents and evaluating bid documents for bidding package No. 36
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
According to Decision No. 771/QD-UBND dated June 24, 2024 of the Chairman of Bac Ninh Provincial People's Committee
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
All in One
Prequalification
No
Location
Gia Bình District, Bắc Ninh
31.Bidding package No. 38: Consulting on appraisal of bidding documents, appraisal of contractor selection results for bidding package No. 36
Tender/ Prequalification Notice ID
Contract execution period
20 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
According to Decision No. 771/QD-UBND dated June 24, 2024 of the Chairman of Bac Ninh Provincial People's Committee
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
All in One
Prequalification
No
Location
Gia Bình District, Bắc Ninh

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Decision on approving the plan to select contractors to carry out a number of construction, consulting, and non-consulting packages under the Investment Project to build Kenh Vang Bridge and the road leading to both ends of the bridge, connecting the two provinces of Bac Ninh and Hai Duong". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Decision on approving the plan to select contractors to carry out a number of construction, consulting, and non-consulting packages under the Investment Project to build Kenh Vang Bridge and the road leading to both ends of the bridge, connecting the two provinces of Bac Ninh and Hai Duong" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 82

Greeting
Greeting,
You are not logged in, please log in to use our various functions for members.

You can use your account on DauThau.info to log in to Dauthau.Net, and vice versa!

If you are still not our member, please sign up.

Only 5 minutes and absolutely free! Your account can be use on all over our ecosystem, including DauThau.info and DauThau.Net.

Search for bid information
Click for advanced search
Statistical
  • 8492 Projects are waiting for contractors
  • 1040 Tender notices posted in the last 24 hours
  • 1305 Contractor selection plan posted in the last 24 hours
  • 25342 Tender notices posted in the past month
  • 39400 Contractor selection plan posted in the last month
Consultants are supporting you
You are not logged in.
To view information, please Login or Register if you do not have an account.
Signing up is simple and completely free.
You did not use the site, Click here to remain logged. Timeout: 60 second