Bidder Selection Plan

Decision to approve additional contractor selection plan Subproject 3: Improving urban infrastructure in Hoang Mai, Hoang Mai town, Nghe An province, under the project "Improving urban infrastructure to minimizing the impact of climate change for 04 North Central coastal provinces" using loans from the French Development Agency.

  Watching      
Find: 15:07 02/10/2023
Contractor Selection Plan ID
PL2200021691-03
Publishing time
14:47 02/10/2023
Posting Status
Published
Contractor selection plan name
Decision to approve additional contractor selection plan Subproject 3: Improving urban infrastructure in Hoang Mai, Hoang Mai town, Nghe An province, under the project "Improving urban infrastructure to minimizing the impact of climate change for 04 North Central coastal provinces" using loans from the French Development Agency.
Investment objective
In order to minimize the impact of climate change on Hoang Mai town
Project management forms
The investor directly manages the project
Using ODA capital?
Have
Funding source
ODA capital
Project number
PR2200016097-00
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group B
Project implementation time
5 Years
Authority that issues the decision
UBND tỉnh Nghệ An
Approval date
31/08/2023
Approval ID
2738/QĐ-UBND
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using Windows operating system and installing Client Agent software (Linux and MacOS operating systems cannot install Client software yet). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use DauThau.info software to download files.
To download, please Login or Register

Files with this icon are not supported by the public procurement system for direct download in normal mode. Visit DauThau.info and select Quick Download mode to download the file if you do not use Windows with Agent. DauThau.info supports downloading on most modern browsers and devices!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
Related announcements

- Change: Filter name, Lowest bid price, Approval date, Approval ID, Publication date, Bidding package information (View changes)

- Change: Lowest bid price, Approval ID, Publication date, Bidding package information (View changes)

- Change: Publication date, Bidding package information (View changes)

Posted for the first time (View changes)

List of Bid:
Number of packages: 26
1.Investigating package: Investigating the current status of forests and forestry land to serve the purpose of converting forests and forestry land to implementing projects under Subproject 3: Improving urban infrastructure in Hoang Mai, town Hoang Mai, Nghe An province, under the project "Improving urban infrastructure to minimize the impact of climate change for 04 North Central coastal provinces" using loans from the French Development Agency
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
- Loan: 24,104,000 EUR (equivalent to 633,260,288 million VND) - Non-refundable aid: EUR 1 million (equivalent to VND 26,272 million) - Reciprocal capital: 167,416.215 million VND (equivalent to 6,372,420 EUR)
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
September 2023
Type of contract
All in One
Prequalification
No
Implementation location
2.GS1 tender package: Consulting and supervision of package XL1
Tender/ Prequalification Notice ID
Contract execution period
24 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
- Loan capital 24,104,000 EUR (equivalent to 633,260,288 million VND) - Non-refundable aid: EUR 1 million (equivalent to VND 26,272 million) - Reciprocal capital: 167,416.215 million VND (equivalent to 6,372,420 EUUR)
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q4 2022
Type of contract
All in One
Prequalification
No
Implementation location
3.Package BH7: construction insurance package XL7
Tender/ Prequalification Notice ID
Contract execution period
24 months
Domestic/ International
Domestic
Bidding method
Directly
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
- Loan: 24,104,000 EUR (equivalent to 633,260,288 million VND) - Non-refundable aid: EUR 1 million (equivalent to VND 26,272 million) - Reciprocal capital: 167,416.215 million VND (equivalent to 6,372,420 EUR)
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2023
Type of contract
All in One
Prequalification
No
Implementation location
4.Package BH2: Construction insurance package number XL2
Tender/ Prequalification Notice ID
Contract execution period
24 months
Domestic/ International
Domestic
Bidding method
Directly
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
- Loan: 24,104,000 EUR (equivalent to 633,260,288 million VND) - Non-refundable aid: EUR 1 million (equivalent to VND 26,272 million) - Reciprocal capital: 167,416.215 million VND (equivalent to 6,372,420 EUR)
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2023
Type of contract
All in One
Prequalification
No
Implementation location
5.Package BH3: Construction insurance package XL3
Tender/ Prequalification Notice ID
Contract execution period
24 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
- Loan: 24,104,000 EUR (equivalent to 633,260,288 million VND) - Non-refundable aid: EUR 1 million (equivalent to VND 26,272 million) - Reciprocal capital: 167,416.215 million VND (equivalent to 6,372,420 EUR)
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q2 2023
Type of contract
All in One
Prequalification
No
Implementation location
6.Package BH4: Construction insurance package XL4
Tender/ Prequalification Notice ID
Contract execution period
24 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
- Loan: 24,104,000 EUR (equivalent to 633,260,288 million VND) - Non-refundable aid: EUR 1 million (equivalent to VND 26,272 million) - Reciprocal capital: 167,416.215 million VND (equivalent to 6,372,420 EUR)
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q2 2023
Type of contract
All in One
Prequalification
No
Implementation location
7.GS5 bidding package: Consulting and supervision of package XL5
Tender/ Prequalification Notice ID
Contract execution period
24 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Capital source details
- Loan: 24,104,000 EUR (equivalent to 633,260,288 million VND) - Non-refundable aid: EUR 1 million (equivalent to VND 26,272 million) - Reciprocal capital: 167,416.215 million VND (equivalent to 6,372,420 EUR)
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q4 2022
Type of contract
All in One
Prequalification
No
Implementation location
8.Package XL1: Road to avoid flooding, section Km0+00 - Km2+140; Route No. 1 (Upgrading National Highway 48E) section Km0+00 - Km2+279; Connection route No. 2 (Upgrading the rescue road connecting National Highway 1A to Ho Vuc Mau) section Km0+00 - Km3+550; lighting electricity.
Tender/ Prequalification Notice ID
Contract execution period
24 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
- Loan: 24,104,000 EUR (equivalent to 633,260,288 million VND) - Non-refundable aid: EUR 1 million (equivalent to VND 26,272 million) - Reciprocal capital 167,416.215 million VND (equivalent to 6,372,420 EUR)
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q4 2022
Type of contract
According to adjusted unit price
Prequalification
No
Implementation location
9.GS3 bidding package: Consulting and supervision of XL3 package
Tender/ Prequalification Notice ID
Contract execution period
24 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
- Loan capital: 24,104,000 EUR (equivalent to 633,260,288 million VND). - Non-refundable aid: EUR 1 million (equivalent to VND 26,272 million) - Reciprocal capital: 167,416.215 million VND (equivalent to 6,372,420 EUR .)
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q4 2022
Type of contract
All in One
Prequalification
No
Implementation location
10.Package BH6: Construction insurance package XL6
Tender/ Prequalification Notice ID
Contract execution period
24 months
Domestic/ International
Domestic
Bidding method
Directly
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
- Loan: 24,104,000 EUR (equivalent to 633,260,288 million VND) - Non-refundable aid: EUR 1 million (equivalent to VND 26,272 million) - Reciprocal capital: 167,416.215 million VND (equivalent to 6,372,420 EUR)
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2023
Type of contract
All in One
Prequalification
No
Implementation location
11.GS4 package: Consulting and supervision of XL4 package
Tender/ Prequalification Notice ID
Contract execution period
24 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
- Loan: 24,104,000 EUR (equivalent to 633,260,288 million VND) - Non-refundable aid: EUR 1 million (equivalent to VND 26,272 million) - Reciprocal capital: 167,416.215 million VND (equivalent to 6,372,420 EUR)
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q4 2022
Type of contract
All in One
Prequalification
No
Implementation location
12.Package XL2: Road to avoid flooding, section Km2+140 - Km7+049; Embankment route No. 2: Hoang Mai river anti-erosion embankment combined with the rescue road on the left bank of Hoang Mai river
Tender/ Prequalification Notice ID
Contract execution period
24 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
- Loan: 24,104,000 EUR (equivalent to 633,260,288 million VND) - Non-refundable aid: EUR 1 million (equivalent to VND 26,272 million) - Reciprocal capital: 167,416.215 million VND (equivalent to 6,372,420 EUR)
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q4 2022
Type of contract
According to adjusted unit price
Prequalification
No
Implementation location
13.GS6 package: Consulting and supervision of package XL6
Tender/ Prequalification Notice ID
Contract execution period
24 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Capital source details
- Loan: 24,104,000 EUR (equivalent to 633,260,288 million VND) - Non-refundable support capital: 1 million EUR (equivalent to 26,272 million VND) - Reciprocal capital: 167,416.215 million VND (equivalent to 6,372,420 EUR)
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q4 2022
Type of contract
All in One
Prequalification
No
Implementation location
14.Package XL4: Hoang Mai 3 Bridge at Km0+795.91; Trich Bridge at Km3+935.84; Vuc Mau Bridge at Km4+925.48; Retaining wall of Hoang Mai bridge 3
Tender/ Prequalification Notice ID
Contract execution period
24 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
- Loan capital: 24,104,000 EUR (equivalent to 633,260,288 million VND). - Non-refundable aid: 1 million EUR (equivalent to 26,272 million VND). - Reciprocal capital: 167,416.215 million VND (equivalent to 6,372,420 EUR
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q4 2022
Type of contract
According to adjusted unit price
Prequalification
No
Implementation location
15.GS7 package: Consulting and supervision of package XL7
Tender/ Prequalification Notice ID
Contract execution period
24 months
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
- Loan capital: 24,104,000 EUR (equivalent to 633,260,288 million VND) - Non-refundable support capital: 1 million EUR (equivalent to 26,272 million VND) - Reciprocal capital: 167,416.215 million VND (equivalent to 6,372,420 EUR))
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2023
Type of contract
All in One
Prequalification
No
Implementation location
16.Package XL7: The entire service pipeline and pumping station system
Tender/ Prequalification Notice ID
Contract execution period
24 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
- Loan: 24,104,000 EUR (equivalent to 633,260,288 million VND) - Non-refundable aid: EUR 1 million (equivalent to VND 26,272 million) - Reciprocal capital: 167,416.215 million VND (equivalent to 6,372,420 EUR)
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q4 2022
Type of contract
According to adjusted unit price
Prequalification
No
Implementation location
17.Package BH5: Construction insurance package XL5
Tender/ Prequalification Notice ID
Contract execution period
24 months
Domestic/ International
Domestic
Bidding method
Directly
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
- Loan: 24,104,000 EUR (equivalent to 633,260,288 million VND) - Non-refundable aid: EUR 1 million (equivalent to VND 26,272 million) - Reciprocal capital: 167,416.215 million VND (equivalent to 6,372,420 EUR)
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2023
Type of contract
All in One
Prequalification
No
Implementation location
18.Package BH1: Construction insurance package XL1
Tender/ Prequalification Notice ID
Contract execution period
24 months
Domestic/ International
Domestic
Bidding method
Directly
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
- Loan: 24,104,000 EUR (equivalent to 633,260,288 million VND) - Non-refundable aid: EUR 1 million (equivalent to VND 26,272 million) - Reciprocal capital: 167,416.215 million VND (equivalent to 6,372,420 EUR)
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2023
Type of contract
All in One
Prequalification
No
Implementation location
19.Package XL5: Construction of Wastewater Treatment Station; wastewater treatment station equipment; medium voltage lines and substations for wastewater treatment plants; wastewater collection network 1 (basin PS1, PS2, PS3) - except for service pipelines and pumping station system.
Tender/ Prequalification Notice ID
Contract execution period
24 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
- Loan capital: 24,104,000 EUR (equivalent to 633,260,288 million VND). - Non-refundable aid: 1 million EUR (equivalent to 26,272 million VND). - Reciprocal capital: 167,416.215 million VND (equivalent to 6,372,420 EUR
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q4 2022
Type of contract
According to adjusted unit price
Prequalification
No
Implementation location
20.Package XL6: Waste collection network 2 (basins PS4, PS5, PS6) - except for service pipelines and pumping station system
Tender/ Prequalification Notice ID
Contract execution period
24 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
- Loan capital: 24,104,000 EUR (equivalent to 633,260,288 million VND) - Non-refundable aid: EUR 1 million (equivalent to VND 26,272 million) - Reciprocal capital: 167,416.215 million VND (equivalent to 6,372,420 EUR)
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q4 2022
Type of contract
According to adjusted unit price
Prequalification
No
Implementation location
21.GS2 package: Consulting and supervision of package XL2
Tender/ Prequalification Notice ID
Contract execution period
24 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
- Loan: 24,104,000 EUR (equivalent to 633,260,288 million VND) - Non-renewable aid: EUR 1 million (equivalent to VND 26,272 million) - Reciprocal capital: 167,416.215 million VND (equivalent to 6,372,420 EUR)
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q4 2022
Type of contract
All in One
Prequalification
No
Implementation location
22.Package XL3: Embankment route No. 1: Hoang Mai river anti-erosion embankment combined with the rescue road on the left bank of Hoang Mai river
Tender/ Prequalification Notice ID
Contract execution period
24 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
- Loan: 24,104,000 EUR (equivalent to 633,260,288 million VND) - Non-refundable aid: EUR 1 million (equivalent to VND 26,272 million) - Reciprocal capital: 167,416.215 million VND (equivalent to 6,372,420 EUR)
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q4 2022
Type of contract
According to adjusted unit price
Prequalification
No
Implementation location
23.Tender package for international payment: Verification and approval of settlement
Tender/ Prequalification Notice ID
Contract execution period
90 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
- Loan: 24,104,000 EUR (equivalent to 633,260,288 million VND) - Non-refundable aid: EUR 1 million (equivalent to VND 26,272 million) - Reciprocal capital: 167,416.215 million VND (equivalent to 6,372,420 EUR)
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q4 2024
Type of contract
All in One
Prequalification
No
Implementation location
24.KT contract package: Audit consulting, project settlement
Tender/ Prequalification Notice ID
Contract execution period
24 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
- Loan: 24,104,000 EUR (equivalent to 633,260,288 million VND) - Non-refundable aid: EUR 1 million (equivalent to VND 26,272 million) - Reciprocal capital: 167,416.215 million VND (equivalent to 6,372,420 EUR)
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q1 2023
Type of contract
All in One
Prequalification
No
Implementation location
25.Environmental and social environment bidding package: Consulting for environmental and social monitoring and supervision
Tender/ Prequalification Notice ID
Contract execution period
24 months
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
- Loan: 24,104,000 EUR (equivalent to 633,260,288 million VND) - Non-refundable aid: EUR 1 million (equivalent to VND 26,272 million) - Reciprocal capital: 167,416.215 million VND (equivalent to 6,372,420 EUR)
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2022
Type of contract
All in One
Prequalification
No
Implementation location
26.Resettlement bidding package: Independent monitoring and resettlement consultancy
Tender/ Prequalification Notice ID
Contract execution period
24 months
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
- Loan: 24,104,000 EUR (equivalent to 633,260,288 million VND) - Non-refundable aid: EUR 1 million (equivalent to VND 26,272 million) - Reciprocal capital: 167,416.215 million VND (equivalent to 6,372,420 EUR)
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2022
Type of contract
All in One
Prequalification
No
Implementation location

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Decision to approve additional contractor selection plan Subproject 3: Improving urban infrastructure in Hoang Mai, Hoang Mai town, Nghe An province, under the project "Improving urban infrastructure to minimizing the impact of climate change for 04 North Central coastal provinces" using loans from the French Development Agency.". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Decision to approve additional contractor selection plan Subproject 3: Improving urban infrastructure in Hoang Mai, Hoang Mai town, Nghe An province, under the project "Improving urban infrastructure to minimizing the impact of climate change for 04 North Central coastal provinces" using loans from the French Development Agency." plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 48

You did not use the site, Click here to remain logged. Timeout: 60 second