Bidder Selection Plan

Implementing the plan to select the contractor of Hong Bang Secondary School Repair Project (Block B, C, D), District 5

  Watching      
Find: 20:36 01/07/2025
Contractor Selection Plan ID
PL2500165239-00
Publishing time
17:25 01/07/2025
Posting Status
Published
Contractor selection plan name
Implementing the plan to select the contractor of Hong Bang Secondary School Repair Project (Block B, C, D), District 5
Investment objective
In order to serve the practical needs of students and schools in the district, create better conditions to gradually improve the facilities, and help the locality achieve the criteria of school and classroom facilities in the development program for developing the common education system of the region.
Project management forms
BQLDA major - area
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
PR2500040563-00
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group C
Project implementation time
2025 Years
Authority that issues the decision
Ủy ban nhân dân Quận 5
Approval date
27/06/2025
Approval ID
4762/QĐ-UBND
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using Windows operating system and installing Client Agent software (Linux and MacOS operating systems cannot install Client software yet). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use DauThau.info software to download files.
To download, please Login or Register

Files with this icon are not supported by the public procurement system for direct download in normal mode. Visit DauThau.info and select Quick Download mode to download the file if you do not use Windows with Agent. DauThau.info supports downloading on most modern browsers and devices!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
Related announcements

- Change: Investor, Highest bid price, Decision-making agency, Approval date, Approval ID, Publication date, Bidding package information (View changes)

Posted for the first time (View changes)

List of Bid:
Number of packages: 15
1.Tender package No 5: Consulting for bidding documents, evaluating bidding documents for construction design consultancy packages and estimates
Tender/ Prequalification Notice ID
Contract execution period
70 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Take a bid solicitor, compile bidding documents, evaluate bidding documents for construction drawing design consultancy packages and cost estimates
Capital source details
city budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Third quarter, 2025
Type of contract
All in One
Implementation location
Prequalification
No
2.Package 6: Advice on appraising bidding documents and evaluating the results of the contractor selection package for construction drawing design and estimates
Tender/ Prequalification Notice ID
Contract execution period
70 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Implement, evaluate bidding documents and evaluate the results of contractor selection package for construction drawing design and estimates
Capital source details
city budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Third quarter, 2025
Type of contract
All in One
Implementation location
Prequalification
No
3.Bidding package 7: Consulting on designing construction drawings and estimates
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Estimated design estimates after base design
Capital source details
city budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Third quarter, 2025
Type of contract
All in One
Implementation location
Prequalification
No
4.Bidding package 8: Consulting on verification of construction drawing designs and estimates
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Verification of design estimation after basic design
Capital source details
city budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Third quarter, 2025
Type of contract
All in One
Implementation location
Prequalification
No
5.Tender package No 9: Equipment valuation consultancy
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Equipment cost appraisal
Capital source details
city budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Third quarter, 2025
Type of contract
All in One
Implementation location
Prequalification
No
6.Package 10: Advice on making bidding documents, evaluating construction bids and supplying and installing technical equipment
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Take a bid solicitor, compile bidding documents, evaluate construction bidding documents and provide technical equipment installation
Capital source details
city budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Fourth quarter, 2025
Type of contract
All in One
Implementation location
Prequalification
No
7.Package 11: Consulting on appraising bidding documents and appraising the results of contractor selection of construction package for construction and installation of technical equipment
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Appraisal of bidding documents and appraise the results of the contractor selection of construction packages for construction and installation of technical equipment
Capital source details
city budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Fourth quarter, 2025
Type of contract
All in One
Implementation location
Prequalification
No
8.Bidding package 12: Consulting to compile bidding documents, evaluate bidding documents for the installation of office equipment and classroom equipment
Tender/ Prequalification Notice ID
Contract execution period
50 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Working as a bid solicitor, preparing bidding documents, evaluating bidding bidding documents to provide office equipment and classroom equipment
Capital source details
city budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Fourth quarter, 2025
Type of contract
All in One
Implementation location
Prequalification
No
9.Package 13: Advice on appraising bidding documents and the results of the contractor selection package to provide office equipment and classroom equipment installation
Tender/ Prequalification Notice ID
Contract execution period
50 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Appraisal of bidding documents and the results of the contractor selection of bidding packages to provide office equipment and classroom equipment
Capital source details
city budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Fourth quarter, 2025
Type of contract
All in One
Implementation location
Prequalification
No
10.Tender package No 14: Consulting for bidding documents, evaluating bidding documents for construction supervision consultancy package and equipment installation
Tender/ Prequalification Notice ID
Contract execution period
70 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
To be a bid solicitor, compile bidding documents, evaluate bidding documents for construction supervision and construction consultancy package and equipment installation
Capital source details
city budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Fourth quarter, 2025
Type of contract
All in One
Implementation location
Prequalification
No
11.Package 15: Advice on appraising bidding documents and results of selection of contractors for construction supervision consultancy package and equipment installation
Tender/ Prequalification Notice ID
Contract execution period
70 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Appraisal of bidding documents and the results of selection of contractors for construction supervision consultancy package and equipment installation
Capital source details
city budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Fourth quarter, 2025
Type of contract
All in One
Implementation location
Prequalification
No
12.Tender package No 16: Construction supervision consultancy and equipment installation
Tender/ Prequalification Notice ID
Contract execution period
270 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Construction supervision and equipment supply and installation
Capital source details
city budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Fourth quarter, 2025
Type of contract
All in One
Implementation location
Prequalification
No
13.Package 17: Construction insurance
Tender/ Prequalification Notice ID
Contract execution period
270 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Construction insurance
Capital source details
city budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Fourth quarter, 2025
Type of contract
All in One
Implementation location
Prequalification
No
14.Package 18: Construction and installation of technical equipment
Tender/ Prequalification Notice ID
Contract execution period
270 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Construction and repair to complete the classroom architecture; construction of transformer stations; building new electrical and water systems; Supply and installation of pressure stations; Supply and installation of wastewater treatment systems.
Capital source details
city budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Fourth quarter, 2025
Type of contract
Fixed unit price
Implementation location
Prequalification
No
15.Tender package No 19: Supply and install office equipment, classrooms
Tender/ Prequalification Notice ID
Contract execution period
150 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Goods
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Supply and install office equipment, classrooms
Capital source details
city budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Fourth quarter, 2025
Type of contract
All in One
Implementation location
Prequalification
No

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Implementing the plan to select the contractor of Hong Bang Secondary School Repair Project (Block B, C, D), District 5". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Implementing the plan to select the contractor of Hong Bang Secondary School Repair Project (Block B, C, D), District 5" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 27

You did not use the site, Click here to remain logged. Timeout: 60 second