Bidder Selection Plan

Install the canopy for the exit gate (gate 3)

    Watching  
Project Overall Procurement plan Contractor selection plan Bid award
Find: 14:38 16/03/2024
Contractor Selection Plan ID
PL2400033791-00
Publishing time
14:38 16/03/2024
Posting Status
Published
Contractor selection plan name
Install the canopy for the exit gate (gate 3)
Investment objective
Development Investment
Project management forms
The investor hires a project management consultant
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
PR2400009961-00
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group C
Project implementation time
4 Month
Authority that issues the decision
Tổng Giám đốc
Approval date
26/02/2024
Approval ID
14/QĐ-BXMT
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using Windows operating system and installing Client Agent software (Linux and MacOS operating systems cannot install Client software yet). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use DauThau.info software to download files.
To download, please Login or Register

Files with this icon are not supported by the public procurement system for direct download in normal mode. Visit DauThau.info and select Quick Download mode to download the file if you do not use Windows with Agent. DauThau.info supports downloading on most modern browsers and devices!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
List of Bid:
Number of packages: 7
1.Project management consultancy
Tender/ Prequalification Notice ID
Contract execution period
4 months
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
- Organize contractor selection in construction activities; - Organize the verification and appraisal of construction drawing designs and construction estimates; - Organize the management of quality, volume, progress, construction costs and completion documents - Organize acceptance, payment and finalization of contracts; Payment and finalization of project construction investment capital
Capital source details
Capital of the enterprise
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2024
Type of contract
All in One
Implementation location
Bình Tân District, City Hồ Chí Minh
Implementation location (After merge)
Prequalification
No
2.Consulting on Preparation of Finance and Technical Report
Tender/ Prequalification Notice ID
Contract execution period
10 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
- Measuring and drawing the current status of the project - Proposing survey tasks to serve the preparation of technical and economic reports for construction works - Prepare technical and economic reports including explanations, construction drawing designs, and estimates to ensure compliance with regulations, standards, and legal regulations on construction
Capital source details
Capital of the enterprise
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2024
Type of contract
All in One
Implementation location
Bình Tân District, City Hồ Chí Minh
Implementation location (After merge)
Prequalification
No
3.Consultancy, design verification, cost estimation
Tender/ Prequalification Notice ID
Contract execution period
7 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
- Design Verification - Verify the estimate
Capital source details
Capital of the enterprise
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2024
Type of contract
All in One
Implementation location
Bình Tân District, City Hồ Chí Minh
Implementation location (After merge)
Prequalification
No
4.Construction supervision consultancy
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Supervise quality, volume, progress, labor safety and environmental protection during construction
Capital source details
Capital of the enterprise
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2024
Type of contract
All in One
Implementation location
Bình Tân District, City Hồ Chí Minh
Implementation location (After merge)
Prequalification
No
5.Civil Works
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Civil Works
Capital source details
Capital of the enterprise
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2024
Type of contract
All in One
Implementation location
Bình Tân District, City Hồ Chí Minh
Implementation location (After merge)
Prequalification
No
6.Insurance
Tender/ Prequalification Notice ID
Contract execution period
one year
Domestic/ International
Domestic
Bidding method
Directly
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
3rd party insurance
Capital source details
Capital of the enterprise
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2024
Type of contract
All in One
Implementation location
Bình Tân District, City Hồ Chí Minh
Implementation location (After merge)
Prequalification
No
7.Audit
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
- Check legal documents; - Check investment capital sources; - Check investment costs; - Check investment costs for damage not included in the value of assets formed through investment; - Check the value of assets formed through investment; - Check outstanding debts, supplies and equipment; - Check the compliance of the investor and relevant units with the conclusions of the State Inspection, Inspection and Audit agencies (if any).
Capital source details
Capital of the enterprise
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
All in One
Implementation location
Implementation location (After merge)
Prequalification
No

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Install the canopy for the exit gate (gate 3)". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Install the canopy for the exit gate (gate 3)" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 21

You did not use the site, Click here to remain logged. Timeout: 60 second