Bidder Selection Plan

Inter-regional roads connecting Ho Chi Minh Road with National Highway 70B and National Highway 32C in Phu Tho province to Yen Bai province

  Watching      
Find: 14:18 02/04/2026
Contractor Selection Plan ID
PL2500069713-02
Publishing time
14:17 02/04/2026
Posting Status
Published
Contractor selection plan name
Inter-regional roads connecting Ho Chi Minh Road with National Highway 70B and National Highway 32C in Phu Tho province to Yen Bai province
Investment objective
- Building a dynamic route, forming a synchronous and convenient transportation system between the northern mountainous provinces through the arterial roads passing through Phu Tho province such as Ho Chi Minh road, National Highway 70B, Highway 32, National Highway 32C, Noi Bai - Lao Cai highway ... Connecting industrial parks of districts: Tam Nong, Cam Khe, Ha Hoa; Urban areas and eco -services in the southwest and northwest of Phu Tho province; facilitate the development of land fund on both sides of the road
Project management forms
The investor directly manages the project
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
PR2500017370-00
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group A
Project implementation time
5 Years
Authority that issues the decision
UBND tỉnh Phú Thọ
Approval date
07/01/2025
Approval ID
44/QĐ-UBND
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using Windows operating system and installing Client Agent software (Linux and MacOS operating systems cannot install Client software yet). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use DauThau.info software to download files.
To download, please Login or Register

Files with this icon are not supported by the public procurement system for direct download in normal mode. Visit DauThau.info and select Quick Download mode to download the file if you do not use Windows with Agent. DauThau.info supports downloading on most modern browsers and devices!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
Related announcements

- Change: Lowest bid price, Publication date, Bidding package information (View changes)

- Change: Filter name, Publication date, Bidding package information (View changes)

Posted for the first time (View changes)

List of Bid:
Number of packages: 19
1.Tender package No 57: Consulting survey, planning, estimation of mine clearance work explosion extended route
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Survey consultancy, plan and estimate of mine clearance exploration of extended route
Capital source details
Central budget, provincial budget and other lawfully mobilized capital sources
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Quarter I, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Implementation location (Before merge)
Phú Thọ, Vĩnh Phúc, Hòa Bình
2.Tender package No 58: Construction of mines and mines and explosive materials for extended route
Tender/ Prequalification Notice ID
Contract execution period
90 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Summary of main tasks of the bid package
Construction of mines and mines and explosive materials for extended route
Capital source details
Central budget, provincial budget and other lawfully mobilized capital sources
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Second quarter, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Implementation location (Before merge)
Phú Thọ, Vĩnh Phúc, Hòa Bình
3.Bidding package No. 59: Advice on supervision of mine clearance, extended route explosive materials
Tender/ Prequalification Notice ID
Contract execution period
90 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Summary of main tasks of the bid package
Consulting on supervision of mine clearance and explosive materials for extended route
Capital source details
Central budget, provincial budget and other lawfully mobilized capital sources
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Second quarter, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Implementation location (Before merge)
Phú Thọ, Vĩnh Phúc, Hòa Bình
4.Tender package No 60: Construction of extended route
Tender/ Prequalification Notice ID
Contract execution period
240 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Summary of main tasks of the bid package
Construction of extended route
Capital source details
Central budget, provincial budget and other lawfully mobilized capital sources
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Second quarter, 2025
Type of contract
Fixed unit price
Prequalification
No
Implementation location (After merge)
Implementation location (Before merge)
Phú Thọ, Vĩnh Phúc, Hòa Bình
5.Tender package No 61: Supervision of construction of extended route
Tender/ Prequalification Notice ID
Contract execution period
240 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Summary of main tasks of the bid package
Construction supervision of extended route
Capital source details
Central budget, provincial budget and other lawfully mobilized capital sources
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Second quarter, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Implementation location (Before merge)
Phú Thọ, Vĩnh Phúc, Hòa Bình
6.Tender package No 62: Construction insurance for extended route
Tender/ Prequalification Notice ID
Contract execution period
240 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Summary of main tasks of the bid package
Projecting road construction insurance
Capital source details
Central budget, provincial budget and other lawfully mobilized capital sources
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Second quarter, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Implementation location (Before merge)
Phú Thọ, Vĩnh Phúc, Hòa Bình
7.Tender package No 64: Construction of the item moving electric lines for site clearance
Tender/ Prequalification Notice ID
Contract execution period
150 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Summary of main tasks of the bid package
Construction of electric lines moving items
Capital source details
Central budget, provincial budget and other lawfully mobilized capital sources
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Second quarter, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Implementation location (Before merge)
Phú Thọ, Vĩnh Phúc, Hòa Bình
8.Tender package No 65: Supervision of construction of the item moving electric lines for site clearance
Tender/ Prequalification Notice ID
Contract execution period
150 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Summary of main tasks of the bid package
Supervision of construction of electric lines moving items
Capital source details
Central budget, provincial budget and other lawfully mobilized capital sources
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Second quarter, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Implementation location (Before merge)
Phú Thọ, Vĩnh Phúc, Hòa Bình
9.Tender package No 66: Insurance to build the item moving electric lines for site clearance
Tender/ Prequalification Notice ID
Contract execution period
150 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Summary of main tasks of the bid package
Insurance to build electricity moving items
Capital source details
Central budget, provincial budget and other lawfully mobilized capital sources
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Second quarter, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Implementation location (Before merge)
Phú Thọ, Vĩnh Phúc, Hòa Bình
10.Tender package No 67: Survey, detailed planning of 1/500 scale of building technical infrastructure of rural population points for site clearance
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Summary of main tasks of the bid package
Surveying and making detailed planning 1/500 scale construction of technical infrastructure of rural population points
Capital source details
Central budget, provincial budget and other lawfully mobilized capital sources
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Quarter I, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Implementation location (Before merge)
Phú Thọ, Vĩnh Phúc, Hòa Bình
11.Tender package No 68: Survey, design construction drawings, estimate items of construction works construction technical infrastructure of rural residential areas for site clearance
Tender/ Prequalification Notice ID
Contract execution period
150 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Surveying, designing construction drawings, estimating items of construction work construction works
Capital source details
Central budget, provincial budget and other lawfully mobilized capital sources
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Second quarter, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Implementation location (Before merge)
Phú Thọ, Vĩnh Phúc, Hòa Bình
12.Tender package No 69: Construction of construction works of technical infrastructure construction of rural population points for site clearance
Tender/ Prequalification Notice ID
Contract execution period
150 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Summary of main tasks of the bid package
Construction of construction work items of technical infrastructure of rural residential areas
Capital source details
Central budget, provincial budget and other lawfully mobilized capital sources
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Second quarter, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Implementation location (Before merge)
Phú Thọ, Vĩnh Phúc, Hòa Bình
13.Tender package No 70: Supervision of construction of construction work items of technical infrastructure of rural population points for site clearance
Tender/ Prequalification Notice ID
Contract execution period
150 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Summary of main tasks of the bid package
Supervise the construction of the item of construction of technical infrastructure of rural population points
Capital source details
Central budget, provincial budget and other lawfully mobilized capital sources
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Second quarter, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Implementation location (Before merge)
Phú Thọ, Vĩnh Phúc, Hòa Bình
14.Tender package No 71: Insurance to build the work of construction works of technical infrastructure of rural residential areas for site clearance
Tender/ Prequalification Notice ID
Contract execution period
150 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Summary of main tasks of the bid package
Insurance to build works of construction work of technical infrastructure of rural residential areas
Capital source details
Central budget, provincial budget and other lawfully mobilized capital sources
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Second quarter, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Implementation location (Before merge)
Phú Thọ, Vĩnh Phúc, Hòa Bình
15.Tender package No 72: Acceptance of electricity for electricity movement of electricity lines and construction of rural population infrastructure for site clearance
Tender/ Prequalification Notice ID
Contract execution period
150 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Summary of main tasks of the bid package
Acceptance of energizing the work item of moving electricity lines and construction of rural population technical infrastructure
Capital source details
Central budget, provincial budget and other lawfully mobilized capital sources
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Second quarter, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Implementation location (Before merge)
Phú Thọ, Vĩnh Phúc, Hòa Bình
16.Bidding package 73: Consulting to make a report on the current state of forest affected by the project
Tender/ Prequalification Notice ID
Contract execution period
120 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Consulting to make a report on the status quo of forest affected by the project
Capital source details
Central budget, provincial budget and other lawfully mobilized capital sources
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Third quarter, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Implementation location (Before merge)
Phú Thọ, Vĩnh Phúc, Hòa Bình
17.Bidding package 74: Traffic safety verification consultant before putting the project into exploitation and use
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Traffic safety verification consultant before putting the project into exploitation and use of extended route
Capital source details
Central budget, provincial budget and other lawfully mobilized capital sources
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Second quarter, 2026
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Implementation location (Before merge)
Phú Thọ, Vĩnh Phúc, Hòa Bình
18.Tender package No 75: Advice on monitoring and monitoring of the environment during the construction process
Tender/ Prequalification Notice ID
Contract execution period
330 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Summary of main tasks of the bid package
Environmental monitoring and monitoring consultancy during the construction process
Capital source details
Central budget, provincial budget and other lawfully mobilized capital sources
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Second quarter, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Implementation location (Before merge)
Phú Thọ, Vĩnh Phúc, Hòa Bình
19.Bidding package 76: Auditing consultancy for the project settlement report to complete the branch and extended route
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Auditing consultancy for project settlement reports to complete branches and extended routes
Capital source details
Central budget, provincial budget and other lawfully mobilized capital sources
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Second quarter, 2026
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Implementation location (Before merge)
Phú Thọ, Vĩnh Phúc, Hòa Bình

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Inter-regional roads connecting Ho Chi Minh Road with National Highway 70B and National Highway 32C in Phu Tho province to Yen Bai province". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Inter-regional roads connecting Ho Chi Minh Road with National Highway 70B and National Highway 32C in Phu Tho province to Yen Bai province" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 3

You did not use the site, Click here to remain logged. Timeout: 60 second