Bidder Selection Plan

Investment preparation stage

  Watching  
Project Contractor selection plan Bid award
Find: 14:12 28/08/2026
Contractor Selection Plan ID
PL2600153381-01
Publishing time
14:11 28/08/2026
Posting Status
Published
Contractor selection plan name
Investment preparation stage
Investment objective
Improving the life of the project, preventing deterioration to meet the needs of the local government, ensuring uniform quality of the image of the Corporation's brand identity system, creating favorable working conditions for employees working at the Commune Post Office to complete assigned tasks.
Project management forms
The investor directly manages the project
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
PR2600030698-01
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group C
Project implementation time
7 Month
Authority that issues the decision
Bưu điện tỉnh Vĩnh Long
Approval date
27/08/2026
Approval ID
783/QĐ-BĐVL
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using Windows operating system and installing Client Agent software (Linux and MacOS operating systems cannot install Client software yet). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use DauThau.info software to download files.
To download, please Login or Register

Files with this icon are not supported by the public procurement system for direct download in normal mode. Visit DauThau.info and select Quick Download mode to download the file if you do not use Windows with Agent. DauThau.info supports downloading on most modern browsers and devices!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
Related announcements

- Change: Total investment, total investment, Approval date, Approval ID, Publication date (View changes)

Posted for the first time (View changes)

List of Bid:
Number of packages: 2
1.Consulting on making economic and technical reports on construction investment
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Making economic and technical reports on construction investment
Capital source details
KHCB
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
June, 2026
Type of contract
All in One
Implementation location
Prequalification
No
2.Consultancy and verification of construction drawing design and total cost estimate
Tender/ Prequalification Notice ID
Contract execution period
10 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Verification of construction drawing design and total cost estimate
Capital source details
KHCB
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
June, 2026
Type of contract
All in One
Implementation location
Prequalification
No

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Investment preparation stage". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Investment preparation stage" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 0

You did not use the site, Click here to remain logged. Timeout: 60 second