Bidder Selection Plan

KHLCNT Project Ring Road 2

  Watching      
Find: 12:02 13/01/2026
Contractor Selection Plan ID
PL2300124556-03
Publishing time
11:59 13/01/2026
Posting Status
Published
Contractor selection plan name
KHLCNT Project Ring Road 2
Project management forms
BQLDA major - area
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
PR2300033688-00
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group A
Project implementation time
6 Years
Authority that issues the decision
Ban Quản lý dự án đầu tư xây dựng các công trình giao thông và nông nghiệp Hải Phòng
Approval date
08/01/2026
Approval ID
23/QĐ-BQL
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using Windows operating system and installing Client Agent software (Linux and MacOS operating systems cannot install Client software yet). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use DauThau.info software to download files.
To download, please Login or Register

Files with this icon are not supported by the public procurement system for direct download in normal mode. Visit DauThau.info and select Quick Download mode to download the file if you do not use Windows with Agent. DauThau.info supports downloading on most modern browsers and devices!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
Related announcements

- Change: Investor, Decision-making agency, Approval date, Approval ID, Publication date, Bidding package information (View changes)

- Change: Publication date, Bidding package information (View changes)

- Change: Filter name, Publication date, Bidding package information (View changes)

Posted for the first time (View changes)

List of Bid:
Number of packages: 22
1.Bidding package 9: Consulting on making tasks, estimates and bidding for consulting packages
Tender/ Prequalification Notice ID
Contract execution period
30 months
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Hai Phong city budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2023
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Implementation location (Before merge)
Hải Phòng
2.Package 10: Consulting on verification of tasks and estimates for bidding packages
Tender/ Prequalification Notice ID
Contract execution period
30 months
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Hai Phong city budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2023
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Implementation location (Before merge)
Hải Phòng
3.Package 11: Survey consultancy, technical design, BVTC design, construction cost estimate and work information model; Making Bidding Bidding package for construction and installation
Tender/ Prequalification Notice ID
Contract execution period
30 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Hai Phong city budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q3 2023
Type of contract
Package and Fixed Price
Prequalification
No
Implementation location (After merge)
Implementation location (Before merge)
Hải Phòng
4.Bidding package 12: Survey supervision consultancy, construction design verification
Tender/ Prequalification Notice ID
Contract execution period
30 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Hai Phong city budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q3 2023
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Implementation location (Before merge)
Hải Phòng
5.Bidding package 13: Consulting on examining construction cost estimates
Tender/ Prequalification Notice ID
Contract execution period
30 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Hai Phong city budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q3 2023
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Implementation location (Before merge)
Hải Phòng
6.Tender package No 14: Environmental monitoring and monitoring consultancy
Tender/ Prequalification Notice ID
Contract execution period
30 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Capital source details
Hai Phong city budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q4 2023
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Implementation location (Before merge)
Hải Phòng
7.Tender package No 15: Survey, set up construction techniques and estimates of mine clearance and explosive objects
Tender/ Prequalification Notice ID
Contract execution period
4 months
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Hai Phong city budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2023
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Implementation location (Before merge)
Hải Phòng
8.Tender package No 16: Mine clearance and explosive objects
Tender/ Prequalification Notice ID
Contract execution period
30 months
Domestic/ International
Domestic
Bidding method
Directly
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Capital source details
Hai Phong city budget
Contractor Selection Type
Specify reference
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2023
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Implementation location (Before merge)
Hải Phòng
9.Tender package No 17: Consulting on supervision of construction and construction of mines and mines explosives
Tender/ Prequalification Notice ID
Contract execution period
30 months
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Capital source details
Hai Phong city budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2023
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Implementation location (Before merge)
Hải Phòng
10.Package 18: Traffic safety examining consultancy
Tender/ Prequalification Notice ID
Contract execution period
30 months
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
city budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Quarter I, 2026
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Implementation location (Before merge)
Hải Phòng
11.Tender package No 19: Building Tan Vu intersection and route to the beginning of the inter -ward intersection
Tender/ Prequalification Notice ID
Contract execution period
20 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Capital source details
Hai Phong city budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
Fixed unit price and Adjusted unit price
Prequalification
No
Implementation location (After merge)
Implementation location (Before merge)
Hải Phòng
12.Tender package No 20: Building the section from the inter -ward intersection to the end of Hai Thanh overpass
Tender/ Prequalification Notice ID
Contract execution period
30 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Capital source details
Hai Phong city budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2023
Type of contract
Fixed unit price and Adjusted unit price
Prequalification
No
Implementation location (After merge)
Implementation location (Before merge)
Hải Phòng
13.Tender package No 21: Building the route from the end of Hai Thanh overpass to the beginning of the intersection of Bui Vien
Tender/ Prequalification Notice ID
Contract execution period
24 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Capital source details
city budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
Fixed unit price and Adjusted unit price
Prequalification
No
Implementation location (After merge)
Implementation location (Before merge)
Hải Phòng
14.Tender package No 22: Building the intersection of Bui Vien
Tender/ Prequalification Notice ID
Contract execution period
24 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Capital source details
Hai Phong city budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2024
Type of contract
Fixed unit price and Adjusted unit price
Prequalification
No
Implementation location (After merge)
Implementation location (Before merge)
Hải Phòng
15.Tender package No 23: Construction of technical infrastructure of resettlement area
Tender/ Prequalification Notice ID
Contract execution period
12 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Capital source details
Hai Phong city budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2023
Type of contract
Fixed unit price
Prequalification
No
Implementation location (After merge)
Implementation location (Before merge)
Hải Phòng
16.Tender package No 24: Supervision of construction of Tan Vu intersection and route to the beginning of the inter -ward intersection
Tender/ Prequalification Notice ID
Contract execution period
20 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Capital source details
Hai Phong city budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q3 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Implementation location (Before merge)
Hải Phòng
17.Tender package No 25: Supervision of construction of the route from the inter -ward intersection to the end of Hai Thanh overpass
Tender/ Prequalification Notice ID
Contract execution period
30 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Capital source details
Hai Phong city budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q4 2023
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Implementation location (Before merge)
Hải Phòng
18.Tender package No 26: Supervision of construction of the route from the end of Hai Thanh overpass to the beginning of the intersection of Bui Vien
Tender/ Prequalification Notice ID
Contract execution period
24 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Capital source details
Hai Phong city budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q3 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Implementation location (Before merge)
Hải Phòng
19.Tender package No 27: Supervision of construction and construction of Bui Vien overpass
Tender/ Prequalification Notice ID
Contract execution period
24 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Capital source details
Hai Phong city budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q1 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Implementation location (Before merge)
Hải Phòng
20.Tender package No 28: Supervising construction of technical infrastructure of resettlement area
Tender/ Prequalification Notice ID
Contract execution period
12 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Capital source details
Hai Phong city budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q4 2023
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Implementation location (Before merge)
Hải Phòng
21.Tender package No 29: Testing for bridge loading and quality testing
Tender/ Prequalification Notice ID
Contract execution period
30 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Hai Phong city budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q1 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Implementation location (Before merge)
Hải Phòng
22.Tender package No 30: Independent audit consultancy
Tender/ Prequalification Notice ID
Contract execution period
36 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Hai Phong city budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q1 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Implementation location (Before merge)
Hải Phòng

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "KHLCNT Project Ring Road 2". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "KHLCNT Project Ring Road 2" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 0

You did not use the site, Click here to remain logged. Timeout: 60 second