Bidder Selection Plan
LCNT plan in the project implementation phase
Contractor Selection Plan ID
PL2500045832-00
Publishing time
16:00 13/03/2025
Contractor selection plan name
LCNT plan in the project implementation phase
Investment objective
Renovate and repair the Convention Center 46 Tran Phu
Project management forms
The investor hires a project management consultant
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
PR2500011364-00
Spending Category
Investment and Development Spending
Project implementation time
3 Years
Authority that issues the decision
UBND tỉnh Khánh Hòa
Approval Documents
Downloading files directly on the new Public Procurement System requires a computer using Windows operating system and installing Client Agent software (Linux and MacOS operating systems cannot install Client software yet). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use DauThau.info software to download files. To download, please Login or Register
Files with this icon are not supported by the public procurement system for direct download in normal mode. Visit DauThau.info and select Quick Download mode to download the file if you do not use Windows with Agent . DauThau.info supports downloading on most modern browsers and devices! In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
List of Bid:
Number of packages: 10
1. Consulting on setting up HSMT; evaluation of bids
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Regulatory compliance
Bidding Law
Summary of main tasks of the bid package
Making Bidding Documents; Evaluation of Bid dossier for bidding packages No. 3, No. 5 and No. 6.
Capital source details
Provincial budget capital
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Quarter I, 2025
Type of contract
All in One
Implementation location (After merge)
Implementation location (Before merge)
Tỉnh Khánh Hoà
2. Consulting on evaluation of Bidding Documents; Contractor selection results
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Regulatory compliance
Bidding Law
Summary of main tasks of the bid package
Consulting on evaluation of Bidding Documents; The results of the contractor selection packages: No. 3, No. 5 and No. 6.
Capital source details
Provincial budget capital
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Quarter I, 2025
Type of contract
All in One
Implementation location (After merge)
Implementation location (Before merge)
Tỉnh Khánh Hoà
3. Consultancy on making design documents, construction drawings and cost estimates
Tender/ Prequalification Notice ID
Contract execution period
45 days
Domestic/ International
Domestic
Regulatory compliance
Bidding Law
Summary of main tasks of the bid package
Prepare construction drawings and design documents
Capital source details
Provincial budget capital
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Quarter I, 2025
Type of contract
All in One
Implementation location (After merge)
Implementation location (Before merge)
Tỉnh Khánh Hoà
4. Consultancy and verification of construction drawing design documents and cost estimates
Tender/ Prequalification Notice ID
Contract execution period
40 days
Domestic/ International
Domestic
Regulatory compliance
Bidding Law
Summary of main tasks of the bid package
Verification of construction drawing design records and estimates
Capital source details
Provincial budget capital
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Quarter I, 2025
Type of contract
All in One
Implementation location (After merge)
Implementation location (Before merge)
Tỉnh Khánh Hoà
5. Construction supervision consultancy and construction equipment installation
Tender/ Prequalification Notice ID
Contract execution period
270 days
Domestic/ International
Domestic
Regulatory compliance
Bidding Law
Summary of main tasks of the bid package
Supervision of construction and installation of construction equipment
Capital source details
Provincial budget capital
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Second quarter, 2025
Type of contract
All in One
Implementation location (After merge)
Implementation location (Before merge)
Tỉnh Khánh Hoà
6. Construction of works and equipment supply and installation
Tender/ Prequalification Notice ID
Contract execution period
270 days
Domestic/ International
Domestic
Regulatory compliance
Bidding Law
Summary of main tasks of the bid package
Construction of works and equipment supply and installation
Capital source details
Provincial budget capital
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Second quarter, 2025
Type of contract
Fixed unit price
Implementation location (After merge)
Implementation location (Before merge)
Tỉnh Khánh Hoà
7. Consulting to check the acceptance of construction works
Tender/ Prequalification Notice ID
Contract execution period
270 days
Domestic/ International
Domestic
Regulatory compliance
Bidding Law
Summary of main tasks of the bid package
Check the acceptance of construction works of the investor.
Capital source details
Provincial budget capital
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Second quarter, 2025
Type of contract
All in One
Implementation location (After merge)
Implementation location (Before merge)
Tỉnh Khánh Hoà
Tender/ Prequalification Notice ID
Contract execution period
270 days
Domestic/ International
Domestic
Regulatory compliance
Bidding Law
Summary of main tasks of the bid package
Construction insurance
Capital source details
Provincial budget capital
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Second quarter, 2025
Type of contract
All in One
Implementation location (After merge)
Implementation location (Before merge)
Tỉnh Khánh Hoà
9. Equipment appraisal consulting
Tender/ Prequalification Notice ID
Contract execution period
45 days
Domestic/ International
Domestic
Regulatory compliance
Bidding Law
Summary of main tasks of the bid package
Equipment valuation of project equipment as a basis for determining construction cost estimates.
Capital source details
Provincial budget capital
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Quarter I, 2025
Type of contract
All in One
Implementation location (After merge)
Implementation location (Before merge)
Tỉnh Khánh Hoà
10. Independent audit consultant
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Regulatory compliance
Bidding Law
Summary of main tasks of the bid package
Auditing the entire project in service of the completed project settlement.
Capital source details
Provincial budget capital
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Second quarter, 2026
Type of contract
All in One
Implementation location (After merge)
Implementation location (Before merge)
Tỉnh Khánh Hoà
Utilities for you:
Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "LCNT plan in the project implementation phase". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Following
Receive similar invitation to bid by email
To be one of the
first to receive email notifications of contractor selection plans similar to the "LCNT plan in the project implementation phase" plan as soon as they are posted,
sign up for DauThau.info's VIP 2 plan.