Bidder Selection Plan

Maintaining and upgrading Hoa Lam kindergarten

  Watching      
Find: 10:05 12/04/2025
Contractor Selection Plan ID
PL2500078229-00
Publishing time
10:03 12/04/2025
Posting Status
Published
Contractor selection plan name
Maintaining and upgrading Hoa Lam kindergarten
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
PR2500019634-00
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group C
Project implementation time
2 Years
Authority that issues the decision
UBND huyện Đông Anh
Approval date
09/04/2025
Approval ID
5150/QĐ-UBND
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using Windows operating system and installing Client Agent software (Linux and MacOS operating systems cannot install Client software yet). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use DauThau.info software to download files.
To download, please Login or Register

Files with this icon are not supported by the public procurement system for direct download in normal mode. Visit DauThau.info and select Quick Download mode to download the file if you do not use Windows with Agent. DauThau.info supports downloading on most modern browsers and devices!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
List of Bid:
Number of packages: 6
1.Project management
Tender/ Prequalification Notice ID
Contract execution period
180 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Consulting for planning, organization, and supervision during project implementation
Capital source details
budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Second quarter, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Đông Anh District, Hà Nội
Implementation location (Before merge)
Ha Noi city
2.Evaluation of Bidding Documents, Evaluation of Bid Bidding package for construction and installation and installation of equipment
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Organize the preparation of Bidding Documents and evaluate the Bidding Documents of contractors participating in the Construction and equipment supply and installation package
Capital source details
budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Second quarter, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Đông Anh District, Hà Nội
Implementation location (Before merge)
Ha Noi city
3.Evaluation of Bids and Bidding Documents and results of construction and installation packages
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Organizing the appraisal of Bidding Documents and the results of the contractor's LCN to participate in the construction and installation package
Capital source details
budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Second quarter, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Đông Anh District, Hà Nội
Implementation location (Before merge)
Ha Noi city
4.Construction supervision and equipment installation
Tender/ Prequalification Notice ID
Contract execution period
180 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Organize the construction and construction supervision, supply and installation of equipment, accepting the quality of works
Capital source details
budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Second quarter, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Đông Anh District, Hà Nội
Implementation location (Before merge)
Ha Noi city
5.Independent audit
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Check the completed project settlement report according to Vietnam Auditing Standard No. 1000
Capital source details
budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Fourth quarter, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Đông Anh District, Hà Nội
Implementation location (Before merge)
Ha Noi city
6.Construction and equipment supply and installation
Tender/ Prequalification Notice ID
Contract execution period
180 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Uncategoried
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Construction of construction works and providing equipment installation in accordance with the approved design
Capital source details
budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Second quarter, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Đông Anh District, Hà Nội
Implementation location (Before merge)
Ha Noi city

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Maintaining and upgrading Hoa Lam kindergarten". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Maintaining and upgrading Hoa Lam kindergarten" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 8

You did not use the site, Click here to remain logged. Timeout: 60 second