Downloading files directly on the new Public Procurement System requires a computer using the Windows operating system and needs to install Client Agent software (Linux and MacOS cannot download Client software yet). ). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use our DauThau.info. Our system will help you download files faster, on any device without installing Client Agent. To download, please Login or Register
CV 639_Phe duyet KH lua chon nha thau dot 3 DA NMN Van Nien.pdf
Related announcements
- Change:Notification form, Publication date (View changes)
Equity to implement the Project; Loans (Banks, credit institutions, ...)
Contractor Selection Type
Bidding widely, domestically, without prequalification, without online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2020
Contract Type
According to the adjusted unit price
Prequalification
No
Location
3.Tender package No 9: Consulting on making bidding documents, evaluating bids. Package: Consulting on project management, supervising construction and equipment installation-Phase 1: 60,000m3/day
Equity to implement the Project; Loans (Banks, credit institutions, ...)
Contractor Selection Type
Appointment of contractors, domestic, no prequalification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2020
Contract Type
All in one
Prequalification
No
Location
4.Package 11: Consulting for making bidding documents, evaluating bids: Design - supply technological equipment and construction (EPC) Van Nien clean water plant - Phase 1: 60,000m3 /ngd
Equity to implement the Project; Loans (Banks, credit institutions, ...)
Contractor Selection Type
Bidding widely, domestically, without prequalification, without online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2020
Contract Type
All in one
Prequalification
No
Location
Utilities for you:
Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Phase 3 Planning and Investment Project of construction of Van Nien clean water treatment plant CS120,000m3/day". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Phase 3 Planning and Investment Project of construction of Van Nien clean water treatment plant CS120,000m3/day" plan as soon as they are posted, sign up for DauThau.info's International VIP 2 plan.