Bidder Selection Plan

Phieng Pan primary and secondary boarding school

  Watching  
Project Contractor selection plan Bid award
Find: 16:28 15/12/2025
Contractor Selection Plan ID
PL2500344558-00
Publishing time
16:27 15/12/2025
Posting Status
Published
Contractor selection plan name
Phieng Pan primary and secondary boarding school
Investment objective
Synchronously build primary and secondary schools for border communes to ensure synchronization and compliance with technical standards, scale and area school and classroom areas; Meet the physical conditions for learning and forging cultural, spiritual, physical training, living conditions and absolute safety; through there in order to improve people's knowledge, quality of human resources, create a source of officials from ethnic groups, localities, improving the material and spiritual life of people in border areas, contributing to strengthening national defense and security
Project management forms
The investor hires a project management consultant
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
PR2500064816-00
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group B
Project implementation time
1 Years
Authority that issues the decision
Bộ chỉ huy quân sự tỉnh Sơn La
Approval date
09/12/2025
Approval ID
6222/QĐ-BCH
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using Windows operating system and installing Client Agent software (Linux and MacOS operating systems cannot install Client software yet). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use DauThau.info software to download files.
To download, please Login or Register

Files with this icon are not supported by the public procurement system for direct download in normal mode. Visit DauThau.info and select Quick Download mode to download the file if you do not use Windows with Agent. DauThau.info supports downloading on most modern browsers and devices!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
List of Bid:
Number of packages: 13
1.Tender package No 01: Project management consulting
Tender/ Prequalification Notice ID
Contract execution period
270 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Project management consultancy
Capital source details
Central budget and other legal sources of capital
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Fourth quarter, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
2.Bidding package No. 02: Design consulting and implementation after basic design
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Consultancy on the design of construction drawings and total cost estimates
Capital source details
Central budget and other legal sources of capital
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Fourth quarter, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
3.Package 03: Consultancy and verification of construction drawing design and cost estimate
Tender/ Prequalification Notice ID
Contract execution period
20 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Consultancy and verification of construction drawing design and cost estimate
Capital source details
Central budget and other legal sources of capital
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Fourth quarter, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
4.Package 04: Construction supervision consultancy and equipment installation
Tender/ Prequalification Notice ID
Contract execution period
210 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Construction supervision and equipment installation
Capital source details
Central budget and other legal sources of capital
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Fourth quarter, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
5.Tender package No 05: Equipment valuation consultancy
Tender/ Prequalification Notice ID
Contract execution period
20 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Equipment appraisal consulting
Capital source details
Central budget and other legal sources of capital
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Fourth quarter, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
6.Tender package No 06: Subsidence monitoring consulting
Tender/ Prequalification Notice ID
Contract execution period
210 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Consulting subsidence monitoring
Capital source details
Central budget and other legal sources of capital
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Quarter I, 2026
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
7.Package 07: Clearing mines
Tender/ Prequalification Notice ID
Contract execution period
20 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Prepare plans and execute clearance of bombs, mines and explosives
Capital source details
Central budget and other legal sources of capital
Contractor Selection Type
Do it yourself
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Fourth quarter, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
8.Package 08: Construction insurance
Tender/ Prequalification Notice ID
Contract execution period
210 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Construction insurance
Capital source details
Central budget and other legal sources of capital
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Fourth quarter, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
9.Tender package No 09: Construction audit
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Independent audit of construction works and site clearance cost audit
Capital source details
Central budget and other legal sources of capital
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
In the third quarter, 2026
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
10.Tender package No 10: Construction of main works
Tender/ Prequalification Notice ID
Contract execution period
210 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Construction of construction items, architecture, termite prevention
Capital source details
Central budget and other legal sources of capital
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Quarter I, 2026
Type of contract
Fixed unit price
Prequalification
No
Implementation location (After merge)
11.Tender package No 11: Technical infrastructure construction
Tender/ Prequalification Notice ID
Contract execution period
210 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Construction of technical infrastructure items, environmental protection costs
Capital source details
Central budget and other legal sources of capital
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Fourth quarter, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
12.Tender package No 12: Construction + installation of fire protection system equipment
Tender/ Prequalification Notice ID
Contract execution period
90 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Construction + installation of fire protection system equipment
Capital source details
Central budget and other legal sources of capital
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Quarter I, 2026
Type of contract
Fixed unit price
Prequalification
No
Implementation location (After merge)
13.Tender package No 13: Construction + installation of medium voltage line equipment + transformer station
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Construction + installation of medium voltage line equipment + transformer station
Capital source details
Central budget and other legal sources of capital
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Quarter I, 2026
Type of contract
Fixed unit price
Prequalification
No
Implementation location (After merge)

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Phieng Pan primary and secondary boarding school". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Phieng Pan primary and secondary boarding school" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 1

You did not use the site, Click here to remain logged. Timeout: 60 second