Bidder Selection Plan

Plan for contractor selection 02 works: Developing distribution grids in Tan Hoi Industrial Cluster, Tan Chau District in 2025 and anti -overloading distribution grid in Tan Chau district in 2025

  Watching      
Find: 20:07 01/07/2025
Contractor Selection Plan ID
PL2500158647-01
Publishing time
11:45 01/07/2025
Posting Status
Published
Contractor selection plan name
Plan for contractor selection 02 works: Developing distribution grids in Tan Hoi Industrial Cluster, Tan Chau District in 2025 and anti -overloading distribution grid in Tan Chau district in 2025
Investment objective
Ensuring the ability to supply electricity and retail directly to each customer in Tan Hoi 1 and 2 Industrial Cluster. Helps to balance the load on the 473th, 478th and 480th routes of TBA 110/22KV Tan Hung. Increase the number of customers, increase commercial electricity output and increase the average price. Reduce the number of power outages, improve electricity quality and reliability of electricity supply.
Project management forms
The investor directly manages the project
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
PR2500039090-00
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group C
Project implementation time
455 Date
Authority that issues the decision
Công ty Điện lực Tây Ninh
Approval date
23/06/2025
Approval ID
1160/QĐ-PCTN
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using Windows operating system and installing Client Agent software (Linux and MacOS operating systems cannot install Client software yet). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use DauThau.info software to download files.
To download, please Login or Register

Files with this icon are not supported by the public procurement system for direct download in normal mode. Visit DauThau.info and select Quick Download mode to download the file if you do not use Windows with Agent. DauThau.info supports downloading on most modern browsers and devices!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
Related announcements

- Change: Publication date (View changes)

Posted for the first time (View changes)

List of Bid:
Number of packages: 3
1.Construction of 02 works: Developing distribution grids in Tan Hoi Industrial Cluster, Tan Chau District in 2025 and anti -overloading the distribution grid in Tan Chau district in 2025
Tender/ Prequalification Notice ID
Contract execution period
90 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Summary of main tasks of the bid package
Construction and installation works
Capital source details
Customer capital, basic depreciation capital and commercial credit
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Second quarter, 2025
Type of contract
Fixed unit price
Prequalification
No
Implementation location (After merge)
Implementation location (Before merge)
Tây Ninh
2.Construction supervision: Developing distribution grids in Tan Hoi Industrial Cluster, Tan Chau District in 2025
Tender/ Prequalification Notice ID
Contract execution period
90 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Construction supervision and installation of works
Capital source details
Capital advance to customers
Contractor Selection Type
Do it yourself
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Third quarter, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Implementation location (Before merge)
Tây Ninh
3.Project supervision: Anti -overloading distribution grid in Tan Chau district in 2025
Tender/ Prequalification Notice ID
Contract execution period
90 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Construction supervision and installation of works
Capital source details
Basic depreciation capital and commercial credit
Contractor Selection Type
Do it yourself
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Third quarter, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Implementation location (Before merge)
Tây Ninh

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Plan for contractor selection 02 works: Developing distribution grids in Tan Hoi Industrial Cluster, Tan Chau District in 2025 and anti -overloading distribution grid in Tan Chau district in 2025". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Plan for contractor selection 02 works: Developing distribution grids in Tan Hoi Industrial Cluster, Tan Chau District in 2025 and anti -overloading distribution grid in Tan Chau district in 2025" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 4

You did not use the site, Click here to remain logged. Timeout: 60 second