Bidder Selection Plan

Plan for contractor selection phase 2

  Watching      
Find: 16:19 07/09/2023
Contractor Selection Plan ID
PL2300160301-00
Publishing time
16:06 07/09/2023
Posting Status
Published
Contractor selection plan name
Plan for contractor selection phase 2
Investment objective
Meet the training needs of PTC2's transformer station operation management staff and testing and repair staff of Technical Service Center 2 - Power Transmission Technical Services Company and operational management services of other Power Transmission Companies (if required)
Project management forms
The investor directly manages the project
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
PR2300042928-00
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group C
Project implementation time
2 Years
Location
Quang Binh Province-Quang Tri Province-Thua Thien Hue Province-Quang Nam Province-Quang Ngai Province-Kon Tum Province
Authority that issues the decision
Công ty Truyền tải điện 2
Approval date
07/09/2023
Approval ID
1096/QĐ-PTC2
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using the Windows operating system and needs to install Client Agent software (Linux and MacOS cannot download Client software yet). ). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use our DauThau.info.
Our system will help you download files faster, on any device without installing Client Agent.
To download, please Login or Register

File can only be downloaded on Windows computers using Agent, please see instructions here!!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
List of Bid:
Number of packages: 4
1.Package number 4: Construction insurance
Tender/ Prequalification Notice ID
Contract execution period
910 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
EVNNPT
Contractor Selection Type
Competitive Offer
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
October, 2023
Type of contract
All in One
Prequalification
No
Location
2.Package 5: Auditing the completed project settlement report
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
EVNNPT
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
March, 2024
Type of contract
All in One
Prequalification
No
Location
3.Tender package No 3: Construction supervision consultancy
Tender/ Prequalification Notice ID
Contract execution period
180 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
EVNNPT
Contractor Selection Type
Do it yourself
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
October, 2023
Type of contract
Is different
Prequalification
No
Location
4.Tender package No 2: Construction work
Tender/ Prequalification Notice ID
Contract execution period
180 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
EVNNPT
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
October, 2023
Type of contract
All in One
Prequalification
No
Location

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Plan for contractor selection phase 2". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Plan for contractor selection phase 2" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 20

You did not use the site, Click here to remain logged. Timeout: 60 second