Bidder Selection Plan

Plan for Phase 3 - An Khe 220kV substation project and connection

  Watching    
Project Contractor selection plan Tender notice Bid award
Find: 16:37 17/01/2023
Contractor Selection Plan ID
PL2300006892-00
Publishing time
16:34 17/01/2023
Posting Status
Published
Contractor selection plan name
Plan for Phase 3 - An Khe 220kV substation project and connection
Project management forms
Another form
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
20210966234-00
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group B
Authority that issues the decision
EVNNPT
Approval date
26/11/2021
Approval ID
1574/QĐ-EVNNPT
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using Windows operating system and installing Client Agent software (Linux and MacOS operating systems cannot install Client software yet). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use DauThau.info software to download files.
To download, please Login or Register

Files with this icon are not supported by the public procurement system for direct download in normal mode. Visit DauThau.info and select Quick Download mode to download the file if you do not use Windows with Agent. DauThau.info supports downloading on most modern browsers and devices!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
List of Bid:
Number of packages: 1
1.Tender package No 9: Supply and transport of VTTB and accessories (including conductors, lightning conductors, insulators, optical cables and accessories)
Tender/ Prequalification Notice ID
Contract execution period
210 days
Domestic/ International
International
Bidding method
Directly
Fields
Goods
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Loans and capital from EVNNPT (National Power Transmission Corporation)
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q2 2022
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
An Khê Town, Gia Lai

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Plan for Phase 3 - An Khe 220kV substation project and connection". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Plan for Phase 3 - An Khe 220kV substation project and connection" plan as soon as they are posted, sign up for DauThau.info's International VIP 2 plan.
Views: 23

You did not use the site, Click here to remain logged. Timeout: 60 second