Bidder Selection Plan
Plan for selecting contractor of Tra Khuc Bridge Project 1
Contractor Selection Plan ID
PL2500191624-02
Publishing time
11:48 03/09/2025
Contractor selection plan name
Plan for selecting contractor of Tra Khuc Bridge Project 1
Investment objective
Gradually improve the synchronous transportation network in the province in accordance with the approved plan, improve transport capacity, connect traffic from the northern gateway to the center of Quang Ngai city, promote the expansion and development of Quang Ngai city urban space in two directions of Tra Khuc River; Create a highlight of architectural space, build a symbol for Quang Ngai city to create a river urban development, changing the appearance and stature of Quang Ngai city in the future.
Project management forms
BQLDA major - area
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
PR2400000696-00
Spending Category
Investment and Development Spending
Project implementation time
4 Years
Authority that issues the decision
Ban Quản lý dự án đầu tư xây dựng các công trình Giao thông tỉnh Quảng Ngãi
Approval Documents
Downloading files directly on the new Public Procurement System requires a computer using Windows operating system and installing Client Agent software (Linux and MacOS operating systems cannot install Client software yet). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use DauThau.info software to download files. To download, please Login or Register
Files with this icon are not supported by the public procurement system for direct download in normal mode. Visit DauThau.info and select Quick Download mode to download the file if you do not use Windows with Agent . DauThau.info supports downloading on most modern browsers and devices! In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
List of Bid:
Number of packages: 22
1. Tender package No 06: Advice on contractor selection of the project to implement the project
Tender/ Prequalification Notice ID
Contract execution period
200 days
Domestic/ International
Domestic
Regulatory compliance
Bidding Law
The estimate of the bid package is approved after the approval of the LCA
Summary of main tasks of the bid package
Advice on selecting contractors for the project implementation package
Capital source details
The provincial budget (basic construction, overcoming and exploiting land funds)
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Third quarter, 2025
Type of contract
All in One
Implementation location (After merge)
2. Tender package No 07: Surveying, designing construction drawings and construction cost estimates
Tender/ Prequalification Notice ID
Contract execution period
120 days
Domestic/ International
Domestic
Regulatory compliance
Bidding Law
The estimate of the bid package is approved after the approval of the LCA
Summary of main tasks of the bid package
Survey, design construction drawings and construction cost estimates
Capital source details
The provincial budget (basic construction, overcoming and exploiting land funds)
Contractor Selection Type
Specify reference
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Third quarter, 2025
Type of contract
Fixed unit price
Implementation location (After merge)
3. Tender package No 08: Supervisor of surveying the construction drawing design step
Tender/ Prequalification Notice ID
Contract execution period
40 days
Domestic/ International
Domestic
Regulatory compliance
Bidding Law
The estimate of the bid package is approved after the approval of the LCA
Summary of main tasks of the bid package
Supervising and surveying the design and construction drawing steps
Capital source details
The provincial budget (basic construction, overcoming and exploiting land funds)
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Third quarter, 2025
Type of contract
Fixed unit price
Implementation location (After merge)
4. Tender package No 09: Consulting on setting up the project information model (BIM) steps to design construction drawings
Tender/ Prequalification Notice ID
Contract execution period
28 months
Domestic/ International
Domestic
Regulatory compliance
Bidding Law
Summary of main tasks of the bid package
Consulting on creating a project information model (BIM)
Capital source details
The provincial budget (basic construction, overcoming and exploiting land funds)
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Third quarter, 2025
Type of contract
All in One
Implementation location (After merge)
Tender/ Prequalification Notice ID
Contract execution period
70 days
Domestic/ International
Domestic
Regulatory compliance
Bidding Law
Summary of main tasks of the bid package
Valuation of all kinds of materials, materials and components not in the quotation of the Department of Construction
Capital source details
The provincial budget (basic construction, overcoming and exploiting land funds)
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Third quarter, 2025
Type of contract
All in One
Implementation location (After merge)
6. Package 11: Examination of construction drawing design and construction cost estimates
Tender/ Prequalification Notice ID
Contract execution period
90 days
Domestic/ International
Domestic
Regulatory compliance
Bidding Law
The estimate of the bid package is approved after the approval of the LCA
Summary of main tasks of the bid package
Verification of construction drawing design and construction cost estimate
Capital source details
The provincial budget (basic construction, overcoming and exploiting land funds)
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Third quarter, 2025
Type of contract
Fixed unit price
Implementation location (After merge)
7. Package 12: Traffic safety verification
Tender/ Prequalification Notice ID
Contract execution period
100 days
Domestic/ International
Domestic
Regulatory compliance
Bidding Law
Summary of main tasks of the bid package
Traffic safety inspection
Capital source details
The provincial budget (basic construction, overcoming and exploiting land funds)
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Third quarter, 2025
Type of contract
All in One
Implementation location (After merge)
8. Bidding package 13: Survey, set up the task of measuring and plugging in the land clearance
Tender/ Prequalification Notice ID
Contract execution period
20 days
Domestic/ International
Domestic
Regulatory compliance
Bidding Law
Summary of main tasks of the bid package
Survey, set up the task of measuring and plugging the land clearance
Capital source details
The provincial budget (basic construction, overcoming and exploiting land funds)
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Third quarter, 2025
Type of contract
All in One
Implementation location (After merge)
9. Package 14: Measure cadastral records and plug in the land clearance pile
Tender/ Prequalification Notice ID
Contract execution period
24 months
Domestic/ International
Domestic
Regulatory compliance
Bidding Law
Summary of main tasks of the bid package
Measure cadastral records and site deposits
Capital source details
The provincial budget (basic construction, overcoming and exploiting land funds)
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Third quarter, 2025
Type of contract
Fixed unit price
Implementation location (After merge)
10. Tender package No 15: Supervision of cadastral map measurement
Tender/ Prequalification Notice ID
Contract execution period
24 months
Domestic/ International
Domestic
Regulatory compliance
Bidding Law
Summary of main tasks of the bid package
Supervision of cadastral map measurement
Capital source details
The provincial budget (basic construction, overcoming and exploiting land funds)
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Third quarter, 2025
Type of contract
Fixed unit price
Implementation location (After merge)
11. Tender package No 16: Surveying and preparing a plan to clear mines and mines and explosives
Tender/ Prequalification Notice ID
Contract execution period
20 days
Domestic/ International
Domestic
Regulatory compliance
Bidding Law
Summary of main tasks of the bid package
Surveying and making plans to clear mines and explosives
Capital source details
The provincial budget (basic construction, overcoming and exploiting land funds)
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Third quarter, 2025
Type of contract
All in One
Implementation location (After merge)
12. Package 17: Construction of clearing mines and explosives
Tender/ Prequalification Notice ID
Contract execution period
40 days
Domestic/ International
Domestic
Regulatory compliance
Bidding Law
Summary of main tasks of the bid package
Construction of clearing mines and explosives
Capital source details
The provincial budget (basic construction, overcoming and exploiting land funds)
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Third quarter, 2025
Type of contract
Fixed unit price
Implementation location (After merge)
13. Package 18: Monitoring and clearing mines and explosives
Tender/ Prequalification Notice ID
Contract execution period
40 days
Domestic/ International
Domestic
Regulatory compliance
Bidding Law
Summary of main tasks of the bid package
Supervision of clearance of mines and explosives
Capital source details
The provincial budget (basic construction, overcoming and exploiting land funds)
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Third quarter, 2025
Type of contract
Fixed unit price
Implementation location (After merge)
14. Package 19: Making tasks of testing and loading quality tests
Tender/ Prequalification Notice ID
Contract execution period
20 days
Domestic/ International
Domestic
Regulatory compliance
Bidding Law
Summary of main tasks of the bid package
Make tasks to test the quality of the work and the bridge load test
Capital source details
The provincial budget (basic construction, overcoming and exploiting land funds)
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Quarter I, 2026
Type of contract
All in One
Implementation location (After merge)
15. Tender package No 20: Project quality testing and bridge load test
Tender/ Prequalification Notice ID
Contract execution period
24 months
Domestic/ International
Domestic
Regulatory compliance
Bidding Law
Summary of main tasks of the bid package
Quality testing of works and bridge load test
Capital source details
The provincial budget (basic construction, overcoming and exploiting land funds)
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Quarter I, 2026
Type of contract
Fixed unit price
Implementation location (After merge)
16. Tender package No 21: Establishing the task of bored pile test
Tender/ Prequalification Notice ID
Contract execution period
20 days
Domestic/ International
Domestic
Regulatory compliance
Bidding Law
Summary of main tasks of the bid package
Establish a test of bored pile tests
Capital source details
The provincial budget (basic construction, overcoming and exploiting land funds)
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Fourth quarter, 2025
Type of contract
Fixed unit price
Implementation location (After merge)
17. Tender package No 22: Bored pile test
Tender/ Prequalification Notice ID
Contract execution period
24 months
Domestic/ International
Domestic
Regulatory compliance
Bidding Law
Summary of main tasks of the bid package
Drilled pile test
Capital source details
The provincial budget (basic construction, overcoming and exploiting land funds)
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Fourth quarter, 2025
Type of contract
Fixed unit price
Implementation location (After merge)
18. Tender package No 23: Construction supervision
Tender/ Prequalification Notice ID
Contract execution period
24 months
Domestic/ International
Domestic
Regulatory compliance
Bidding Law
Summary of main tasks of the bid package
Supervision of construction works
Capital source details
The provincial budget (basic construction, overcoming and exploiting land funds)
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Fourth quarter, 2025
Type of contract
Fixed unit price
Implementation location (After merge)
19. Tender package No 24: Construction construction
Tender/ Prequalification Notice ID
Contract execution period
24 months
Domestic/ International
Domestic
Regulatory compliance
Bidding Law
Summary of main tasks of the bid package
Construction of the entire project (including equipment)
Capital source details
The provincial budget (basic construction, overcoming and exploiting land funds)
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Fourth quarter, 2025
Type of contract
According to adjusted unit price
Implementation location (After merge)
20. Tender package No 25: Construction insurance
Tender/ Prequalification Notice ID
Contract execution period
48 months
Domestic/ International
Domestic
Regulatory compliance
Bidding Law
Summary of main tasks of the bid package
Construction insurance
Capital source details
The provincial budget (basic construction, overcoming and exploiting land funds)
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Fourth quarter, 2025
Type of contract
By percentage
Implementation location (After merge)
21. Tender package No 26: Check the acceptance work
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Regulatory compliance
Bidding Law
Summary of main tasks of the bid package
Check the acceptance work
Capital source details
The provincial budget (basic construction, overcoming and exploiting land funds)
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Quarter IV, 2027
Type of contract
All in One
Implementation location (After merge)
22. Tender package No 27: Construction audit
Tender/ Prequalification Notice ID
Contract execution period
18 months
Domestic/ International
Domestic
Regulatory compliance
Bidding Law
Summary of main tasks of the bid package
Construction audit
Capital source details
The provincial budget (basic construction, overcoming and exploiting land funds)
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Second quarter, 2026
Type of contract
Fixed unit price
Implementation location (After merge)
Utilities for you:
Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Plan for selecting contractor of Tra Khuc Bridge Project 1". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Following
Receive similar invitation to bid by email
To be one of the
first to receive email notifications of contractor selection plans similar to the "Plan for selecting contractor of Tra Khuc Bridge Project 1" plan as soon as they are posted,
sign up for DauThau.info's VIP 2 plan.