Procurement name
Phuoc Trung Primary School
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Shopping budget
To view full information, please Login or Register
Spending Category
Mandatory spending
Authority that issues the decision
Trường Tiểu học Phước Trung
Approval date
24/12/2025
Approval ID
Số: 282/QĐ-THPT
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using Windows operating system and installing Client Agent software (Linux and MacOS operating systems cannot install Client software yet). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use DauThau.info software to download files.
To download, please Login or Register

Files with this icon are not supported by the public procurement system for direct download in normal mode. Visit DauThau.info and select Quick Download mode to download the file if you do not use Windows with Agent. DauThau.info supports downloading on most modern browsers and devices!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
List of Bid:
Number of packages: 1
1.Tender package No 1: Construction
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
- New roof: Demolish the concrete foundation, excavate the soil and pour concrete foundation. Fabrication and erection of steel columns, trusses and purlins. Roofed with square corrugated iron, installed gable light panels. - Hall stage background: Demolition of brick walls. Pour concrete. Build a wall. Plastering the outside wall. Three-level washed stone plastering. - Leveling the floor behind the classroom row: Leveling with soil. Install plastic pipes. - Window system of 2 classroom rows: Remove degraded doors. Install new aluminum glass frame doors. - Drainage system: Cut slots in the concrete yard floor. Demolition of concrete structures. Dig the soil. Install 220mm diameter plastic pipe. Backfill with soil, concrete and 1x2 stone foundation to return to current state. - Flower beds: Demolition of walls. Build a wall. Plastering the outside wall. Ceramic tiles.
Capital source details
The 2025 commune-level budget (education, training and vocational education budget, funding for other spending tasks) of the targeted supplementary provincial budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Fourth quarter, 2025
Type of contract
All in One
Implementation location
Prequalification
No

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Plan for selecting contractors for Phuoc Trung Primary School project". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Plan for selecting contractors for Phuoc Trung Primary School project" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 9

You did not use the site, Click here to remain logged. Timeout: 60 second