Bidder Selection Plan

plan for selecting contractors for several bidding packages, including design and construction drawings and project cost estimation: Construction of a road connecting the Ấp Tre and Đồng Vỡ residential areas to National Highway 35 in Quang Minh commune.

  Watching      
Project Contractor selection plan Tender notice Bid Opening Result Bid award
Find: 09:18 19/08/2026
Contractor Selection Plan ID
PL2600265953-00
Publishing time
09:16 19/08/2026
Posting Status
Published
Contractor selection plan name
plan for selecting contractors for several bidding packages, including design and construction drawings and project cost estimation: Construction of a road connecting the Ấp Tre and Đồng Vỡ residential areas to National Highway 35 in Quang Minh commune.
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
PR2600057483-00
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group B
Project implementation time
4 Years
Authority that issues the decision
Ban Quản lý dự án Đầu tư - Hạ tầng xã Quang Minh
Approval date
16/08/2026
Approval ID
687/QĐ-BQLDA
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using Windows operating system and installing Client Agent software (Linux and MacOS operating systems cannot install Client software yet). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use DauThau.info software to download files.
To download, please Login or Register

Files with this icon are not supported by the public procurement system for direct download in normal mode. Visit DauThau.info and select Quick Download mode to download the file if you do not use Windows with Agent. DauThau.info supports downloading on most modern browsers and devices!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
List of Bid:
Number of packages: 7
1.Package 1: Development of a tender document and evaluation of design proposals for the construction project.
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Develop a Request for Proposal (RFP) and evaluate proposals for design services for the construction of a wastewater treatment plant.
Capital source details
Town budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
August, 2026
Type of contract
All in One
Implementation location
Xã Quang Minh, City Hà Nội
Prequalification
No
2.Lot 2: Evaluation of bidding documents, and results of the tender for design consulting services for the construction project.
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Evaluation of the bidding documents, results of the tender for design services for the construction of a wastewater treatment plant (WWTP)
Capital source details
Town budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
August, 2026
Type of contract
All in One
Implementation location
Xã Quang Minh, City Hà Nội
Prequalification
No
3.Bidding package No. 3: Prepare construction drawing design - estimate
Tender/ Prequalification Notice ID
Contract execution period
90 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Design of construction drawings - estimates
Capital source details
Town budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
August, 2026
Type of contract
All in One
Implementation location
Xã Quang Minh, City Hà Nội
Prequalification
No
4.Bidding package No. 4: Verification of financial protection design - estimate
Tender/ Prequalification Notice ID
Contract execution period
90 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Verification of BVTC design - estimate
Capital source details
Town budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
August, 2026
Type of contract
All in One
Implementation location
Xã Quang Minh, City Hà Nội
Prequalification
No
5.Tender package No 5: Prepare land plot maps and place landmarks to serve site clearance
Tender/ Prequalification Notice ID
Contract execution period
90 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Prepare land clearing maps and place landmarks to serve site clearance
Capital source details
Town budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
August, 2026
Type of contract
All in One
Implementation location
Xã Quang Minh, City Hà Nội
Prequalification
No
6.Package 6: Appraisal of equipment
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Equipment cost appraisal
Capital source details
Town budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
August, 2026
Type of contract
All in One
Implementation location
Xã Quang Minh, City Hà Nội
Prequalification
No
7.Tender package No 7: Mine clearance
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Clearing mines
Capital source details
Town budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
August, 2026
Type of contract
All in One
Implementation location
Xã Quang Minh, City Hà Nội
Prequalification
No

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "plan for selecting contractors for several bidding packages, including design and construction drawings and project cost estimation: Construction of a road connecting the Ấp Tre and Đồng Vỡ residential areas to National Highway 35 in Quang Minh commune.". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "plan for selecting contractors for several bidding packages, including design and construction drawings and project cost estimation: Construction of a road connecting the Ấp Tre and Đồng Vỡ residential areas to National Highway 35 in Quang Minh commune." plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 4

You did not use the site, Click here to remain logged. Timeout: 60 second