Bidder Selection Plan
Plan to choose Hoa Lien NMN contractor
Contractor selection plan ID
20190850822-00
Publication date
13:57 20/08/2019
Publication status
Actual notification
Contractor selection plan name
Plan to choose Hoa Lien NMN contractor
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
20190308851-00
Spending Category
Investment and Development Project
QD status
There has been a decision to approve the investment project
List of Bid:
Number of packages: 11
1. Design, equipment supply and construction (EPC)
Tender/ Prequalification Notice ID
Domestic/ International
International
Funding source
city budget
Contractor Selection Type
Bidding widely, domestically, without prequalification, without online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2019
Contract Type
Package and Adjusted unit price
2. Making outline and project on surface water exploitation
Tender/ Prequalification Notice ID
Domestic/ International
International
Funding source
city budget
Contractor Selection Type
Bidding widely, domestically, without prequalification, without online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2019
3. Prepare outlines and plans for disaster response for works, downstream areas and emergency response
Tender/ Prequalification Notice ID
Domestic/ International
International
Funding source
city budget
Contractor Selection Type
Bidding widely, domestically, without prequalification, without online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2019
Tender/ Prequalification Notice ID
Domestic/ International
International
Funding source
city budget
Contractor Selection Type
Bidding widely, domestically, without prequalification, without online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2019
5. Periodic environmental monitoring reports during the construction phase
Tender/ Prequalification Notice ID
Domestic/ International
International
Funding source
city budget
Contractor Selection Type
Appointment of short-term, domestic contractors, no prequalification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2019
6. Verification of construction drawing design - cost estimate
Tender/ Prequalification Notice ID
Domestic/ International
International
Funding source
city budget
Contractor Selection Type
Bidding widely, domestically, without prequalification, without online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2019
7. Construction supervision and equipment installation
Tender/ Prequalification Notice ID
Domestic/ International
International
Funding source
city budget
Contractor Selection Type
Bidding widely, domestically, without prequalification, without online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2019
8. Piles static compression test
Tender/ Prequalification Notice ID
Domestic/ International
International
Funding source
city budget
Contractor Selection Type
Appointment of short-term, domestic contractors, no prequalification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2019
Tender/ Prequalification Notice ID
Domestic/ International
International
Funding source
city budget
Contractor Selection Type
Bidding widely, domestically, without prequalification, without online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2019
Tender/ Prequalification Notice ID
Domestic/ International
International
Funding source
city budget
Contractor Selection Type
Bidding widely, domestically, without prequalification, online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2020
11. Equipment cost appraisal
Tender/ Prequalification Notice ID
Domestic/ International
International
Funding source
city budget
Contractor Selection Type
Appointment of short-term, domestic contractors, no prequalification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2019
Utilities for you:
Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Plan to choose Hoa Lien NMN contractor". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Following
Receive similar invitation to bid by email