Contractor Selection Plan ID
20211064236-00
Publishing time
09:23 07/09/2022
Posting Status
Published
Contractor selection plan name
Plan to select contractor for investment project to upgrade and expand U Minh - Khanh Hoi route
Project management forms
Another form
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
20220245655-00
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group C
Location
Authority that issues the decision
N/A
Approval date
22/10/2021
Approval ID
576/QĐ-UBND ngày 24/02/2022
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using the Windows operating system and needs to install Client Agent software (Linux and MacOS cannot download Client software yet). ). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use our DauThau.info.
Our system will help you download files faster, on any device without installing Client Agent.
To download, please Login or Register

File can only be downloaded on Windows computers using Agent, please see instructions here!!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
Related announcements

- Change: Publication date, Bidding package information (View changes)

- Change: Publication date (View changes)

- Change: Investor, Bidding package number, Publication date, Bidding package information (View changes)

- Change: Publication date (View changes)

- Change: Publication date, Bidding package information (View changes)

- Change: Publication date, Bidding package information (View changes)

- Change: Publication date, Bidding package information (View changes)

- Change: Approval date, Approval ID, Publication date (View changes)

- Change: Lowest bid price, Publication date, Bidding package information (View changes)

- Change: Publication date, Bidding package information (View changes)

- Change: Publication date, Bidding package information (View changes)

Posted for the first time (View changes)

List of Bid:
Number of packages: 17
1.Tender package No 46: Construction supervision for the package No. 50
Tender/ Prequalification Notice ID
Contract execution period
510 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Capital source details
Government budget and provincial budget support in the medium-term public investment plan for the period 2021-2025
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q3 2022
Type of contract
All in One
Prequalification
No
Location
2.Package 03: Surveying topography, geology and making construction drawing design – construction cost estimate of the route from Km 0+000 to Km 14+000
Tender/ Prequalification Notice ID
Contract execution period
70 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
The central budget supports and the provincial budget in the medium-term public investment plan for the period 2021-2025, the capital plan in 2022 is assigned in Decision No. 2759/QD-UBND dated December 7, 2021
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q1 2022
Type of contract
All in One
Prequalification
No
Location
3.Tender package No 27: Supervision of construction works for package No. 30
Tender/ Prequalification Notice ID
Contract execution period
540 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Government budget and provincial budget support in the medium-term public investment plan for the period 2021-2025
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q3 2022
Type of contract
All in One
Prequalification
No
Location
4.Package 25: Supervision of construction works for package No. 28
Tender/ Prequalification Notice ID
Contract execution period
540 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Government budget and provincial budget support in the medium-term public investment plan for the period 2021-2025
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q3 2022
Type of contract
All in One
Prequalification
No
Location
5.Tender package No 48: Construction supervision for package No. 52
Tender/ Prequalification Notice ID
Contract execution period
510 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Government budget and provincial budget support in the medium-term public investment plan for the period 2021-2025
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q3 2022
Type of contract
All in One
Prequalification
No
Location
6.Tender package No 47: Construction supervision for package No. 51
Tender/ Prequalification Notice ID
Contract execution period
510 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Government budget and provincial budget support in the medium-term public investment plan for the period 2021-2025
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q4 2022
Type of contract
All in One
Prequalification
No
Location
7.Package 36: Audit of investment capital for the whole project
Tender/ Prequalification Notice ID
Contract execution period
90 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Government budget and provincial budget support in the medium-term public investment plan for the period 2021-2025
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q4 2022
Type of contract
All in One
Prequalification
No
Location
8.Package 28: Construction of the section of the route from Km 0+000 to Km 0+720 (including roads and rainwater drainage system)
Tender/ Prequalification Notice ID
Contract execution period
540 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Government budget and provincial budget support in the medium-term public investment plan for the period 2021-2025
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q3 2022
Type of contract
Fixed unit price
Prequalification
No
Location
9.Package 01: Surveying the topography and making a feasibility study report for construction work
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Government budget and provincial budget support in the medium-term public investment plan for the period 2021-2025
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q4 2021
Type of contract
All in One
Prequalification
No
Location
10.Package 29: Construction of the section from Km 0+900 to Km 2+260
Tender/ Prequalification Notice ID
Contract execution period
540 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Government budget and provincial budget support in the medium-term public investment plan for the period 2021-2025
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q3 2022
Type of contract
Fixed unit price
Prequalification
No
Location
11.Package 52: Construction of the section from Km 9+000 to Km 14+000 (including rainwater drainage system)
Tender/ Prequalification Notice ID
Contract execution period
510 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Government budget and provincial budget support in the medium-term public investment plan for the period 2021-2025
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q3 2022
Type of contract
Fixed unit price
Prequalification
No
Location
12.Package 51: Construction of the section from Km 7+060 to Km 9+000 (including Ba Mu bridge)
Tender/ Prequalification Notice ID
Contract execution period
510 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Government budget and provincial budget support in the medium-term public investment plan for the period 2021-2025
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q4 2022
Type of contract
Fixed unit price
Prequalification
No
Location
13.Package 50: Construction of the section from Km 4+080 to Km 7+060 (including Muoi Quan bridge)
Tender/ Prequalification Notice ID
Contract execution period
510 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Government budget and provincial budget support in the medium-term public investment plan for the period 2021-2025
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q3 2022
Type of contract
Fixed unit price
Prequalification
No
Location
14.Package 30: Construction of the section from Km 2+260 to Km 3+000 (including Kenh Hau bridge)
Tender/ Prequalification Notice ID
Contract execution period
540 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Government budget and provincial budget support in the medium-term public investment plan for the period 2021-2025
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q3 2022
Type of contract
Fixed unit price
Prequalification
No
Location
15.Tender package No 45: Construction supervision for package No. 49
Tender/ Prequalification Notice ID
Contract execution period
510 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Government budget and provincial budget support in the medium-term public investment plan for the period 2021-2025
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q4 2022
Type of contract
All in One
Prequalification
No
Location
16.Package 26: Supervision of construction works for package No. 29
Tender/ Prequalification Notice ID
Contract execution period
540 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Government budget and provincial budget support in the medium-term public investment plan for the period 2021-2025
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q3 2022
Type of contract
All in One
Prequalification
No
Location
17.Package 49: Construction of the section from Km 3+000 to Km 4+080 (including Cay Bang bridge)
Tender/ Prequalification Notice ID
Contract execution period
510 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Government budget and provincial budget support in the medium-term public investment plan for the period 2021-2025
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q4 2022
Type of contract
Fixed unit price
Prequalification
No
Location

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Plan to select contractor for investment project to upgrade and expand U Minh - Khanh Hoi route". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Plan to select contractor for investment project to upgrade and expand U Minh - Khanh Hoi route" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 108

Greeting
Greeting,
You are not logged in, please log in to use our various functions for members.

You can use your account on DauThau.info to log in to Dauthau.Net, and vice versa!

If you are still not our member, please sign up.

Only 5 minutes and absolutely free! Your account can be use on all over our ecosystem, including DauThau.info and DauThau.Net.

Search for bid information
Click for advanced search
Statistical
  • 8533 Projects are waiting for contractors
  • 144 Tender notices posted in the last 24 hours
  • 156 Contractor selection plan posted in the last 24 hours
  • 23681 Tender notices posted in the past month
  • 37139 Contractor selection plan posted in the last month
Consultants are supporting you
You are not logged in.
To view information, please Login or Register if you do not have an account.
Signing up is simple and completely free.
You did not use the site, Click here to remain logged. Timeout: 60 second