Bidder Selection Plan

Plan to select contractor for the project of Renovating and upgrading Hong Ky A primary school

  Watching      
Find: 11:37 11/06/2022
Contractor selection plan ID
20220154150-01
Publication date
11:32 11/06/2022
Publication status
Actual notification
Contractor selection plan name
Plan to select contractor for the project of Renovating and upgrading Hong Ky A primary school
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
20220154074-00
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Project
QD status
There has been a decision to approve the investment project
Location
Approval date
17/01/2022
Approval ID
837/QĐ-UBND; 5527/QĐ-UBND ngày 10/6/2022 điều chỉnh KHLCNT
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using the Windows operating system and needs to install Client Agent software (Linux and MacOS cannot download Client software yet). ). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use our DauThau.info.
Our system will help you download files faster, on any device without installing Client Agent.
To download, please Login or Register

Related announcements

- Change: Notification form, Highest bid price, Approval ID, Publication date, Bidding package information (View changes)

Posted for the first time (View changes)

List of Bid:
Number of packages: 8
1.Bidding package No. 5: Consulting on making bidding documents, evaluating bid packages for bidding packages
Tender/ Prequalification Notice ID
Contract Period
45 days
Domestic/ International
International
Bidding method
Directly
Fields
Advise
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
District budget, City budget support and other funding
Contractor Selection Type
Short appointment of contractors, no pre-qualification domestically, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2022
Contract Type
All in one
Prequalification
No
Location
2.Tender package No 6: Consulting on setting up construction drawing design
Tender/ Prequalification Notice ID
Contract Period
90 days
Domestic/ International
International
Bidding method
Online
Fields
Advise
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
District budget, City budget support and other funding
Contractor Selection Type
Open bidding, domestic without pre-qualification, online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2022
Contract Type
All in one
Prequalification
No
Location
3.Package 7: Consultancy and verification of construction drawing design and cost estimate
Tender/ Prequalification Notice ID
Contract Period
60 days
Domestic/ International
International
Bidding method
Directly
Fields
Advise
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
District budget, City budget support and other funding
Contractor Selection Type
Short appointment of contractors, no pre-qualification domestically, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2022
Contract Type
All in one
Prequalification
No
Location
4.Tender package No 8: Design appraisal
Tender/ Prequalification Notice ID
Contract Period
90 days
Domestic/ International
International
Bidding method
Directly
Fields
Advise
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
District budget, City budget support and other funding
Contractor Selection Type
Short appointment of contractors, no pre-qualification domestically, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2022
Contract Type
All in one
Prequalification
No
Location
5.Package 10: Supervision of construction and equipment installation
Tender/ Prequalification Notice ID
Contract Period
270 days
Domestic/ International
International
Bidding method
Online
Fields
Advise
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
District budget, City budget support and other funding
Contractor Selection Type
Open bidding, domestic without pre-qualification, online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q2 2022
Contract Type
All in one
Prequalification
No
Location
6.Tender package No 11: Construction Insurance
Tender/ Prequalification Notice ID
Contract Period
635 days
Domestic/ International
International
Bidding method
Directly
Fields
Non-consulting
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
District budget, City budget support and other funding
Contractor Selection Type
Short appointment of contractors, no pre-qualification domestically, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q2 2022
Contract Type
All in one
Prequalification
No
Location
7.Tender package No 9: Construction of building blocks: 2, 3, 5, 7 and construction and installation, fire protection equipment
Tender/ Prequalification Notice ID
Contract Period
270 days
Domestic/ International
International
Bidding method
Online
Fields
Civil Works
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
District budget, City budget support and other funding
Contractor Selection Type
Open bidding, domestic without pre-qualification, online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q2 2022
Contract Type
All in one
Prequalification
No
Location
8.Package 12: Construction and renovation of houses No. 4, 6, 13 and technical and auxiliary infrastructure items, procurement of school equipment, electrical equipment
Tender/ Prequalification Notice ID
Contract Period
270 days
Domestic/ International
International
Bidding method
Online
Fields
Civil Works
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
District budget, City budget support and other funding
Contractor Selection Type
Open bidding, domestic without pre-qualification, online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q2 2022
Contract Type
All in one
Prequalification
No
Location

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Plan to select contractor for the project of Renovating and upgrading Hong Ky A primary school". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Plan to select contractor for the project of Renovating and upgrading Hong Ky A primary school" plan as soon as they are posted, sign up for DauThau.info's International VIP 2 plan.
Views: 58

You did not use the site, Click here to remain logged. Timeout: 60 second