Bidder Selection Plan

Plan to select contractor for the road construction project connecting the satellite urban area with Vo Nguyen Giap street, Soc Son district

  Watching      
Find: 17:04 06/07/2020
Contractor selection plan ID
20200533935-01
Publication date
17:00 06/07/2020
Publication status
Actual notification
Contractor selection plan name
Plan to select contractor for the road construction project connecting the satellite urban area with Vo Nguyen Giap street, Soc Son district
Investor
Ủy ban nhân dân huyện Sóc Sơn
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
PR2300058002-00
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Project
QD status
There has been a decision to approve the investment project
Location
Approval date
12/05/2020
Approval ID
397/QĐ-KHĐT
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using the Windows operating system and needs to install Client Agent software (Linux and MacOS cannot download Client software yet). ). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use our DauThau.info.
Our system will help you download files faster, on any device without installing Client Agent.
To download, please Login or Register

Related announcements

- Change: Notification form, Publication date, Bidding package information (View changes)

- Change: Highest bid price, Publication date (View changes)

Posted for the first time (View changes)

List of Bid:
Number of packages: 12
1.Bidding package No. 12: Consulting on setting up bidding documents, evaluating bids for construction and installation bidding packages and supervising construction and installation
Tender/ Prequalification Notice ID
Contract Period
60 days
Domestic/ International
International
Bidding method
Directly
Fields
Advise
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
city budget
Contractor Selection Type
Appointment of short-term, domestic contractors, no prequalification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q2 2020
Contract Type
All in one
Prequalification
No
Location
2.Package 13: The entire construction and installation section from Km0+00 to Km0+819
Tender/ Prequalification Notice ID
Contract Period
360 days
Domestic/ International
International
Bidding method
Online
Fields
Civil Works
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
city budget
Contractor Selection Type
Bidding widely, domestically, without prequalification, online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q2 2020
Contract Type
All in one
Prequalification
No
Location
3.Package 14: The entire construction and installation part from Km1+284.2 to Km1+700
Tender/ Prequalification Notice ID
Contract Period
360 days
Domestic/ International
International
Bidding method
Online
Fields
Civil Works
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
city budget
Contractor Selection Type
Bidding widely, domestically, without prequalification, online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q2 2020
Contract Type
All in one
Prequalification
No
Location
4.Package 15: The entire construction and installation section from Km1+700 to Km2+320
Tender/ Prequalification Notice ID
Contract Period
360 days
Domestic/ International
International
Bidding method
Online
Fields
Civil Works
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
city budget
Contractor Selection Type
Bidding widely, domestically, without prequalification, online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q2 2020
Contract Type
All in one
Prequalification
No
Location
5.Package 16: The entire construction and installation part from Km2+320 to Km3+080
Tender/ Prequalification Notice ID
Contract Period
360 days
Domestic/ International
International
Bidding method
Online
Fields
Civil Works
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
city budget
Contractor Selection Type
Bidding widely, domestically, without prequalification, online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q2 2020
Contract Type
All in one
Prequalification
No
Location
6.Package 17: The entire construction and installation part from Km3+080 to Km3+930.1
Tender/ Prequalification Notice ID
Contract Period
360 days
Domestic/ International
International
Bidding method
Online
Fields
Civil Works
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
city budget
Contractor Selection Type
Bidding widely, domestically, without prequalification, online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q2 2020
Contract Type
All in one
Prequalification
No
Location
7.Package 18: The entire construction and installation of VNG road intersection - Segment 1 (branch 1, Km0+00÷Km0+507 branch 2, branch of National Highway 18-2)
Tender/ Prequalification Notice ID
Contract Period
360 days
Domestic/ International
International
Bidding method
Online
Fields
Civil Works
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
city budget
Contractor Selection Type
Bidding widely, domestically, without prequalification, online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q2 2020
Contract Type
All in one
Prequalification
No
Location
8.Package 19: The entire construction and installation of VNG road intersection - Segment 2 (Km0+507÷Km0+976.77 branch 2, branch 3, 4, 5, branch of National Highway 18-1, 2 branches connecting VNG)
Tender/ Prequalification Notice ID
Contract Period
360 days
Domestic/ International
International
Bidding method
Online
Fields
Civil Works
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
city budget
Contractor Selection Type
Bidding widely, domestically, without prequalification, online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q2 2020
Contract Type
All in one
Prequalification
No
Location
9.Package 20: The entire construction and installation of the overpass on National Highway 18
Tender/ Prequalification Notice ID
Contract Period
360 days
Domestic/ International
International
Bidding method
Online
Fields
Civil Works
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
city budget
Contractor Selection Type
Bidding widely, domestically, without prequalification, online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q2 2020
Contract Type
All in one
Prequalification
No
Location
10.Package 21: The entire construction and installation of traffic safety and trees
Tender/ Prequalification Notice ID
Contract Period
360 days
Domestic/ International
International
Bidding method
Online
Fields
Civil Works
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
city budget
Contractor Selection Type
Bidding widely, domestically, without prequalification, online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q2 2020
Contract Type
All in one
Prequalification
No
Location
11.Tender package No 22: The entire construction and installation of lighting and equipment
Tender/ Prequalification Notice ID
Contract Period
360 days
Domestic/ International
International
Bidding method
Online
Fields
Civil Works
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
city budget
Contractor Selection Type
Bidding widely, domestically, without prequalification, online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q2 2020
Contract Type
All in one
Prequalification
No
Location
12.Tender package No 23: Supervision of construction works
Tender/ Prequalification Notice ID
Contract Period
360 days
Domestic/ International
International
Bidding method
Online
Fields
Advise
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
city budget
Contractor Selection Type
Bidding widely, domestically, without prequalification, online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q2 2020
Contract Type
All in one
Prequalification
No
Location

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Plan to select contractor for the road construction project connecting the satellite urban area with Vo Nguyen Giap street, Soc Son district". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Plan to select contractor for the road construction project connecting the satellite urban area with Vo Nguyen Giap street, Soc Son district" plan as soon as they are posted, sign up for DauThau.info's International VIP 2 plan.
Views: 279

Greeting
Greeting,
You are not logged in, please log in to use our various functions for members.

You can use your account on DauThau.info to log in to Dauthau.Net, and vice versa!

If you are still not our member, please sign up.

Only 5 minutes and absolutely free! Your account can be use on all over our ecosystem, including DauThau.info and DauThau.Net.

Search for bid information
Click for advanced search
Statistical
  • 8550 Projects are waiting for contractors
  • 418 Tender notices posted in the last 24 hours
  • 431 Contractor selection plan posted in the last 24 hours
  • 24860 Tender notices posted in the past month
  • 38641 Contractor selection plan posted in the last month
Consultants are supporting you
You are not logged in.
To view information, please Login or Register if you do not have an account.
Signing up is simple and completely free.
You did not use the site, Click here to remain logged. Timeout: 60 second