Bidder Selection Plan

Plan to select the project contractor to take advantage of emissions to generate electricity - Kien Luong Cement Factory

  Watching      
Find: 10:29 17/03/2025
Contractor Selection Plan ID
PL2500048322-00
Publishing time
10:29 17/03/2025
Posting Status
Published
Contractor selection plan name
Plan to select the project contractor to take advantage of emissions to generate electricity - Kien Luong Cement Factory
Investment objective
1. Recall and take full advantage of the waste heat sources of cement production lines for electricity generation; 2. Minimize dust pollution, heat pollution in the factory environment and reduce CO2 emissions converted to contribute to the national environmental protection strategy; 3. Part of the electricity is required for the production of the whole factory; 4. Comply with the provisions of the Prime Minister of Vietnam on the development strategy of Vietnam construction materials in the 2021-2030 period, orientation to 2050.
Project management forms
The investor directly manages the project
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
PR2500011960-00
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group B
Project implementation time
16 Month
Authority that issues the decision
Hội đồng Quản trị Công ty cổ phần Xi măng VICEM Hà Tiên
Approval date
12/03/2025
Approval ID
12/03/QĐ-HĐQT
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using Windows operating system and installing Client Agent software (Linux and MacOS operating systems cannot install Client software yet). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use DauThau.info software to download files.
To download, please Login or Register

Files with this icon are not supported by the public procurement system for direct download in normal mode. Visit DauThau.info and select Quick Download mode to download the file if you do not use Windows with Agent. DauThau.info supports downloading on most modern browsers and devices!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
List of Bid:
Number of packages: 9
1.Package 1 - Design, supply of goods and construction (EPC)
Tender/ Prequalification Notice ID
Contract execution period
16 months
Domestic/ International
International
Bidding method
Directly
Fields
Uncategoried
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Survey for design and construction surveys; Provide and translate technical documents and design documents of the project; Design and approval of fire prevention and fighting; Supplying materials, imported equipment and technical services; Carry out equipment inspection; Import tax; Customs clearance services imported and transporting equipment from the port to the project; Procurement of domestic equipment and materials, construction; Construction of fire protection system; Processing equipment on the spot; and other related work of the bidding package.
Capital source details
Own capital and commercial loan
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Quarter I, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Kiên Lương District, An Giang
Implementation location (Before merge)
Tỉnh Kiên Giang
2.Package 2 - Construction insurance
Tender/ Prequalification Notice ID
Contract execution period
12 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Insurance for material losses of the building during construction time
Capital source details
Equity capital
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Second quarter, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Kiên Lương District, An Giang
Implementation location (Before merge)
Tỉnh Kiên Giang
3.Tender package No 3 - Auditing settlement of investment capital investment capital completed
Tender/ Prequalification Notice ID
Contract execution period
2 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Auditing settlement of project investment capital completed
Capital source details
Equity capital
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Second quarter, 2026
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Kiên Lương District, An Giang
Implementation location (Before merge)
Tỉnh Kiên Giang
4.Bidding package No. 4 - Preparation of records, applying to adjust the electricity purchase agreement
Tender/ Prequalification Notice ID
Contract execution period
2 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Prepare records, please adjust the electricity purchase agreement
Capital source details
Equity capital
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Second quarter, 2026
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Kiên Lương District, An Giang
Implementation location (Before merge)
Tỉnh Kiên Giang
5.Tender package No 5 - Supervisory consultancy
Tender/ Prequalification Notice ID
Contract execution period
12 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Construction supervision, processing supervision of non -standard equipment and equipment installation for the entire project (including monitoring and installation of fire prevention and fighting system)
Capital source details
Equity capital
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Second quarter, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Kiên Lương District, An Giang
Implementation location (Before merge)
Tỉnh Kiên Giang
6.Package 6 - Making Bidding Bidding Tender package No 1
Tender/ Prequalification Notice ID
Contract execution period
2 months
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Making bidding documents for package 1 - Designing, supplying goods and construction
Capital source details
Equity capital
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Quarter I, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Kiên Lương District, An Giang
Implementation location (Before merge)
Tỉnh Kiên Giang
7.Bidding package No. 7-Design examination
Tender/ Prequalification Notice ID
Contract execution period
2 months
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Including construction design verification (after basic design) and technological design verification (after the basic design)
Capital source details
Equity capital
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Second quarter, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Kiên Lương District, An Giang
Implementation location (Before merge)
Tỉnh Kiên Giang
8.Bidding package No. 8-Check the settlement of investment capital investment capital
Tender/ Prequalification Notice ID
Contract execution period
2 months
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Verification of final settlement of investment project investment
Capital source details
Equity capital
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Second quarter, 2026
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Kiên Lương District, An Giang
Implementation location (Before merge)
Tỉnh Kiên Giang
9.Tender package No 9 - Construction quality testing
Tender/ Prequalification Notice ID
Contract execution period
12 months
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Quality testing works
Capital source details
Equity capital
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Third quarter, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Kiên Lương District, An Giang
Implementation location (Before merge)
Tỉnh Kiên Giang

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Plan to select the project contractor to take advantage of emissions to generate electricity - Kien Luong Cement Factory". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Plan to select the project contractor to take advantage of emissions to generate electricity - Kien Luong Cement Factory" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 115

You did not use the site, Click here to remain logged. Timeout: 60 second