Planning and development for the bidding packages under the Project of Supplementing and upgrading phase 2 of the production control camera system of Vinh Tan 4 Thermal Power Plant
Planning and development for the bidding packages under the Project of Supplementing and upgrading phase 2 of the production control camera system of Vinh Tan 4 Thermal Power Plant
Downloading files directly on the new Public Procurement System requires a computer using the Windows operating system and needs to install Client Agent software (Linux and MacOS cannot download Client software yet). ). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use our DauThau.info. Our system will help you download files faster, on any device without installing Client Agent. To download, please Login or Register
5. QD phe duyet KHLCNT - Camera.pdf
List of Bid:
Number of packages: 2
1.Package 09: Supply and install Additional, upgrade phase 2 camera system for production control of Vinh Tan 4 Thermal Power Plant
Open bidding, domestic without pre-qualification, online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2022
Contract Type
All in one
Prequalification
No
Location
2.Package 10: Consulting, installation supervision, supplementing and upgrading phase 2 of the production control camera system at Vinh Tan 4 Thermal Power Plant
Open bidding, domestic without pre-qualification, online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2022
Contract Type
All in one
Prequalification
No
Location
Utilities for you:
Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Planning and development for the bidding packages under the Project of Supplementing and upgrading phase 2 of the production control camera system of Vinh Tan 4 Thermal Power Plant". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Planning and development for the bidding packages under the Project of Supplementing and upgrading phase 2 of the production control camera system of Vinh Tan 4 Thermal Power Plant" plan as soon as they are posted, sign up for DauThau.info's International VIP 2 plan.