Bidder Selection Plan

Planning for contractor selection during the project implementation and supporting land acquisition activities: Construction of a road from the Dong Do apartment complex to Xuan Tao street (as per the plan).

  Watching      
Project Contractor selection plan Tender notice Bid Opening Result Bid award
Find: 14:35 10/08/2026
Contractor Selection Plan ID
PL2600251378-00
Publishing time
14:33 10/08/2026
Posting Status
Published
Contractor selection plan name
Planning for contractor selection during the project implementation and supporting land acquisition activities: Construction of a road from the Dong Do apartment complex to Xuan Tao street (as per the plan).
Project management forms
The investor directly manages the project
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
PR2600054552-00
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group C
Project implementation time
2 Years
Authority that issues the decision
UBND phường Nghĩa Đô
Approval date
03/08/2026
Approval ID
289/QĐ-UBND
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using Windows operating system and installing Client Agent software (Linux and MacOS operating systems cannot install Client software yet). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use DauThau.info software to download files.
To download, please Login or Register

Files with this icon are not supported by the public procurement system for direct download in normal mode. Visit DauThau.info and select Quick Download mode to download the file if you do not use Windows with Agent. DauThau.info supports downloading on most modern browsers and devices!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
List of Bid:
Number of packages: 10
1.Package 6: Consulting services for preparing an Electronic Health System (EHS) and evaluating a Construction Package.
Tender/ Prequalification Notice ID
Contract execution period
45 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Consulting E-HSMT, E-HSDT Bidding package for construction and installation
Capital source details
Ward budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
In the third quarter, 2026
Type of contract
All in One
Implementation location
Phường Nghĩa Đô, City Hà Nội
Prequalification
No
2.Lot 7: Consulting and evaluation of E-HSMT (Electronic Procurement System), and evaluation of the results of selecting contractors for construction packages.
Tender/ Prequalification Notice ID
Contract execution period
45 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
E-HSMT appraisal consultancy, evaluation of the results of the contractor selection of construction and installation package
Capital source details
Ward budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
In the third quarter, 2026
Type of contract
All in One
Implementation location
Phường Nghĩa Đô, City Hà Nội
Prequalification
No
3.Tender package No 8: Construction supervision consultancy
Tender/ Prequalification Notice ID
Contract execution period
360 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Construction supervision consultancy
Capital source details
Ward budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
In the third quarter, 2026
Type of contract
All in One
Implementation location
Phường Nghĩa Đô, City Hà Nội
Prequalification
No
4.Tender package No 9: Construction
Tender/ Prequalification Notice ID
Contract execution period
360 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Construction
Capital source details
Ward budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
In the third quarter, 2026
Type of contract
All in One
Implementation location
Phường Nghĩa Đô, City Hà Nội
Prequalification
No
5.Contract No. 10: Consulting services for surveying, developing a plan for relocating electrical and lighting systems.
Tender/ Prequalification Notice ID
Contract execution period
35 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Consulting services for site surveys, development of electrical and lighting system relocation plans.
Capital source details
Ward budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
In the third quarter, 2026
Type of contract
All in One
Implementation location
Phường Nghĩa Đô, City Hà Nội
Prequalification
No
6.Procurement Tender package No 11: Consulting services for assessing and evaluating relocation plans for the electrical and lighting systems.
Tender/ Prequalification Notice ID
Contract execution period
20 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Consultation on assessing the feasibility of relocating the electrical and lighting system.
Capital source details
Ward budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
In the third quarter, 2026
Type of contract
All in One
Implementation location
Phường Nghĩa Đô, City Hà Nội
Prequalification
No
7.Contract No. 12: Consulting services for surveying and developing a water supply system relocation plan.
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Consulting services for site surveys and development of a water supply system relocation plan.
Capital source details
Ward budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
In the third quarter, 2026
Type of contract
All in One
Implementation location
Phường Nghĩa Đô, City Hà Nội
Prequalification
No
8.Contract No. 13: Consulting services for assessing relocation options for the water supply system.
Tender/ Prequalification Notice ID
Contract execution period
20 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Consultation on assessing the feasibility of relocating the water supply system.
Capital source details
Ward budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
In the third quarter, 2026
Type of contract
All in One
Implementation location
Phường Nghĩa Đô, City Hà Nội
Prequalification
No
9.Contract No. 14: Consulting services for surveying and developing a plan to relocate the information and telecommunications system.
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Consulting services for site surveys, development of plans for relocating information and telecommunications systems.
Capital source details
Ward budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
In the third quarter, 2026
Type of contract
All in One
Implementation location
Phường Nghĩa Đô, City Hà Nội
Prequalification
No
10.Procurement Tender package No 15: Consulting services for assessing and evaluating relocation plans for information and telecommunications systems.
Tender/ Prequalification Notice ID
Contract execution period
20 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Consulting services for assessing the feasibility of relocating the information and telecommunications system.
Capital source details
Ward budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
In the third quarter, 2026
Type of contract
All in One
Implementation location
Phường Nghĩa Đô, City Hà Nội
Prequalification
No

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Planning for contractor selection during the project implementation and supporting land acquisition activities: Construction of a road from the Dong Do apartment complex to Xuan Tao street (as per the plan).". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Planning for contractor selection during the project implementation and supporting land acquisition activities: Construction of a road from the Dong Do apartment complex to Xuan Tao street (as per the plan)." plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 0

You did not use the site, Click here to remain logged. Timeout: 60 second