Bidder Selection Plan

Project contractor selection plan: Building Thanh Tan Primary School, Thanh Tan Commune, Thach Thanh District

  Watching      
Find: 10:42 12/09/2025
Contractor Selection Plan ID
PL2500219548-01
Publishing time
10:40 12/09/2025
Posting Status
Published
Contractor selection plan name
Project contractor selection plan: Building Thanh Tan Primary School, Thanh Tan Commune, Thach Thanh District
Investment objective
Step by step improve facilities, strive to meet national standard level 2; create conditions for teachers and students to feel secure teaching and learning, gradually improving the quality of education, improving knowledge, contributing to socio -economic development in the locality
Project management forms
BQLDA major - area
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
PR2500047936-01
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group C
Project implementation time
3 Years
Authority that issues the decision
Uỷ ban nhân dân xã Vân du
Approval date
09/09/2025
Approval ID
466/QĐ-UBND
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using Windows operating system and installing Client Agent software (Linux and MacOS operating systems cannot install Client software yet). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use DauThau.info software to download files.
To download, please Login or Register

Files with this icon are not supported by the public procurement system for direct download in normal mode. Visit DauThau.info and select Quick Download mode to download the file if you do not use Windows with Agent. DauThau.info supports downloading on most modern browsers and devices!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
Related announcements

- Change: Lowest bid price, Publication date, Bidding package information (View changes)

- Change: Approval date, Approval ID, Publication date, Bidding package information (View changes)

- Change: Decision-making agency, Approval date, Approval ID, Publication date, Bidding package information (View changes)

Posted for the first time (View changes)

List of Bid:
Number of packages: 7
1.Package 01: Design consultancy BVTC-DT
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Design BVTC-DT
Capital source details
The provincial budget supports notice No. 7889/TBSTC dated December 25, 2024 of the Department of Finance of Thanh Hoa Province is VND 20.7 billion; The rest from the district budget and mobilizing other legal sources.
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Second quarter, 2025
Type of contract
All in One
Implementation location
Prequalification
No
2.Tender package No 02: Consultancy for verification of design and cost estimate
Tender/ Prequalification Notice ID
Contract execution period
15 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Design verification and construction estimate
Capital source details
The provincial budget supports notice No. 7889/TBSTC dated December 25, 2024 of the Department of Finance of Thanh Hoa Province is VND 20.7 billion; The rest from the district budget and mobilizing other legal sources.
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Second quarter, 2025
Type of contract
All in One
Implementation location
Prequalification
No
3.Package 03: Consulting for E-HSMT preparation, E-HSDT evaluation
Tender/ Prequalification Notice ID
Contract execution period
90 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
E-HSMT, E-HSDT assessment of consulting and construction bidding packages, equipment
Capital source details
The provincial budget supports notice No. 7889/TBSTC dated December 25, 2024 of the Department of Finance of Thanh Hoa Province is VND 20.7 billion; The rest from the district budget and mobilizing other legal sources.
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Second quarter, 2025
Type of contract
All in One
Implementation location
Prequalification
No
4.Tender package No 04: Construction and supply and installation of equipment
Tender/ Prequalification Notice ID
Contract execution period
360 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Construction under design approved and supplying and installing equipment
Capital source details
The provincial budget supports notice No. 7889/TBSTC dated December 25, 2024 of the Department of Finance of Thanh Hoa Province is VND 20.7 billion; The rest from the district budget and mobilizing other legal sources.
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Third quarter, 2025
Type of contract
All in One
Implementation location
Prequalification
No
5.Tender package No 05: Supervision consultancy
Tender/ Prequalification Notice ID
Contract execution period
360 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Construction supervision and equipment installation
Capital source details
The provincial budget supports notice No. 7889/TBSTC dated December 25, 2024 of the Department of Finance of Thanh Hoa Province is VND 20.7 billion; The rest from the district budget and mobilizing other legal sources.
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Second quarter, 2025
Type of contract
All in One
Implementation location
Prequalification
No
6.Package 06: Insurance
Tender/ Prequalification Notice ID
Contract execution period
360 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Construction insurance
Capital source details
The provincial budget supports notice No. 7889/TBSTC dated December 25, 2024 of the Department of Finance of Thanh Hoa Province is VND 20.7 billion; The rest from the district budget and mobilizing other legal sources.
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Third quarter, 2025
Type of contract
All in One
Implementation location
Prequalification
No
7.Package 07: Audit
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Completed project audit
Capital source details
The provincial budget supports notice No. 7889/TBSTC dated December 25, 2024 of the Department of Finance of Thanh Hoa Province is VND 20.7 billion; The rest from the district budget and mobilizing other legal sources.
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Second quarter, 2025
Type of contract
All in One
Implementation location
Prequalification
No

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Project contractor selection plan: Building Thanh Tan Primary School, Thanh Tan Commune, Thach Thanh District". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Project contractor selection plan: Building Thanh Tan Primary School, Thanh Tan Commune, Thach Thanh District" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 16

You did not use the site, Click here to remain logged. Timeout: 60 second