Bidder Selection Plan

Project contractor selection plan: Electrical resistance 500KV Refund strategic backup

  Watching      
Project Contractor selection plan Tender notice Bid Opening Result Bid award
Find: 08:23 08/05/2025
Contractor Selection Plan ID
PL2500083353-01
Publishing time
08:13 08/05/2025
Posting Status
Published
Contractor selection plan name
Project contractor selection plan: Electrical resistance 500KV Refund strategic backup
Investment objective
- Returning EVNNPT's strategic backup device has transferred to the 500kV 300KV ĐZ 3 to ensure sufficient quantity according to the norm and response that can be transferred to the key grid projects with urgent progress. - Preventing the national electricity transmission system to take the initiative for operating methods. - Contribute to ensuring safe and reliable power transmission systems to meet the country's socio -economic development needs.
Project management forms
The investor directly manages the project
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
PR2500020991-02
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group C
Project implementation time
8 Month
Authority that issues the decision
PTC1
Approval date
06/05/2025
Approval ID
1342/QĐ-PTC1
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using Windows operating system and installing Client Agent software (Linux and MacOS operating systems cannot install Client software yet). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use DauThau.info software to download files.
To download, please Login or Register

Files with this icon are not supported by the public procurement system for direct download in normal mode. Visit DauThau.info and select Quick Download mode to download the file if you do not use Windows with Agent. DauThau.info supports downloading on most modern browsers and devices!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
Related announcements

- Change: Total investment, total investment, Lowest bid price, Highest bid price, Approval date, Approval ID, Publication date, Bidding package information (View changes)

Posted for the first time (View changes)

List of Bid:
Number of packages: 2
1.Tender package No 1: Supply and transportation of 500kV - 120MVAr resistors
Tender/ Prequalification Notice ID
Contract execution period
210 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Goods
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Supply and transport of 500kV - 120MVAr resistors
Capital source details
EVNNPT
Contractor Selection Type
Direct shopping
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Second quarter, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Implementation location (Before merge)
Thành phố Đà Nẵng
2.Package 2: Auditing the completed project settlement report
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Audit of completed project settlement reports
Capital source details
EVNNPT
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Fourth quarter, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Implementation location (Before merge)
Thành phố Hà Nội

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Project contractor selection plan: Electrical resistance 500KV Refund strategic backup". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Project contractor selection plan: Electrical resistance 500KV Refund strategic backup" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 8

You did not use the site, Click here to remain logged. Timeout: 60 second