Bidder Selection Plan
Project contractor selection plan for improving cement grinding capacity at Kien Luong Cement Factory.
Contractor selection plan ID
20211109236-00
Publication date
13:28 05/11/2021
Publication status
Actual notification
Contractor selection plan name
Project contractor selection plan for improving cement grinding capacity at Kien Luong Cement Factory.
Investor
Project Management Department of Ha Tien 1 Cement Joint stock company
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
20211108927-00
Spending Category
Investment and Development Project
QD status
There has been a decision to approve the investment project
Approval ID
01/11/QĐ-HĐQT
Approval Documents
Downloading files directly on the new Public Procurement System requires a computer using Windows operating system and installing Client Agent software (Linux and MacOS operating systems cannot install Client software yet). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use DauThau.info software to download files. To download, please Login or Register
2021-11-03 so 01-11 QD PD KHLCNT DA NCNLKL FNCNLKL.pdf
List of Bid:
Number of packages: 39
1. Tender package No 1 – Providing design, equipment, materials and technical services
Tender/ Prequalification Notice ID
Contract Period
20 months
Domestic/ International
International
Funding source
Loan + Own capital
Contractor Selection Type
Open, international bidding without pre-qualification, not online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2021
2. Package 2 - Construction of items in the stage of receiving, storing, homogenizing and transporting raw materials
Tender/ Prequalification Notice ID
Contract Period
11 months
Domestic/ International
International
Funding source
Loan + Own capital
Contractor Selection Type
Open bidding, domestic, no pre-qualification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2022
Contract Type
According to fixed unit price
3. Package 3 - Construction of main work items (except for cement silos)
Tender/ Prequalification Notice ID
Contract Period
11 months
Domestic/ International
International
Funding source
Loan + Own capital
Contractor Selection Type
Open bidding, domestic, no pre-qualification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2022
Contract Type
According to fixed unit price
4. Package 4 - Construction of cement silo
Tender/ Prequalification Notice ID
Contract Period
11 months
Domestic/ International
International
Funding source
Loan + Own capital
Contractor Selection Type
Open bidding, domestic, no pre-qualification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2022
Contract Type
According to fixed unit price
5. Tender package No 5 - Construction of port works
Tender/ Prequalification Notice ID
Contract Period
11 months
Domestic/ International
International
Funding source
Loan + Own capital
Contractor Selection Type
Open bidding, domestic, no pre-qualification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2022
Contract Type
According to fixed unit price
6. Package 6 - Construction of auxiliary items (demolition of old works, construction of drainage ditches, toilets, internal traffic systems, storage yards)
Tender/ Prequalification Notice ID
Contract Period
11 months
Domestic/ International
International
Funding source
Loan + Own capital
Contractor Selection Type
Open bidding, domestic, no pre-qualification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2022
Contract Type
According to fixed unit price
7. Tender package No 7 - Domestic procurement
Tender/ Prequalification Notice ID
Contract Period
10 months
Domestic/ International
International
Funding source
Loan + Own capital
Contractor Selection Type
Open bidding, domestic, no pre-qualification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q2 2022
Contract Type
According to fixed unit price
8. Tender package No 8 - Processing, manufacturing and installing equipment
Tender/ Prequalification Notice ID
Contract Period
10 months
Domestic/ International
International
Funding source
Loan + Own capital
Contractor Selection Type
Open bidding, domestic, no pre-qualification, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2022
9. Package 9 - Survey for design
Tender/ Prequalification Notice ID
Domestic/ International
International
Funding source
Self-possessed
Contractor Selection Type
Open bidding, domestic without pre-qualification, online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2022
Contract Type
According to fixed unit price
10. Package 10 - Estimating construction and equipment designed by foreign countries
Tender/ Prequalification Notice ID
Domestic/ International
International
Funding source
Self-possessed
Contractor Selection Type
Open bidding, domestic without pre-qualification, online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q2 2022
11. Package 11 - Port construction design
Tender/ Prequalification Notice ID
Domestic/ International
International
Funding source
Self-possessed
Contractor Selection Type
Open bidding, domestic without pre-qualification, online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2021
12. Package 12 - Design verification, cost estimate of foreign-designed items
Tender/ Prequalification Notice ID
Domestic/ International
International
Funding source
Self-possessed
Contractor Selection Type
Open bidding, domestic without pre-qualification, online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2022
13. Package 13 - Construction supervision and equipment installation (except port construction)
Tender/ Prequalification Notice ID
Contract Period
16 months
Domestic/ International
International
Funding source
Self-possessed
Contractor Selection Type
Open bidding, domestic without pre-qualification, online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2022
14. Package 14 - Construction supervision of port construction
Tender/ Prequalification Notice ID
Contract Period
11 months
Domestic/ International
International
Funding source
Self-possessed
Contractor Selection Type
Open bidding, domestic without pre-qualification, online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2022
15. Package 15 - Inspection and quality control of works, specialized experiments and deformation monitoring of works
Tender/ Prequalification Notice ID
Contract Period
20 months
Domestic/ International
International
Funding source
Self-possessed
Contractor Selection Type
Open bidding, domestic without pre-qualification, online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2022
16. Package 16 - Project completion audit
Tender/ Prequalification Notice ID
Domestic/ International
International
Funding source
Self-possessed
Contractor Selection Type
Open bidding, domestic without pre-qualification, online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
1st Quarter 2024
17. Package 17 - Independent inspection of imported equipment
Tender/ Prequalification Notice ID
Domestic/ International
International
Funding source
Self-possessed
Contractor Selection Type
Open bidding, domestic without pre-qualification, online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q2 2022
18. Tender package No 18 - Purchase Insurance for Construction and Equipment
Tender/ Prequalification Notice ID
Contract Period
16 months
Domestic/ International
International
Funding source
Self-possessed
Contractor Selection Type
Open bidding, domestic without pre-qualification, online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2022
19. Tender package No 19 - Loading and unloading, transporting equipment
Tender/ Prequalification Notice ID
Domestic/ International
International
Funding source
Self-possessed
Contractor Selection Type
Open bidding, domestic without pre-qualification, online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q2 2022
20. Package 20 - Consulting on importing equipment, materials and technical services
Tender/ Prequalification Notice ID
Contract Period
16 months
Domestic/ International
International
Funding source
Self-possessed
Contractor Selection Type
Open bidding, domestic without pre-qualification, online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2021
21. Package 21 - Supply and installation of fire protection equipment (Firefighting)
Tender/ Prequalification Notice ID
Domestic/ International
International
Funding source
Self-possessed
Contractor Selection Type
Open bidding, domestic without pre-qualification, online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2022
22. Package 22 - Supply design, equipment and installation of online monitoring equipment
Tender/ Prequalification Notice ID
Domestic/ International
International
Funding source
Self-possessed
Contractor Selection Type
Open bidding, domestic without pre-qualification, online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2023
23. Package 23 - Supply of equipment and installation of connection to the Scada . system
Tender/ Prequalification Notice ID
Domestic/ International
International
Funding source
Self-possessed
Contractor Selection Type
Open bidding, domestic without pre-qualification, online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2023
24. Package 24 - Design and construction of auxiliary items (demolition of old works, construction of drainage ditches, toilets, internal traffic systems, storage yards)
Tender/ Prequalification Notice ID
Domestic/ International
International
Funding source
Self-possessed
Contractor Selection Type
Open bidding, domestic without pre-qualification, online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2021
25. Tender package No 25 - Verification of construction drawing design, port construction estimate
Tender/ Prequalification Notice ID
Domestic/ International
International
Funding source
Self-possessed
Contractor Selection Type
Short appointment of contractors, no pre-qualification domestically, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2022
26. Package 26 - Verification of construction drawing design, cost estimate of auxiliary items and internal roads
Tender/ Prequalification Notice ID
Domestic/ International
International
Funding source
Self-possessed
Contractor Selection Type
Short appointment of contractors, no pre-qualification domestically, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q2 2022
27. Tender package No 27 - Design to connect with Scada . system
Tender/ Prequalification Notice ID
Domestic/ International
International
Funding source
Self-possessed
Contractor Selection Type
Short appointment of contractors, no pre-qualification domestically, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2022
28. Tender package No 28 - Survey for port design
Tender/ Prequalification Notice ID
Domestic/ International
International
Funding source
Self-possessed
Contractor Selection Type
Short appointment of contractors, no pre-qualification domestically, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2021
29. Tender package No 29 - Verification and approval of investment capital settlement
Tender/ Prequalification Notice ID
Domestic/ International
International
Funding source
Self-possessed
Contractor Selection Type
Short appointment of contractors, no pre-qualification domestically, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
1st Quarter 2024
30. Package 30 - Converting construction investment costs to the time of handing over, putting into operation and use
Tender/ Prequalification Notice ID
Domestic/ International
International
Funding source
Self-possessed
Contractor Selection Type
Short appointment of contractors, no pre-qualification domestically, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2023
31. Bidding Tender package No 31 - Prepare bidding documents for international bidding packages
Tender/ Prequalification Notice ID
Domestic/ International
International
Funding source
Self-possessed
Contractor Selection Type
Short appointment of contractors, no pre-qualification domestically, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2021
32. Tender package No 32 - Prepare bidding documents for Domestic Procurement, Fabrication and Equipment Installation
Tender/ Prequalification Notice ID
Domestic/ International
International
Funding source
Self-possessed
Contractor Selection Type
Short appointment of contractors, no pre-qualification domestically, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q2 2022
33. Package 33 - Update design documents of station 110 according to the requirements of the power industry
Tender/ Prequalification Notice ID
Domestic/ International
International
Funding source
Self-possessed
Contractor Selection Type
Short appointment of contractors, no pre-qualification domestically, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2022
34. Tender package No 34 - Testing of 110 kV current transformer, 110 kV . substation switching procedures
Tender/ Prequalification Notice ID
Domestic/ International
International
Funding source
Self-possessed
Contractor Selection Type
Short appointment of contractors, no pre-qualification domestically, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q2 2023
35. Tender package No 35 - Verification of specialized designs for substations
Tender/ Prequalification Notice ID
Domestic/ International
International
Funding source
Self-possessed
Contractor Selection Type
Short appointment of contractors, no pre-qualification domestically, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2023
36. Tender package No 36 - Agreement on power supply planning for 110kV . substations
Tender/ Prequalification Notice ID
Domestic/ International
International
Funding source
Self-possessed
Contractor Selection Type
Short appointment of contractors, no pre-qualification domestically, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2022
37. Tender package No 37 - Fire protection design
Tender/ Prequalification Notice ID
Domestic/ International
International
Funding source
Self-possessed
Contractor Selection Type
Short appointment of contractors, no pre-qualification domestically, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q2 2022
38. Tender package No 38 - Verification of construction drawing design, cost estimate of fire prevention and fighting and submission of fire protection design for approval
Tender/ Prequalification Notice ID
Domestic/ International
International
Funding source
Self-possessed
Contractor Selection Type
Short appointment of contractors, no pre-qualification domestically, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2022
39. Tender package No 39 - Translation of foreign documents
Tender/ Prequalification Notice ID
Contract Period
15 months
Domestic/ International
International
Funding source
Self-possessed
Contractor Selection Type
Short appointment of contractors, no pre-qualification domestically, no online
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2022
Utilities for you:
Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Project contractor selection plan for improving cement grinding capacity at Kien Luong Cement Factory.". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Following
Receive similar invitation to bid by email
To be one of the
first to receive email notifications of contractor selection plans similar to the "Project contractor selection plan for improving cement grinding capacity at Kien Luong Cement Factory." plan as soon as they are posted,
sign up for DauThau.info's International VIP 2 plan.