Bidder Selection Plan

Project contractor selection plan: Moving high voltage, medium voltage, low voltage lines, substations to serve site clearance for the project: Road connecting National Highway 279 - Chieng Sinh commune center

  Watching      
Find: 17:15 08/12/2025
Contractor Selection Plan ID
PL2500331459-00
Publishing time
17:14 08/12/2025
Posting Status
Published
Contractor selection plan name
Project contractor selection plan: Moving high voltage, medium voltage, low voltage lines, substations to serve site clearance for the project: Road connecting National Highway 279 - Chieng Sinh commune center
Project management forms
The investor directly manages the project
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
PR2500067015-00
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group C
Project implementation time
2 Years
Authority that issues the decision
Ban Quản lý dự án và Phát triển quỹ đất khu vực 3
Approval date
08/12/2025
Approval ID
110/QĐ-BQLDAKV3
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using Windows operating system and installing Client Agent software (Linux and MacOS operating systems cannot install Client software yet). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use DauThau.info software to download files.
To download, please Login or Register

Files with this icon are not supported by the public procurement system for direct download in normal mode. Visit DauThau.info and select Quick Download mode to download the file if you do not use Windows with Agent. DauThau.info supports downloading on most modern browsers and devices!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
List of Bid:
Number of packages: 3
1.Prepare bidding documents and evaluate bidding documents for the bidding package for construction and relocation of power lines
Tender/ Prequalification Notice ID
Contract execution period
40 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Prepare bidding documents and evaluate bids in accordance with the provisions of the Bidding Law
Capital source details
Capital source for site clearance compensation costs of the project Connecting National Highway 279 - Chieng Sinh commune center, approved by the Provincial People's Committee in Decision No. 2347/QD-UBND
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Fourth quarter, 2025
Type of contract
All in One
Implementation location
Prequalification
No
2.Construction of electric lines
Tender/ Prequalification Notice ID
Contract execution period
8 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Construction of items in approved financial protection documents
Capital source details
Capital source for site clearance compensation costs of the project Connecting National Highway 279 - Chieng Sinh commune center, approved by the Provincial People's Committee in Decision No. 2347/QD-UBND
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Fourth quarter, 2025
Type of contract
Fixed unit price
Implementation location
Prequalification
No
3.Supervision of electricity movement
Tender/ Prequalification Notice ID
Contract execution period
8 months
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Supervise construction work of construction contractors, ensuring quality, progress, safety and environmental sanitation
Capital source details
Capital source for site clearance compensation costs of the project Connecting National Road 279 - Chieng Sinh commune center, approved by the Provincial People's Committee in Decision No. 2347/QD-UBND dated October 6, 2025
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Fourth quarter, 2025
Type of contract
All in One
Implementation location
Prequalification
No

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Project contractor selection plan: Moving high voltage, medium voltage, low voltage lines, substations to serve site clearance for the project: Road connecting National Highway 279 - Chieng Sinh commune center". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Project contractor selection plan: Moving high voltage, medium voltage, low voltage lines, substations to serve site clearance for the project: Road connecting National Highway 279 - Chieng Sinh commune center" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 28

You did not use the site, Click here to remain logged. Timeout: 60 second