Downloading files directly on the new Public Procurement System requires a computer using the Windows operating system and needs to install Client Agent software (Linux and MacOS cannot download Client software yet). ). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use our DauThau.info. Our system will help you download files faster, on any device without installing Client Agent. To download, please Login or Register
03. QĐ KHLCNT.pdf
File can only be downloaded on Windows computers using Agent, please see instructions here!! In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
List of Bid:
Number of packages: 6
1.Package 57/2024 - Construction Investment - MS - Risk Investment: Procurement of equipment for the project of new construction of substations in Bac Tu Liem district in 2024, phase 1
2.Package 58/2024 - Construction Investment - MS - Risk Investment: Procurement of materials for the project of new construction of substations in Bac Tu Liem district in 2024, phase 1
3.Package 59/2024 - Construction Investment - TN - TTH: Electrical testing project New construction of substations in Bac Tu Liem district in 2024, phase 1 (C30)
4.Package 60/2024 - Construction Investment - KD - TTH: Electrical inspection and testing of the project New construction of substations in Bac Tu Liem district in 2024, phase 1 (X5)
5.Package 61/2024 - Construction Investment - GS - TTH: Construction supervision of the project of new construction of substations in Bac Tu Liem district in 2024, phase 1
6.Package 62/2024 - Construction Investment - Construction - Risk Investment: Construction of project to build new substations in Bac Tu Liem district in 2024, phase 1
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Project contractor selection plan: New construction of substations in Bac Tu Liem district in 2024, phase 1". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Project contractor selection plan: New construction of substations in Bac Tu Liem district in 2024, phase 1" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.