Bidder Selection Plan
Project contractor selection plan: renovating and upgrading Phuc Tho District General Hospital
Contractor Selection Plan ID
PL2500022720-00
Publishing time
16:39 13/02/2025
Contractor selection plan name
Project contractor selection plan: renovating and upgrading Phuc Tho District General Hospital
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
PR2500005609-00
Spending Category
Investment and Development Spending
Project implementation time
2 Years
Authority that issues the decision
Sở Kế hoạch và Đầu tư thành phố Hà Nội
Approval Documents
Downloading files directly on the new Public Procurement System requires a computer using Windows operating system and installing Client Agent software (Linux and MacOS operating systems cannot install Client software yet). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use DauThau.info software to download files. To download, please Login or Register
Files with this icon are not supported by the public procurement system for direct download in normal mode. Visit DauThau.info and select Quick Download mode to download the file if you do not use Windows with Agent . DauThau.info supports downloading on most modern browsers and devices! In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
List of Bid:
Number of packages: 18
1. Package 06: Testing and evaluating the status of the work
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Regulatory compliance
Bidding Law
Summary of main tasks of the bid package
Inspect and evaluate the current state of the project
Capital source details
Hanoi city budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Quarter I, 2025
Type of contract
All in One
Implementation location (After merge)
Implementation location (Before merge)
Ha Noi city
2. Tender package No 07: Geological survey drilling in the period of TKBVTC
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Regulatory compliance
Bidding Law
Summary of main tasks of the bid package
Drilling for geological survey in the period of TKBVTC
Capital source details
Hanoi city budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Quarter I, 2025
Type of contract
All in One
Implementation location (After merge)
Implementation location (Before merge)
Ha Noi city
3. Tender package No 08: Supervision of geological survey drilling
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Regulatory compliance
Bidding Law
Summary of main tasks of the bid package
Geological survey drilling supervision
Capital source details
Hanoi city budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Quarter I, 2025
Type of contract
All in One
Implementation location (After merge)
Implementation location (Before merge)
Ha Noi city
4. Package 09: Construction drawing design and cost estimate
Tender/ Prequalification Notice ID
Contract execution period
150 days
Domestic/ International
Domestic
Regulatory compliance
Bidding Law
Summary of main tasks of the bid package
Design construction drawings and cost estimates
Capital source details
Hanoi city budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Quarter I, 2025
Type of contract
All in One
Implementation location (After merge)
Implementation location (Before merge)
Ha Noi city
5. Package 10: Making Bidding Documents, evaluating Bid Bids Tender package No 9
Tender/ Prequalification Notice ID
Contract execution period
45 days
Domestic/ International
Domestic
Regulatory compliance
Bidding Law
Summary of main tasks of the bid package
Preparation of Bid Documents, evaluation of bids for package No. 9
Capital source details
Hanoi city budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Quarter I, 2025
Type of contract
All in One
Implementation location (After merge)
Implementation location (Before merge)
Ha Noi city
6. Package 11: Verification of construction drawing design and cost estimate
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Regulatory compliance
Bidding Law
Summary of main tasks of the bid package
Verification of construction drawing design and cost estimate
Capital source details
Hanoi city budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Quarter I, 2025
Type of contract
All in One
Implementation location (After merge)
Implementation location (Before merge)
Ha Noi city
7. Package 12: Construction and fire prevention system
Tender/ Prequalification Notice ID
Contract execution period
550 days
Domestic/ International
Domestic
Regulatory compliance
Bidding Law
Summary of main tasks of the bid package
Construction and fire protection system
Capital source details
Hanoi city budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Third quarter, 2025
Type of contract
Package and Fixed Price
Implementation location (After merge)
Implementation location (Before merge)
Ha Noi city
8. Bidding Tender package No 13: Prepare Bid Documents, Evaluate Bid Tender package No 12
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Regulatory compliance
Bidding Law
Summary of main tasks of the bid package
Prepare Bidding Documents, evaluate bids for package No. 12
Capital source details
Hanoi city budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Third quarter, 2025
Type of contract
All in One
Implementation location (After merge)
Implementation location (Before merge)
Ha Noi city
9. Package 14: Construction supervision
Tender/ Prequalification Notice ID
Contract execution period
550 days
Domestic/ International
Domestic
Regulatory compliance
Bidding Law
Summary of main tasks of the bid package
Construction supervision
Capital source details
Hanoi city budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Third quarter, 2025
Type of contract
All in One
Implementation location (After merge)
Implementation location (Before merge)
Ha Noi city
10. Bidding Tender package No 15: Prepare Bid Documents, Evaluate Bid Tender package No 14
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Regulatory compliance
Bidding Law
Summary of main tasks of the bid package
Prepare bidding documents and evaluate bidding documents for package No. 14
Capital source details
Hanoi city budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Third quarter, 2025
Type of contract
All in One
Implementation location (After merge)
Implementation location (Before merge)
Ha Noi city
11. Package 16: Supply and installation of medical equipment
Tender/ Prequalification Notice ID
Contract execution period
210 days
Domestic/ International
Domestic
Regulatory compliance
Bidding Law
Summary of main tasks of the bid package
Supply and installation of medical equipment
Capital source details
Hanoi city budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Quarter I, 2026
Type of contract
All in One
Implementation location (After merge)
Implementation location (Before merge)
Ha Noi city
12. Bidding Tender package No 17: Prepare Bid Documents, Evaluate Bid Tender package No 16
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Regulatory compliance
Bidding Law
Summary of main tasks of the bid package
Making Bidding Documents, evaluating Bid Bids Package 16
Capital source details
Hanoi city budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Quarter I, 2026
Type of contract
All in One
Implementation location (After merge)
Implementation location (Before merge)
Ha Noi city
13. Tender package No 18: Monitoring and installing medical equipment
Tender/ Prequalification Notice ID
Contract execution period
210 days
Domestic/ International
Domestic
Regulatory compliance
Bidding Law
Summary of main tasks of the bid package
Supervision of installation of medical equipment
Capital source details
Hanoi city budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Quarter I, 2026
Type of contract
All in One
Implementation location (After merge)
Implementation location (Before merge)
Ha Noi city
14. Tender package No 19: Equipment certificate
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Regulatory compliance
Bidding Law
Summary of main tasks of the bid package
Create a Device Certificate
Capital source details
Hanoi city budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Quarter I, 2025
Type of contract
All in One
Implementation location (After merge)
Implementation location (Before merge)
Ha Noi city
15. Package 20: Consulting for static compression of piles
Tender/ Prequalification Notice ID
Contract execution period
45 days
Domestic/ International
Domestic
Regulatory compliance
Bidding Law
Summary of main tasks of the bid package
Consulting Piles Static Compression
Capital source details
Hanoi city budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Third quarter, 2025
Type of contract
All in One
Implementation location (After merge)
Implementation location (Before merge)
Ha Noi city
16. Tender package No 21: Construction insurance
Tender/ Prequalification Notice ID
Contract execution period
550 days
Domestic/ International
Domestic
Regulatory compliance
Bidding Law
Summary of main tasks of the bid package
Construction insurance
Capital source details
Hanoi city budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Third quarter, 2025
Type of contract
By percentage
Implementation location (After merge)
Implementation location (Before merge)
Ha Noi city
17. Tender package No 22: Independent Audit
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Regulatory compliance
Bidding Law
Summary of main tasks of the bid package
Independent audit
Capital source details
Hanoi city budget
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Fourth quarter, 2026
Type of contract
All in One
Implementation location (After merge)
Implementation location (Before merge)
Ha Noi city
18. Package 23: Making Bidding Documents, evaluating Bid Bids package No. 22
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Regulatory compliance
Bidding Law
Summary of main tasks of the bid package
Prepare bidding documents and evaluate bidding documents for package No. 22
Capital source details
Hanoi city budget
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Fourth quarter, 2026
Type of contract
All in One
Implementation location (After merge)
Implementation location (Before merge)
Ha Noi city
Utilities for you:
Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Project contractor selection plan: renovating and upgrading Phuc Tho District General Hospital". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Following
Receive similar invitation to bid by email
To be one of the
first to receive email notifications of contractor selection plans similar to the "Project contractor selection plan: renovating and upgrading Phuc Tho District General Hospital" plan as soon as they are posted,
sign up for DauThau.info's VIP 2 plan.