Bidder Selection Plan

Project contractor selection plan: Vi Thanh city resettlement area (phase 2)

  Watching      
Find: 19:06 24/06/2024
Contractor Selection Plan ID
PL2300168266-04
Publishing time
15:54 24/06/2024
Posting Status
Published
Contractor selection plan name
Project contractor selection plan: Vi Thanh city resettlement area (phase 2)
Bid Solicitor
Investor
Investment objective
Synchronous construction of infrastructure, subdivision of ground lots for resettlement according to regulations
Project management forms
The investor hires a project management consultant
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
PR2300041432-00
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group B
Project implementation time
3 Years
Authority that issues the decision
UBND tỉnh Hậu Giang
Approval date
07/06/2024
Approval ID
804/QĐ-UBND
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using Windows operating system and installing Client Agent software (Linux and MacOS operating systems cannot install Client software yet). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use DauThau.info software to download files.
To download, please Login or Register

Files with this icon are not supported by the public procurement system for direct download in normal mode. Visit DauThau.info and select Quick Download mode to download the file if you do not use Windows with Agent. DauThau.info supports downloading on most modern browsers and devices!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
Related announcements

- Change: Publication date, Bidding package information (View changes)

- Change: Publication date (View changes)

- Change: Publication date, Bidding package information (View changes)

- Change: Total investment, Highest bid price, Approval date, Approval ID, Publication date, Bidding package information (View changes)

Posted for the first time (View changes)

List of Bid:
Number of packages: 23
1.Project management consultancy
Tender/ Prequalification Notice ID
Contract execution period
720 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Capital of the Provincial Development Investment Fund and other lawful capital sources
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q3 2023
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Vị Thanh City, Cần Thơ
Implementation location (Before merge)
Hau Giang province
2.Geological survey consultancy, construction drawing design and cost estimate
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Capital source details
Capital from the Provincial Development Investment Fund and other legal capital sources
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q3 2023
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Vị Thanh City, Cần Thơ
Implementation location (Before merge)
Hau Giang province
3.Supervision of geological survey work
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Capital source details
Capital from the Provincial Development Investment Fund and other legal capital sources
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2023
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Vị Thanh City, Cần Thơ
Implementation location (Before merge)
Hau Giang province
4.Verification of construction designs and estimates
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Capital from the Provincial Development Investment Fund and other legal capital sources
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2023
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Vị Thanh City, Cần Thơ
Implementation location (Before merge)
Hau Giang province
5.Construction and equipment installation
Tender/ Prequalification Notice ID
Contract execution period
400 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Construction includes the following items: Ground leveling; Road system; Park - green trees; Rainwater drainage system; Wastewater collection system; Water supply and fire protection systems; Wastewater treatment area; Box culvert; Power supply system; Lighting system; equipment installation
Capital source details
Capital from the Provincial Development Investment Fund and other legal capital sources
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2024
Type of contract
Fixed unit price
Prequalification
No
Implementation location (After merge)
Vị Thanh City, Cần Thơ
Implementation location (Before merge)
Hau Giang province
6.Consultancy of construction supervision and equipment installation
Tender/ Prequalification Notice ID
Contract execution period
400 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Consultancy of construction supervision and equipment installation
Capital source details
Capital from the Provincial Development Investment Fund and other legal capital sources
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q4 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Vị Thanh City, Cần Thơ
Implementation location (Before merge)
Hau Giang province
7.Prepare bidding documents, evaluate bids for geological survey consulting, design construction drawings and estimates
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Capital source details
Capital from the Provincial Development Investment Fund and other legal capital sources
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2023
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Vị Thanh City, Cần Thơ
Implementation location (Before merge)
Hau Giang province
8.Prepare bidding documents, evaluate bids for construction supervision consultancy and equipment installation
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Prepare bidding documents, evaluate bids for construction supervision consultancy and equipment installation
Capital source details
Capital from the Provincial Development Investment Fund and other legal capital sources
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Vị Thanh City, Cần Thơ
Implementation location (Before merge)
Hau Giang province
9.preparation of bidding documents, evaluation of bids for construction and equipment installation
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Prepare bidding documents, evaluate bids for construction and equipment installation.
Capital source details
Capital from the Provincial Development Investment Fund and other legal capital sources
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Vị Thanh City, Cần Thơ
Implementation location (Before merge)
Hau Giang province
10.Appraisal of bidding documents, appraisal of results of selection of geological survey consulting contractors, construction drawing designs and estimates
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Capital from the Provincial Development Investment Fund and other legal capital sources
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2023
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Vị Thanh City, Cần Thơ
Implementation location (Before merge)
Hau Giang province
11.Appraisal of bidding documents, appraisal of contractor selection results Construction supervision consultancy and equipment installation
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Appraisal of bidding documents, appraisal of contractor selection results Construction supervision consultancy and equipment installation
Capital source details
Capital from the Provincial Development Investment Fund and other legal capital sources
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Vị Thanh City, Cần Thơ
Implementation location (Before merge)
Hau Giang province
12.Appraisal of bidding documents, appraisal of results of selection of construction and equipment installation contractors
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Appraisal of bidding documents, appraisal of results of selection of construction and equipment installation contractors
Capital source details
Capital from the Provincial Development Investment Fund and other legal capital sources
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Vị Thanh City, Cần Thơ
Implementation location (Before merge)
Hau Giang province
13.Prepare bidding documents and evaluate project management consulting bids
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Capital source details
Capital from the Provincial Development Investment Fund and other legal capital sources
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2023
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Vị Thanh City, Cần Thơ
Implementation location (Before merge)
Hau Giang province
14.Appraisal of bidding documents, appraisal of results of selection of project management consulting contractors
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Capital from the Provincial Development Investment Fund and other legal capital sources
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2023
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Vị Thanh City, Cần Thơ
Implementation location (Before merge)
Hau Giang province
15.Pile static load test (2 hearts)
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Pile static load test (2 hearts)
Capital source details
Capital from the Provincial Development Investment Fund and other legal capital sources
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Vị Thanh City, Cần Thơ
Implementation location (Before merge)
Hau Giang province
16.Prepare a report on the proposal for an environmental permit
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Prepare a report on the proposal for an environmental permit
Capital source details
Capital from the Provincial Development Investment Fund and other legal capital sources
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Second quarter, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Vị Thanh City, Cần Thơ
Implementation location (Before merge)
Hau Giang province
17.Construction of clearing mines and explosives
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Capital from the Provincial Development Investment Fund and other legal capital sources
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2023
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Vị Thanh City, Cần Thơ
Implementation location (Before merge)
Hau Giang province
18.Supervision of clearance of mines and explosives
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Capital source details
Capital from the Provincial Development Investment Fund and other legal capital sources
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2023
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Vị Thanh City, Cần Thơ
Implementation location (Before merge)
Hau Giang province
19.Construction insurance
Tender/ Prequalification Notice ID
Contract execution period
400 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Construction insurance
Capital source details
Capital from the Provincial Development Investment Fund and other legal capital sources
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Vị Thanh City, Cần Thơ
Implementation location (Before merge)
Hau Giang province
20.Independent audit
Tender/ Prequalification Notice ID
Contract execution period
90 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Independent audit
Capital source details
Capital from the Provincial Development Investment Fund and other legal capital sources
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Third quarter, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Vị Thanh City, Cần Thơ
Implementation location (Before merge)
Hau Giang province
21.Measuring and placing landmarks to classify land plots to serve the application for issuance of Land Use Rights Certificates
Tender/ Prequalification Notice ID
Contract execution period
90 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Measuring and placing landmarks to classify land plots to serve the application for issuance of Land Use Rights Certificates
Capital source details
Capital from the Provincial Development Investment Fund and other legal capital sources
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Second quarter, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Vị Thanh City, Cần Thơ
Implementation location (Before merge)
Hau Giang province
22.Appraisal of wastewater treatment plant equipment
Tender/ Prequalification Notice ID
Contract execution period
45 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Capital from the Provincial Development Investment Fund and other legal capital sources
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2023
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Vị Thanh City, Cần Thơ
Implementation location (Before merge)
Hau Giang province
23.Report on the results of trial operation of the project's waste treatment works
Tender/ Prequalification Notice ID
Contract execution period
180 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Report on the results of trial operation of the project's waste treatment works
Capital source details
Capital from the Provincial Development Investment Fund and other legal capital sources
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Third quarter, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Vị Thanh City, Cần Thơ
Implementation location (Before merge)
Hau Giang province

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Project contractor selection plan: Vi Thanh city resettlement area (phase 2)". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Project contractor selection plan: Vi Thanh city resettlement area (phase 2)" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 26

You did not use the site, Click here to remain logged. Timeout: 60 second