Bidder Selection Plan

Project: Expanding and upgrading Coc San water plant.

  Watching      
Project Contractor selection plan Tender notice Bid Opening Result Bid award
Find: 15:50 26/06/2025
Contractor Selection Plan ID
PL2500161370-00
Publishing time
15:50 26/06/2025
Posting Status
Published
Contractor selection plan name
Project: Expanding and upgrading Coc San water plant.
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Spending Category
Investment and Development Spending
Authority that issues the decision
CÔNG TY CP CẤP NƯỚC TỈNH LÀO CAI
Approval date
26/06/2025
Approval ID
150/QĐ - CNLC
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using Windows operating system and installing Client Agent software (Linux and MacOS operating systems cannot install Client software yet). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use DauThau.info software to download files.
To download, please Login or Register

Files with this icon are not supported by the public procurement system for direct download in normal mode. Visit DauThau.info and select Quick Download mode to download the file if you do not use Windows with Agent. DauThau.info supports downloading on most modern browsers and devices!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
List of Bid:
Number of packages: 4
1.Consultancy on preparation of bidding documents, evaluation of bids.
Tender/ Prequalification Notice ID
Contract execution period
40 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Evaluation and selection of contractors with enough capacity and experience to perform the bidding package
Capital source details
Self -capital of enterprises + loans
Contractor Selection Type
Specify reference
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
June, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Lào Cai City, Lào Cai
Implementation location (Before merge)
Tỉnh Lào Cai
2.Civil Works
Tender/ Prequalification Notice ID
Contract execution period
120 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Building 02 reinforced concrete tanks: La Men settling tanks. Fast filter tank, technological supplies installation, wire pull, installation of electrical cabinets, installation of steel frame roofs, corrugated iron roofs, lightning protection systems.
Capital source details
Self -capital of enterprises + loans
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
July, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Lào Cai City, Lào Cai
Implementation location (Before merge)
Tỉnh Lào Cai
3.Construction supervision consultancy
Tender/ Prequalification Notice ID
Contract execution period
120 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Supervise, monitor and inspect contractors to build, ensure, standards, quality, techniques, art, ensure safety, life, property and environment as prescribed.
Capital source details
Self -capital of enterprises + loans
Contractor Selection Type
Specify reference
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
August, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Lào Cai City, Lào Cai
Implementation location (Before merge)
Tỉnh Lào Cai
4.Audit
Tender/ Prequalification Notice ID
Contract execution period
10 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Considering and evaluating from the preparation of investment to the end of investment, checking and detecting shortcomings in the process of investing in investment to adjust and handle errors in the process of implementation
Capital source details
Self -capital of enterprises + loans
Contractor Selection Type
Specify reference
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Quarter I, 2026
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Lào Cai City, Lào Cai
Implementation location (Before merge)
Tỉnh Lào Cai

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Project: Expanding and upgrading Coc San water plant.". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Project: Expanding and upgrading Coc San water plant." plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 7

You did not use the site, Click here to remain logged. Timeout: 60 second