Bidder Selection Plan

Project planning: Building EVN bidding network system

  Watching      
Find: 09:42 10/06/2026
Contractor Selection Plan ID
PL2600163931-00
Publishing time
09:41 10/06/2026
Posting Status
Published
Contractor selection plan name
Project planning: Building EVN bidding network system
Project management forms
The investor directly manages the project
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
PR2600033885-00
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group C
Project implementation time
18 Month
Authority that issues the decision
EVNICT
Approval date
09/06/2026
Approval ID
397/QĐ-EVNICT
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using Windows operating system and installing Client Agent software (Linux and MacOS operating systems cannot install Client software yet). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use DauThau.info software to download files.
To download, please Login or Register

Files with this icon are not supported by the public procurement system for direct download in normal mode. Visit DauThau.info and select Quick Download mode to download the file if you do not use Windows with Agent. DauThau.info supports downloading on most modern browsers and devices!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
List of Bid:
Number of packages: 5
1.Package 2: Outsourcing the development of EVN bidding network system
Tender/ Prequalification Notice ID
Contract execution period
9 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Hire programming and testing for 34 use cases of the EVN bidding network system
Capital source details
Own capital of EVN
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Second quarter, 2026
Type of contract
All in One
Implementation location
Prequalification
No
2.Bidding package 3: Building and deploying EVN bidding network system
Tender/ Prequalification Notice ID
Contract execution period
19 months
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
- Build 66 software use cases - Use case specification, Domain model building, Software design for 34 outsourced use cases - Product packaging - Training on how to use and deploy the system.
Capital source details
Own capital of EVN
Contractor Selection Type
Do it yourself
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Second quarter, 2026
Type of contract
Is different
Implementation location
Prequalification
No
3.Package 4: Rent infrastructure to deploy the bidding network system
Tender/ Prequalification Notice ID
Contract execution period
13 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
- Infrastructure ensures system deployment within 12 months including service packages: + K8s master cluster + K8s worker cluster + VM cluster +Data + Back up data + Firewall + LB HA + Transmission line - Infrastructure ensures level 3 information security for the system for 12 months, including packages: + Dedicated VPN; + Infrastructure to prevent and combat denial of service attacks; + Ensuring the security of the database server; + Web application firewall; + Manage and analyze information security events; + Manage anti-malware software on servers/user computers; + Prevent and combat data loss
Capital source details
Own capital of EVN
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Second quarter, 2026
Type of contract
All in One
Implementation location
Prequalification
No
4.Package 5: Develop video lectures on how to use the EVN bidding network system
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Develop tutorials on how to use the system in video form
Capital source details
Own capital of EVN
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
In the third quarter, 2026
Type of contract
All in One
Implementation location
Prequalification
No
5.Bidding package 6: Testing and evaluating network security and information security of EVN bidding network system
Tender/ Prequalification Notice ID
Contract execution period
11 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
1. The contractor performs the first time: After completing the electronic bidding module, contractor management, registration to participate in the system and related functions: - Survey to collect information and develop plans to inspect and evaluate security and safety - Weakness assessment and penetration testing: + Evaluate application source code weaknesses + Assess library/dependency weaknesses + Weakness assessment and API penetration testing; + Weakness assessment and application penetration testing; + Weakness assessment and server/container penetration testing + Weakness assessment and database penetration testing - Synthesize and prepare reports to evaluate security and safety - Re-assess security and safety and report re-evaluating the results of fixing vulnerabilities 2. Contractor performs the second time: Evaluates the remaining functions with the same work content as the first time
Capital source details
Own capital of EVN
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
In the third quarter, 2026
Type of contract
All in One
Implementation location
Prequalification
No

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Project planning: Building EVN bidding network system". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Project planning: Building EVN bidding network system" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 28

You did not use the site, Click here to remain logged. Timeout: 60 second