Bidder Selection Plan

Project planning: Construction of transmission lines and substations in Khoai Chau and Kim Dong districts, Hung Yen province, added in 2023

  Watching      
Find: 09:20 01/12/2023
Contractor Selection Plan ID
PL2300239459-00
Publishing time
09:17 01/12/2023
Posting Status
Published
Contractor selection plan name
Project planning: Construction of transmission lines and substations in Khoai Chau and Kim Dong districts, Hung Yen province, added in 2023
Investment objective
In order to prevent overload for distribution substations with loads of densely populated and densely populated areas, with many production loads in craft villages, with many inns, this is a potential economic development area with the potential to increase large mechanical population density, production customers account for a large billion, have a growth rate of load, reduce power loss, overcome overload at present and in the coming years. Increase commercial power output, expand business capabilities of Hung Yen Power Company, reduce loss
Project management forms
The investor directly manages the project
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
PR2300060867-00
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group C
Project implementation time
1 Years
Location
Authority that issues the decision
Công ty Điện lực Hưng Yên - CN tổng Công ty Điện lực Hưng Yên
Approval date
30/11/2023
Approval ID
3616/QĐ-PCHY
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using the Windows operating system and needs to install Client Agent software (Linux and MacOS cannot download Client software yet). ). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use our DauThau.info.
Our system will help you download files faster, on any device without installing Client Agent.
To download, please Login or Register

File can only be downloaded on Windows computers using Agent, please see instructions here!!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
List of Bid:
Number of packages: 4
1.Package 03 – Procurement of transformers
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Goods
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Commercial capital of Northern Power Corporation
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q4 2023
Type of contract
All in One
Prequalification
No
Location
Kim Động District, Hưng Yên
2.Package 04 – Construction and procurement of remaining VTTB
Tender/ Prequalification Notice ID
Contract execution period
150 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Commercial capital of Northern Power Corporation
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q4 2023
Type of contract
All in One
Prequalification
No
Location
Khoái Châu District, Hưng Yên
3.Package 05 – Construction supervision consultancy
Tender/ Prequalification Notice ID
Contract execution period
150 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Scientific and technical capital of Northern Power Corporation
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q4 2023
Type of contract
All in One
Prequalification
No
Location
Kim Động District, Hưng Yên
4.Package 06 – Construction audit
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Basic Depreciation Capital of Northern Power Corporation
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q1 2024
Type of contract
All in One
Prequalification
No
Location
Kim Động District, Hưng Yên

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Project planning: Construction of transmission lines and substations in Khoai Chau and Kim Dong districts, Hung Yen province, added in 2023". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Project planning: Construction of transmission lines and substations in Khoai Chau and Kim Dong districts, Hung Yen province, added in 2023" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 2

You did not use the site, Click here to remain logged. Timeout: 60 second