Project planning: Construction, renovation to improve operating capacity, medium and low voltage power grid in Sa Pa ward and Ta Phin, Bao Ha, Bao Yen communes, Lao Cai province in 2027
Project planning: Construction, renovation to improve operating capacity, medium and low voltage power grid in Sa Pa ward and Ta Phin, Bao Ha, Bao Yen communes, Lao Cai province in 2027
Renovate, prevent overload, improve power supply reliability, ensure quality and reduce power loss from the power grid in Sa Pa ward and communes of Ta Phin, Bao Ha, Xuan Hoa, Bao Yen, Lao Cai province
Downloading files directly on the new Public Procurement System requires a computer using Windows operating system and installing Client Agent software (Linux and MacOS operating systems cannot install Client software yet). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use DauThau.info software to download files. To download, please Login or Register
1742QĐ-PCLK.pdf
Files with this icon are not supported by the public procurement system for direct download in normal mode. Visit DauThau.info and select Quick Download mode to download the file if you do not use Windows with Agent. DauThau.info supports downloading on most modern browsers and devices! In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
Providing materials and equipment (except for the transformer provided by the investor) and constructing and installing the entire project with the following scale: Construction of 0.05 km of 22 kV transmission line; 0.580 km of 22 kV AL/XLPE/PVC/ DSTA/PVC-W-12.7/22(24) kV-3x240 mm2 underground cable; 0.225 km of 22 kV Al/XLPE/PVC/ DSTA/PVC-W-12.7/22(24) kV-3x70 mm2 underground cable; 0.062 km of 22 kV Cu/XLPE/PVC/ DSTA/PVC-W-12.7/22(24) kV-3x50 mm2 underground cable; Construction of 01 suspended substation 400 kVA-22/0.4 kV + 01 cylindrical substation 400 kVA-22/0.4 kV + 02 cylindrical substations 630 kVA-22/0.4 kV; Construction of 0.274 km of 0.4 kV underground cable; Construction of 0.299 km of 0.4 kV line; Renovating 10,887 km of 0.4 kV lines.
Capital source details
Commercial credit loans and basic depreciation of Northern Power Corporation
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Project planning: Construction, renovation to improve operating capacity, medium and low voltage power grid in Sa Pa ward and Ta Phin, Bao Ha, Bao Yen communes, Lao Cai province in 2027". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Project planning: Construction, renovation to improve operating capacity, medium and low voltage power grid in Sa Pa ward and Ta Phin, Bao Ha, Bao Yen communes, Lao Cai province in 2027" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.