Bidder Selection Plan

Project planning: Thoroughly handling the landslide in Da Giang dike area, section Km2+538 and upstream of Den bridge in Dong Tien ward, Hoa Binh city to protect the safety of civil, economic and industrial activities. within the scope of the project.

  Watching      
Find: 17:52 05/11/2023
Contractor Selection Plan ID
PL2300166757-01
Publishing time
10:18 05/11/2023
Posting Status
Published
Contractor selection plan name
Project planning: Thoroughly handling the landslide in Da Giang dike area, section Km2+538 and upstream of Den bridge in Dong Tien ward, Hoa Binh city to protect the safety of civil, economic and industrial activities. within the scope of the project.
Investment objective
Thoroughly handle the landslide in the Da Giang dike area, section Km2+538 and upstream of Den bridge in Dong Tien ward, Hoa Binh city to protect the safety of civil and economic activities and works within the area. microproject.
Project management forms
The investor directly manages the project
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
PR2300044468-02
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group C
Project implementation time
1 Years
Location
Hoa Binh province
Authority that issues the decision
Ủy ban nhân dân tỉnh Hòa Bình
Approval date
01/11/2023
Approval ID
QĐ số 2517/QĐ-UBND
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using the Windows operating system and needs to install Client Agent software (Linux and MacOS cannot download Client software yet). ). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use our DauThau.info.
Our system will help you download files faster, on any device without installing Client Agent.
To download, please Login or Register

File can only be downloaded on Windows computers using Agent, please see instructions here!!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
Related announcements

- Change: Bidding package number, total investment, Highest bid price, Approval date, Approval ID, Publication date, Bidding package information (View changes)

Posted for the first time (View changes)

List of Bid:
Number of packages: 8
1.Bidding package No. 04: Survey consulting, construction drawing design and estimates
Tender/ Prequalification Notice ID
Contract execution period
20 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
The central budget reserve support in Decision No. 1661/QD-TTg dated December 31, 2022 of the Prime Minister
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
September 2023
Type of contract
All in One
Prequalification
No
Location
2.Bidding package No. 05: Verification of construction drawing design documents and estimates
Tender/ Prequalification Notice ID
Contract execution period
10 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
The central budget reserve support in Decision No. 1661/QD-TTg dated December 31, 2022 of the Prime Minister
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
September 2023
Type of contract
All in One
Prequalification
No
Location
3.Tender package No 06: Supervision and survey of the TKBVTC phase
Tender/ Prequalification Notice ID
Contract execution period
20 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
The central budget reserve support in Decision No. 1661/QD-TTg dated December 31, 2022 of the Prime Minister
Contractor Selection Type
Do it yourself
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
September 2023
Type of contract
All in One
Prequalification
No
Location
4.Bidding package No. 07: Costs for preparing bidding documents and evaluating construction and installation bids
Tender/ Prequalification Notice ID
Contract execution period
15 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
The central budget reserve support in Decision No. 1661/QD-TTg dated December 31, 2022 of the Prime Minister
Contractor Selection Type
Do it yourself
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
September 2023
Type of contract
All in One
Prequalification
No
Location
5.Package 08: Construction supervision
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
The central budget reserve support in Decision No. 1661/QD-TTg dated December 31, 2022 of the Prime Minister
Contractor Selection Type
Do it yourself
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
September 2023
Type of contract
All in One
Prequalification
No
Location
6.Bidding package No. 09: Construction insurance
Tender/ Prequalification Notice ID
Contract execution period
390 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
The central budget reserve support in Decision No. 1661/QD-TTg dated December 31, 2022 of the Prime Minister
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2023
Type of contract
All in One
Prequalification
No
Location
7.Package 10: Construction work
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
The central budget reserve support in Decision No. 1661/QD-TTg dated December 31, 2022 of the Prime Minister
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q4 2023
Type of contract
All in One
Prequalification
No
Location
8.Tender package No 11: Independent Audit
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
The central budget reserve support in Decision No. 1661/QD-TTg dated December 31, 2022 of the Prime Minister
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2023
Type of contract
All in One
Prequalification
No
Location

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Project planning: Thoroughly handling the landslide in Da Giang dike area, section Km2+538 and upstream of Den bridge in Dong Tien ward, Hoa Binh city to protect the safety of civil, economic and industrial activities. within the scope of the project.". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Project planning: Thoroughly handling the landslide in Da Giang dike area, section Km2+538 and upstream of Den bridge in Dong Tien ward, Hoa Binh city to protect the safety of civil, economic and industrial activities. within the scope of the project." plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 12

Greeting
Greeting,
You are not logged in, please log in to use our various functions for members.

You can use your account on DauThau.info to log in to Dauthau.Net, and vice versa!

If you are still not our member, please sign up.

Only 5 minutes and absolutely free! Your account can be use on all over our ecosystem, including DauThau.info and DauThau.Net.

Search for bid information
Click for advanced search
Statistical
  • 8534 Projects are waiting for contractors
  • 141 Tender notices posted in the last 24 hours
  • 159 Contractor selection plan posted in the last 24 hours
  • 23692 Tender notices posted in the past month
  • 37141 Contractor selection plan posted in the last month
Consultants are supporting you
You are not logged in.
To view information, please Login or Register if you do not have an account.
Signing up is simple and completely free.
You did not use the site, Click here to remain logged. Timeout: 60 second