To arrange the resettlement foundation for affected households when performing compensation, support and resettlement work for Song Hau Industrial Park phase 2 project and projects in Chau Thanh district.
Downloading files directly on the new Public Procurement System requires a computer using the Windows operating system and needs to install Client Agent software (Linux and MacOS cannot download Client software yet). ). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use our DauThau.info. Our system will help you download files faster, on any device without installing Client Agent. To download, please Login or Register
QĐ phê duyệt điều chỉnh KHLCNT Khu TĐC Mái Dầm.pdf
File can only be downloaded on Windows computers using Agent, please see instructions here!! In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
List of Bid:
Number of packages: 24
1.Bidding package: Consultancy, verification of construction design and cost estimate of items: Power supply system; Lighting systems
4.Bidding package: Consulting on appraisal of bidding documents and results of selecting contractors for construction items: Ground leveling; Road - sidewalk - trees; Rainwater drainage system; Wastewater drainage system, Wastewater treatment area; Water supply system - Fire protection; Parks, trees, parking lots, solid waste collection points and wastewater treatment equipment and operating chemicals
7.Bidding package: Consulting on preparation of bidding documents, evaluation of bid documents, supervision of construction and equipment installation for items: Leveling; Road - sidewalk - trees; Rainwater drainage system; Wastewater drainage system, Wastewater treatment area; Water supply system - Fire protection; Parks, trees, parking lots, solid waste collection points and wastewater treatment equipment and operating chemicals
8.Bidding package: Consulting on appraisal of bidding documents and results of selecting contractors to supervise construction and equipment installation for items: Ground leveling; Road - sidewalk - trees; Rainwater drainage system; Wastewater drainage system, Wastewater treatment area; Water supply system - Fire protection; Parks, trees, parking lots, solid waste collection points and wastewater treatment equipment and operating chemicals
10.Bidding package: Consultancy on preparation of bidding documents, evaluation of bids for construction of items: Power supply system; Lighting systems
11.Bidding package: Consulting on appraisal of bidding documents and results of selecting contractors to construct construction items: Power supply system; Lighting systems.
14.Bidding package: Consulting on preparing bidding documents, evaluating bid documents, supervising construction items: Power supply system, lighting system
15.Bidding package: Consulting on appraisal of bidding documents and results of selecting contractors to supervise construction items: Power supply system, lighting system
20.Bidding package: Consulting on preparing bidding documents, evaluating bidding documents on positioning, placing foundation piles and measuring to issue land use rights certificates
21.Bidding package: Consulting on appraisal of bidding documents and results of selecting contractors for positioning, installing foundation piles and measuring to issue land use right certificates
23.Bidding package: Consulting on preparing a proposal report for environmental licensing (stipulated in Section 4, Law on Environmental Protection dated November 17, 2020)
24.Bidding package: Consulting on reporting results of trial operation of the project's waste treatment works (Article 46 of the Law on Environmental Protection dated November 17, 2020)
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Regarding approval of adjusting the contractor selection plan for project: Mai Dam resettlement area". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Regarding approval of adjusting the contractor selection plan for project: Mai Dam resettlement area" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.