Bidder Selection Plan

Regarding approving tasks, cost estimates Surveying, preparing construction drawing design - Estimates, Supervising survey work and verifying construction drawing design - Estimates and contractor selection plan Project: New construction of Dinh Binh bridge, Vinh Thanh district

  Watching      
Find: 15:33 17/01/2026
Contractor Selection Plan ID
PL2600012288-00
Publishing time
15:32 17/01/2026
Posting Status
Published
Contractor selection plan name
Regarding approving tasks, cost estimates Surveying, preparing construction drawing design - Estimates, Supervising survey work and verifying construction drawing design - Estimates and contractor selection plan Project: New construction of Dinh Binh bridge, Vinh Thanh district
Project management forms
The investor directly manages the project
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
PR2600002377-00
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group C
Project implementation time
3 Years
Authority that issues the decision
Ban Quản lý dự án các công trình Giao thông và Dân dụng tỉnh Gia Lai
Approval date
09/09/2025
Approval ID
1689
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using Windows operating system and installing Client Agent software (Linux and MacOS operating systems cannot install Client software yet). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use DauThau.info software to download files.
To download, please Login or Register

Files with this icon are not supported by the public procurement system for direct download in normal mode. Visit DauThau.info and select Quick Download mode to download the file if you do not use Windows with Agent. DauThau.info supports downloading on most modern browsers and devices!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
List of Bid:
Number of packages: 10
1.Construction supervision consultancy
Tender/ Prequalification Notice ID
Contract execution period
15 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Summary of main tasks of the bid package
Construction supervision consultancy
Capital source details
Government budget Capital
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Fourth quarter, 2025
Type of contract
Fixed unit price
Implementation location
Prequalification
No
2.Environmental Protection registration
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Environmental Protection registration
Capital source details
Government budget Capital
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Third quarter, 2025
Type of contract
Fixed unit price
Implementation location
Prequalification
No
3.Completed project settlement audit consulting
Tender/ Prequalification Notice ID
Contract execution period
45 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Completed project settlement audit consulting
Capital source details
Government budget Capital
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Fourth quarter, 2025
Type of contract
Fixed unit price
Implementation location
Prequalification
No
4.Consultancy on quality control of works
Tender/ Prequalification Notice ID
Contract execution period
15 months
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Consultancy on quality control of works
Capital source details
Government budget Capital
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Fourth quarter, 2025
Type of contract
Fixed unit price
Implementation location
Prequalification
No
5.Construction insurance for construction and installation package
Tender/ Prequalification Notice ID
Contract execution period
75 months
Domestic/ International
Domestic
Bidding method
Directly
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Construction insurance for construction and installation package
Capital source details
Government budget Capital
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Fourth quarter, 2025
Type of contract
Fixed unit price
Implementation location
Prequalification
No
6.The entire volume of construction work
Tender/ Prequalification Notice ID
Contract execution period
15 months
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Summary of main tasks of the bid package
All construction volume, lighting electricity, traffic safety system
Capital source details
Government budget Capital
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Fourth quarter, 2025
Type of contract
According to adjusted unit price
Implementation location
Prequalification
No
7.Construction of clearing mines and explosives
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Construction of clearing mines and explosives
Capital source details
Government budget Capital
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Third quarter, 2025
Type of contract
Fixed unit price
Implementation location
Prequalification
No
8.Plug in the ground clearance stakes
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Plug in the ground clearance stakes
Capital source details
Government budget Capital
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Third quarter, 2025
Type of contract
Fixed unit price
Implementation location
Prequalification
No
9.Geodetic surveying
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Geodetic surveying
Capital source details
Government budget Capital
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Third quarter, 2025
Type of contract
Fixed unit price
Implementation location
Prequalification
No
10.Construction information board (Pano)
Tender/ Prequalification Notice ID
Contract execution period
10 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Construction information board (Pano)
Capital source details
Government budget Capital
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Third quarter, 2025
Type of contract
Fixed unit price
Implementation location
Prequalification
No

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Regarding approving tasks, cost estimates Surveying, preparing construction drawing design - Estimates, Supervising survey work and verifying construction drawing design - Estimates and contractor selection plan Project: New construction of Dinh Binh bridge, Vinh Thanh district". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Regarding approving tasks, cost estimates Surveying, preparing construction drawing design - Estimates, Supervising survey work and verifying construction drawing design - Estimates and contractor selection plan Project: New construction of Dinh Binh bridge, Vinh Thanh district" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 30

You did not use the site, Click here to remain logged. Timeout: 60 second