Bidder Selection Plan

RENOVATION AND REPAIR OF THE EXTERIOR AND ROOF OF THE BIDV HA DONG BRANCH HEADQUARTERS BUILDING

  Watching      
Find: 17:35 19/08/2024
Contractor Selection Plan ID
PL2400173478-00
Publishing time
17:34 19/08/2024
Posting Status
Published
Contractor selection plan name
RENOVATION AND REPAIR OF THE EXTERIOR AND ROOF OF THE BIDV HA DONG BRANCH HEADQUARTERS BUILDING
Project management forms
The investor directly manages the project
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
PR2400045864-01
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group C
Project implementation time
2 Years
Location
Authority that issues the decision
Ngân hàng TMCP Đầu tư và Phát triển Việt Nam
Approval date
16/08/2024
Approval ID
5417/QĐ-BIDV
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using the Windows operating system and needs to install Client Agent software (Linux and MacOS cannot download Client software yet). ). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use our DauThau.info.
Our system will help you download files faster, on any device without installing Client Agent.
To download, please Login or Register

File can only be downloaded on Windows computers using Agent, please see instructions here!!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
List of Bid:
Number of packages: 4
1.PACKAGE 3: CONSTRUCTION AND RENOVATION AND REPAIR OF PROJECTS
Tender/ Prequalification Notice ID
Contract execution period
150 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
BIDV charter capital and expenses at Ha Dong branch
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
Fixed unit price
Prequalification
No
Location
Hà Đông District, Hà Nội
2.Package 4: Construction supervision
Tender/ Prequalification Notice ID
Contract execution period
150 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Costs at Ha Dong branch
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
All in One
Prequalification
No
Location
Hà Đông District, Hà Nội
3.Package 5: Construction insurance
Tender/ Prequalification Notice ID
Contract execution period
150 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Costs at Ha Dong branch
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q3 2024
Type of contract
All in One
Prequalification
No
Location
Hà Đông District, Hà Nội
4.PACKAGE 6: AUDIT OF INVESTMENT CAPITAL SETTLEMENT REPORT OF COMPLETED PROJECTS
Tender/ Prequalification Notice ID
Contract execution period
45 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
Costs at Ha Dong branch
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Third quarter, 2025
Type of contract
All in One
Prequalification
No
Location
Hà Đông District, Hà Nội

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "RENOVATION AND REPAIR OF THE EXTERIOR AND ROOF OF THE BIDV HA DONG BRANCH HEADQUARTERS BUILDING". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "RENOVATION AND REPAIR OF THE EXTERIOR AND ROOF OF THE BIDV HA DONG BRANCH HEADQUARTERS BUILDING" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 2

Greeting
Greeting,
You are not logged in, please log in to use our various functions for members.

You can use your account on DauThau.info to log in to Dauthau.Net, and vice versa!

If you are still not our member, please sign up.

Only 5 minutes and absolutely free! Your account can be use on all over our ecosystem, including DauThau.info and DauThau.Net.

Search for bid information
Click for advanced search
Statistical
  • 8563 Projects are waiting for contractors
  • 1076 Tender notices posted in the last 24 hours
  • 1882 Contractor selection plan posted in the last 24 hours
  • 25193 Tender notices posted in the past month
  • 40597 Contractor selection plan posted in the last month
Consultants are supporting you
You are not logged in.
To view information, please Login or Register if you do not have an account.
Signing up is simple and completely free.
You did not use the site, Click here to remain logged. Timeout: 60 second