Bidder Selection Plan

Repairing the foundation and road surface of sections Km2+610 - Km2+760 (P), Km2+810 -Km2+900 (T), Km3+470 - Km3+570 (T), Km3+500 - Km3+580 (P ), Km4+500 - Km4+530 (P), Km6+050 - Km6+110 (P), Km6+250 - Km6+350 (T), Km8+300 - Km8+500 (T), Km8+800 - Km8+850 (T), Km10+900 - Km10+950(T), Km11+280 - Km11+360(T); Repairing the slope of Rach Son bridge Km2+498; Repairing the drainage system of sections Km4+294 - Km4+677 (T); Km12+220 - Km13+636 (W); Renovating the median strip opening point Km14+150 National Highway 22B Tay Ninh province

  Watching      
Find: 15:16 19/02/2024
Contractor Selection Plan ID
PL2400019932-00
Publishing time
15:15 19/02/2024
Posting Status
Published
Contractor selection plan name
Repairing the foundation and road surface of sections Km2+610 - Km2+760 (P), Km2+810 -Km2+900 (T), Km3+470 - Km3+570 (T), Km3+500 - Km3+580 (P ), Km4+500 - Km4+530 (P), Km6+050 - Km6+110 (P), Km6+250 - Km6+350 (T), Km8+300 - Km8+500 (T), Km8+800 - Km8+850 (T), Km10+900 - Km10+950(T), Km11+280 - Km11+360(T); Repairing the slope of Rach Son bridge Km2+498; Repairing the drainage system of sections Km4+294 - Km4+677 (T); Km12+220 - Km13+636 (W); Renovating the median strip opening point Km14+150 National Highway 22B Tay Ninh province
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
PR2400005933-00
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group C
Project implementation time
2 Years
Authority that issues the decision
Cục đường bộ Viêt Nam
Approval date
06/02/2024
Approval ID
1017/QĐ-CĐBVN
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using Windows operating system and installing Client Agent software (Linux and MacOS operating systems cannot install Client software yet). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use DauThau.info software to download files.
To download, please Login or Register

Files with this icon are not supported by the public procurement system for direct download in normal mode. Visit DauThau.info and select Quick Download mode to download the file if you do not use Windows with Agent. DauThau.info supports downloading on most modern browsers and devices!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
List of Bid:
Number of packages: 4
1.Tender package No 1: Consultancy on setting up Bid Documents and Bid Evaluation
Tender/ Prequalification Notice ID
Contract execution period
45 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Bidding documents and evaluation of project bids: Repair of foundation and road surface of sections Km2+610 - Km2+760 (P), Km2+810 -Km2+900 (T), Km3+470 - Km3+570 (T), Km3 +500 - Km3+580 (P), Km4+500 - Km4+530 (P), Km6+050 - Km6+110 (P), Km6+250 - Km6+350 (W), Km8+300 - Km8+500 (T), Km8+800 - Km8+850 (T), Km10+900 - Km10+950(T), Km11+280 - Km11+360(T); Repairing the slope of Rach Son bridge Km2+498; Repairing the drainage system of sections Km4+294 - Km4+677 (T); Km12+220 - Km13+636 (W); Renovating the median strip opening point Km14+150 National Highway 22B, Tay Ninh province
Capital source details
State budget (non-business funding for road economic activities)
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
February 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Implementation location (Before merge)
Ho Chi Minh city
2.Tender package No 2: Construction and repair
Tender/ Prequalification Notice ID
Contract execution period
75 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Construction and repair works: Repairing the foundation and road surface of sections Km2+610 - Km2+760 (P), Km2+810 -Km2+900 (T), Km3+470 - Km3+570 (T), Km3+ 500 - Km3+580 (P), Km4+500 - Km4+530 (P), Km6+050 - Km6+110 (P), Km6+250 - Km6+350 (T), Km8+300 - Km8+500 (T), Km8+800 - Km8+850 (T), Km10+900 - Km10+950(T) , Km11+280 - Km11+360(T); Repairing the slope of Rach Son bridge Km2+498; Repairing the drainage system of sections Km4+294 - Km4+677 (T); Km12+220 - Km13+636 (W); Renovating the median strip opening point Km14+150 National Highway 22B, Tay Ninh province
Capital source details
State budget (non-business funding for road economic activities)
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
March, 2024
Type of contract
Fixed unit price
Prequalification
No
Implementation location (After merge)
Implementation location (Before merge)
Tay Ninh province
3.Package 3: Construction supervision consultancy
Tender/ Prequalification Notice ID
Contract execution period
75 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Construction supervision: Repairing foundations and road surfaces of sections Km2+610 - Km2+760 (P), Km2+810 -Km2+900 (T), Km3+470 - Km3+570 (T), Km3+ 500 - Km3+580 (P), Km4+500 - Km4+530 (P), Km6+050 - Km6+110 (P), Km6+250 - Km6+350 (W), Km8+300 - Km8+500 ( T), Km8+800 - Km8+850 (T), Km10+900 - Km10+950(T), Km11+280 - Km11+360(T); Repairing the slope of Rach Son bridge Km2+498; Repairing the drainage system of sections Km4+294 - Km4+677 (T); Km12+220 - Km13+636 (W); Renovating the median strip opening point Km14+150 National Highway 22B, Tay Ninh province
Capital source details
State budget (non-business funding for road economic activities)
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
March, 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Implementation location (Before merge)
Tay Ninh province
4.Package 4: Auditing the finalization of the completed project
Tender/ Prequalification Notice ID
Contract execution period
30 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Project settlement audit: Repair of foundations and road surfaces of sections Km2+610 - Km2+760 (P), Km2+810 -Km2+900 (T), Km3+470 - Km3+570 (T), Km3+ 500 - Km3+580 (P), Km4+500 - Km4+530 (P), Km6+050 - Km6+110 (P), Km6+250 - Km6+350 (T), Km8+300 - Km8+500 (T), Km8+800 - Km8+850 (T), Km10+900 - Km10+950(T) , Km11+280 - Km11+360(T); Repairing the slope of Rach Son bridge Km2+498; Repairing the drainage system of sections Km4+294 - Km4+677 (T); Km12+220 - Km13+636 (W); Renovating the median strip opening point Km14+150 National Highway 22B, Tay Ninh province
Capital source details
State budget (non-business funding for road economic activities)
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
July 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Implementation location (Before merge)
Ho Chi Minh city

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Repairing the foundation and road surface of sections Km2+610 - Km2+760 (P), Km2+810 -Km2+900 (T), Km3+470 - Km3+570 (T), Km3+500 - Km3+580 (P ), Km4+500 - Km4+530 (P), Km6+050 - Km6+110 (P), Km6+250 - Km6+350 (T), Km8+300 - Km8+500 (T), Km8+800 - Km8+850 (T), Km10+900 - Km10+950(T), Km11+280 - Km11+360(T); Repairing the slope of Rach Son bridge Km2+498; Repairing the drainage system of sections Km4+294 - Km4+677 (T); Km12+220 - Km13+636 (W); Renovating the median strip opening point Km14+150 National Highway 22B Tay Ninh province". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Repairing the foundation and road surface of sections Km2+610 - Km2+760 (P), Km2+810 -Km2+900 (T), Km3+470 - Km3+570 (T), Km3+500 - Km3+580 (P ), Km4+500 - Km4+530 (P), Km6+050 - Km6+110 (P), Km6+250 - Km6+350 (T), Km8+300 - Km8+500 (T), Km8+800 - Km8+850 (T), Km10+900 - Km10+950(T), Km11+280 - Km11+360(T); Repairing the slope of Rach Son bridge Km2+498; Repairing the drainage system of sections Km4+294 - Km4+677 (T); Km12+220 - Km13+636 (W); Renovating the median strip opening point Km14+150 National Highway 22B Tay Ninh province" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 101

You did not use the site, Click here to remain logged. Timeout: 60 second