Bidder Selection Plan

Residential area Phu Thanh - Long Tan

  Watching      
Project Contractor selection plan Tender notice Bid Opening Result Bid award
Find: 10:15 15/03/2016
Contractor selection plan ID
20160305006-00
Publication date
10:15 15/03/2016
Publication status
Actual notification
Contractor selection plan name
Residential area Phu Thanh - Long Tan
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Total investment
To view full information, please Login or Register
Spending Category
 Investment projects
QD status
 There has been a decision to approve the investment project
Approval date
14/03/2016
List of Bid:
Number of packages: 10
1.Technical infrastructure of Subdivision 1F
Tender/ Prequalification Notice ID
Contract Period
120 days
Domestic/ International
International
Bidding method
Online
Fields
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
Business capital + Loan capital
Contractor Selection Type
Open bidding,Domestic,No prequalification,One phase, one dossier bag
Contractor Selection Method
Contractor Selection Period
Second quarter of 2016
Contract Type
According to fixed unit price
Prequalification
No
Implementation location
2.Technical infrastructure of Subdivision 1F
Tender/ Prequalification Notice ID
Contract Period
20 days
Domestic/ International
International
Bidding method
Online
Fields
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
Enterprise capital + Loan capital
Contractor Selection Type
Competitive offers, Domestic, No pre-qualification, One stage, one envelope
Contractor Selection Method
Contractor Selection Period
Fourth quarter of 2016
Contract Type
According to fixed unit price
Prequalification
No
Implementation location
3.Technical infrastructure of Division 1E
Tender/ Prequalification Notice ID
Contract Period
135 days
Domestic/ International
International
Bidding method
Online
Fields
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
Business capital + Loan capital
Contractor Selection Type
Open bidding,Domestic,No prequalification,One stage, two dossier bags
Contractor Selection Method
Contractor Selection Period
Second quarter of 2016
Contract Type
All in one
Prequalification
No
Implementation location
4.Technical infrastructure of Division 1E
Tender/ Prequalification Notice ID
Contract Period
60 days
Domestic/ International
International
Bidding method
Online
Fields
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
Business capital + Loan capital
Contractor Selection Type
Competitive offers, Domestic, No pre-qualification, One stage, one envelope
Contractor Selection Method
Contractor Selection Period
Second quarter of 2016
Contract Type
All in one
Prequalification
No
Implementation location
5.Construction of road D1
Tender/ Prequalification Notice ID
Contract Period
90 days
Domestic/ International
International
Bidding method
Online
Fields
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
Business capital + Loan capital
Contractor Selection Type
Open bidding,Domestic,No prequalification,One phase, one dossier bag
Contractor Selection Method
Contractor Selection Period
Second quarter of 2016
Contract Type
According to fixed unit price
Prequalification
No
Implementation location
6.Construction of road D1
Tender/ Prequalification Notice ID
Contract Period
20 days
Domestic/ International
International
Bidding method
Online
Fields
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
Business capital + Loan capital
Contractor Selection Type
Competitive offers, Domestic, No pre-qualification, One stage, one envelope
Contractor Selection Method
Contractor Selection Period
Fourth quarter of 2016
Contract Type
According to fixed unit price
Prequalification
No
Implementation location
7.Construction of road D2
Tender/ Prequalification Notice ID
Contract Period
90 days
Domestic/ International
International
Bidding method
Online
Fields
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
Enterprise capital + Loan capital
Contractor Selection Type
Open bidding,Domestic,No prequalification,One phase, one dossier bag
Contractor Selection Method
Contractor Selection Period
Second quarter of 2016
Contract Type
According to fixed unit price
Prequalification
No
Implementation location
8.Construction of road D2
Tender/ Prequalification Notice ID
Contract Period
20 days
Domestic/ International
International
Bidding method
Online
Fields
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
Enterprise capital + Loan capital
Contractor Selection Type
Competitive offers, Domestic, No pre-qualification, One stage, one envelope
Contractor Selection Method
Contractor Selection Period
Fourth quarter of 2016
Contract Type
According to fixed unit price
Prequalification
No
Implementation location
9.Construction of road D4
Tender/ Prequalification Notice ID
Contract Period
135 days
Domestic/ International
International
Bidding method
Online
Fields
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
Enterprise capital + Loan capital
Contractor Selection Type
Open bidding,Domestic,No prequalification,One phase, one dossier bag
Contractor Selection Method
Contractor Selection Period
Second quarter of 2016
Contract Type
According to fixed unit price
Prequalification
No
Implementation location
10.Construction of road D4
Tender/ Prequalification Notice ID
Contract Period
20 days
Domestic/ International
International
Bidding method
Online
Fields
Regulatory compliance
Tender value
To view full information, please Login or Register
Funding source
Enterprise capital + Loan capital
Contractor Selection Type
Competitive offers, Domestic, No pre-qualification, One stage, one envelope
Contractor Selection Method
Contractor Selection Period
Fourth quarter of 2016
Contract Type
According to fixed unit price
Prequalification
No
Implementation location

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Residential area Phu Thanh - Long Tan". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Residential area Phu Thanh - Long Tan" plan as soon as they are posted, sign up for DauThau.info's International VIP 2 plan.
Views: 28

You did not use the site, Click here to remain logged. Timeout: 60 second