Bidder Selection Plan

Road C (extended Le Duan)

  Watching      
Find: 10:26 19/04/2025
Contractor Selection Plan ID
PL2300257496-01
Publishing time
10:25 19/04/2025
Posting Status
Published
Contractor selection plan name
Road C (extended Le Duan)
Investment objective
Road C (extended Le Duan)
Project management forms
The investor directly manages the project
Using ODA capital?
Are not
Funding source
Do not use ODA capital
Project number
PR2300064213-00
Name of project
Total investment
To view full information, please Login or Register
Spending Category
Investment and Development Spending
Project group
Group B
Project implementation time
3 Years
Authority that issues the decision
UBND thành phố Tây Ninh
Approval date
15/04/2024
Approval ID
262/QĐ-UBND
Approval Documents

Downloading files directly on the new Public Procurement System requires a computer using Windows operating system and installing Client Agent software (Linux and MacOS operating systems cannot install Client software yet). Therefore, to be able to download files on smartphones, tablets or computers using operating systems other than Windows, you need to use DauThau.info software to download files.
To download, please Login or Register

Files with this icon are not supported by the public procurement system for direct download in normal mode. Visit DauThau.info and select Quick Download mode to download the file if you do not use Windows with Agent. DauThau.info supports downloading on most modern browsers and devices!
In case it is discovered that the BMT does not fully attach the E-HSMT file and design documents, the contractor is requested to immediately notify the Investor or the Authorized Person at the address specified in Chapter II-Data Table in E- Application form and report to the Procurement News hotline: 02437.686.611
Related announcements

- Change: Approval date, Approval ID, Publication date, Bidding package information (View changes)

Posted for the first time (View changes)

List of Bid:
Number of packages: 12
1.Survey, design construction drawings
Tender/ Prequalification Notice ID
Contract execution period
90 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
The estimate of the bid package is approved after the approval of the LCA
To view full information, please Login or Register
Capital source details
City Budget and Provincial Budget support the goal
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Q4 2023
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Tây Ninh City, Tây Ninh
Implementation location (Before merge)
Tay Ninh province
2.Consultancy on bidding for survey package, making construction drawing design
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
City Budget and Provincial Budget support the goal
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q4 2023
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Tây Ninh City, Tây Ninh
Implementation location (Before merge)
Tay Ninh province
3.Verification of construction drawing design – cost estimate
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Capital source details
City Budget and Provincial Budget support the goal
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Q1 2024
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Tây Ninh City, Tây Ninh
Implementation location (Before merge)
Tay Ninh province
4.Construction (including the cost of ensuring traffic)
Tender/ Prequalification Notice ID
Contract execution period
365 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Construction (including the cost of ensuring traffic)
Capital source details
City Budget and Provincial Budget support the goal
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Second quarter, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Tây Ninh City, Tây Ninh
Implementation location (Before merge)
Tay Ninh province
5.Construction bidding consultancy
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Construction bidding consultancy
Capital source details
City Budget and Provincial Budget support the goal
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Second quarter, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Tây Ninh City, Tây Ninh
Implementation location (Before merge)
Tay Ninh province
6.Insurance
Tender/ Prequalification Notice ID
Contract execution period
365 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Non-consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Insurance
Capital source details
City Budget and Provincial Budget support the goal
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Second quarter, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Tây Ninh City, Tây Ninh
Implementation location (Before merge)
Tay Ninh province
7.Construction supervision
Tender/ Prequalification Notice ID
Contract execution period
365 days
Domestic/ International
Domestic
Bidding method
Online
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Construction supervision
Capital source details
City Budget and Provincial Budget support the goal
Contractor Selection Type
Open bidding
Contractor Selection Method
Single Stage Two Envelopes
Contractor Selection Period
Second quarter, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Tây Ninh City, Tây Ninh
Implementation location (Before merge)
Tay Ninh province
8.Construction supervision bidding consultancy
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Construction supervision bidding consultancy
Capital source details
City Budget and Provincial Budget support the goal
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Second quarter, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Tây Ninh City, Tây Ninh
Implementation location (Before merge)
Tay Ninh province
9.Clearing mines and explosives
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Constructions
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Clearing mines and explosives
Capital source details
City Budget and Provincial Budget support the goal
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Second quarter, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Tây Ninh City, Tây Ninh
Implementation location (Before merge)
Tay Ninh province
10.Environmental impact assessment
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Environmental impact assessment
Capital source details
City Budget and Provincial Budget support the goal
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Second quarter, 2025
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Tây Ninh City, Tây Ninh
Implementation location (Before merge)
Tay Ninh province
11.Traffic safety inspection
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Traffic safety inspection
Capital source details
City Budget and Provincial Budget support the goal
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Third quarter, 2026
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Tây Ninh City, Tây Ninh
Implementation location (Before merge)
Tay Ninh province
12.Audit
Tender/ Prequalification Notice ID
Contract execution period
60 days
Domestic/ International
Domestic
Bidding method
Directly
Fields
Consulting
Regulatory compliance
Bidding Law
Tender value
To view full information, please Login or Register
Summary of main tasks of the bid package
Audit
Capital source details
City Budget and Provincial Budget support the goal
Contractor Selection Type
Shortened Direct Contracting
Contractor Selection Method
Single Stage Single Envelope
Contractor Selection Period
Third quarter, 2026
Type of contract
All in One
Prequalification
No
Implementation location (After merge)
Tây Ninh City, Tây Ninh
Implementation location (Before merge)
Tay Ninh province

Utilities for you:

Follow up the contractor selection plan
The Tracking of Contractor Selection Plan helps you to quickly and promptly capture the changes of the Contractor selection plan "Road C (extended Le Duan)". Our software will keep track of the contractor selection plans you have signed up for. When there are any changes, it will immediately send an email notification to you. When the bidding notice of the contractor selection plan appears, the software will also notify you.
Receive similar invitation to bid by email
To be one of the first to receive email notifications of contractor selection plans similar to the "Road C (extended Le Duan)" plan as soon as they are posted, sign up for DauThau.info's VIP 2 plan.
Views: 92

You did not use the site, Click here to remain logged. Timeout: 60 second